Registered Project
Ready (per RERA completion date)The Abode
SITE NO-D-2, KATHA NO-95/95/D-2, RAMANASHREE CALIFORNIA GARDENS, WARD NO-02, Yelahanka, Bengaluru Urban, Karnataka - 560064
- Total Units
- 28
- Floors
- 3
- Towers
- 1
- Total Area
- 0.46 Acres
- Handover
- 30 Jun 2026
RERA progress
Stage 4 of 4 · Handover- RERA applied(completed)
- RERA approved(completed)
- Under construction(completed)
- Handover(current stage)
RERA Approved
15 Jul 2024
PRM/KA/RERA/1251/472/PR/150724/006940
Est. Handover as per RERA
30 Jun 2026
Configurations & unit mix
| 3 BHK | 28 | 14 of 28 | 1,169 – 1,838 sq ft |
|---|
Available from the promoter's RERA report, Q1 2026-27, filed 21 Jul 2026.
The register doesn't list prices, so none are shown here.
Latest quarterly report on the register
Construction progress
Construction complete100%
- Quarter
- Q1 2026-27
- Filed on
- 21 Jul 2026
- Units booked
- 14 of 28
- Units available
- 14
- Reports on file
- 3
Amenities
- Electricity
- CCTV Surveillance
- Community Hall
- Swimming Pool
- Piped Gas
- Water and Sanitation
RERA & approvals
Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/472/PR/150724/006940)
Complaints on the register: 0 recorded on this project; the promoter's count isn't shown here, so check the register
These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.
- RERA registration
- PRM/KA/RERA/1251/472/PR/150724/006940
- Registered as
- THE ABODE
- Acknowledgement no.
- ACK/KA/RERA/1251/472/PR/220524/008169
- Status on the register
- Ongoing
- Stage
- Ready (per RERA completion date)
- Work stage
- 100% complete, Q1 2026-27 report filed 21 Jul 2026
- Sales status
- Ongoing Sales (per RERA QPR Q1 2026-27, as of 21 Jul 2026)
- RERA approved on
- 15 Jul 2024
- Proposed completion
- 30 Jun 2026
- Land area
- 0.46 acres (1,857 sq m)
- Towers (this registration)
- 1
- Floors (this registration)
- 3
- Units (this registration)
- 28
- Plan approved by
- BBMP - Bruhat Bengaluru Mahanagara Palike
- Approved plan no.
- PRJ/8579/23-24
- Plan approval date
- 16 Nov 2023
- Land use
- Residential
Dates on the register
- Completion filed with RERA
- 30 Jun 2026 (Karnataka RERA)
- Latest construction report
- 100% complete, Q1 2026-27, filed 21 Jul 2026 (promoter's report to RERA)
This date has passed. Our copy of the register has no handover dates, so it can't tell you whether homes were delivered. This is the date on the register now, and it may have been extended since registration.
We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.
Documents
Also filed on the register. We open a file here only after checking it for personal or financial details:
- Commencement Certificate
- Water Permission Letter
- Approved Building/Plotting Plan
- Existing Section Plan and Specification
- Sectional Drawing of the apartments
- Project Specifications
- Certificate from Registered Engineer indicating the structural safety of the building
- Proforma of Agreement for Sale
- Proforma of Allotment Letter
- KWSSB/Water
- Approval/NOC under section 109 of KLR Act 1961
- Approval/NOC under section 14 of the KTCP Act
- Fire Force Department
- Airport Authority of India
- KSPCB
- SEIAA
- BSNL
- Lift Authorities
- BMRCL
- NOC in case of building proposals abutting to neighbouring properties
Location
About The Abode
Residential Apartment Comprises of 28 Flats of Different Dimensions
- Project Type
- Residential/Group Housing
- Type
- Apartment
- Status
- Ready (per RERA completion date)
- Total Land
- 0.46 Acres
- No. of Towers
- 1
- No. of Floors
- 3
- Total Units
- 28
- Handover Date
- 30 Jun 2026
- RERA No.
- PRM/KA/RERA/1251/472/PR/150724/006940
- Location
- Yelahanka, Bangalore
The Abode: questions answered
Where is The Abode located?
The Karnataka RERA register places The Abode in Yelahanka, Bengaluru Urban.
What is the RERA number of The Abode?
The Karnataka RERA registration number of The Abode is PRM/KA/RERA/1251/472/PR/150724/006940, approved on 15 Jul 2024.
What completion date was filed for The Abode?
The completion date filed on the register was 30 Jun 2026. Check the register for any extension.
How big is The Abode?
The register lists The Abode with 28 units, 1 tower and about 0.46 acres of land.
What is the latest construction progress of The Abode?
The quarterly report for Q1 2026-27, filed on 21 Jul 2026, shows construction 100% complete and 14 of 28 units booked.
Where does this information about The Abode come from?
From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.
Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.