Surya Valencia Phase I

Residential Apartment Building in Sy No 200/7, 200/9, 200/10, 201/2, 200/11, 201/1, 201/8, 201/7, 201/9 and 201/10 of, Addevishwanathapura Village, Hesaragatta Hobli, Yelahanka, Bengaluru Urban, Karnataka - 560088

Total Units
44
Floors
4
Towers
5
Total Area
3.65 Acres
Handover
31 Dec 2028

RERA progress

Stage 3 of 4 · Under construction
  1. RERA applied(completed)
  2. RERA approved(completed)
  3. Under construction(current stage)
  4. Handover(upcoming)

RERA Approved

17 Dec 2024

PRM/KA/RERA/1251/472/PR/171224/007305

Est. Handover as per RERA

31 Dec 2028

Configurations & unit mix

4 BHK and 5 BHK44

The promoter's RERA report, Q2 2026-27, filed 15 Oct 2026, by its own types and totals, which don't line up with the rows above. Types listed more than once are added together: 5 BHK 7 of 32 available; 4 BHK 4 of 12 available.

The register doesn't list prices, so none are shown here.

Latest quarterly report on the register

Construction progress

Construction complete68%

Quarter
Q2 2026-27
Filed on
15 Oct 2026
Units booked
33 of 44
Units available
11
Reports on file
4

Amenities

  • Electricity
  • Club House
  • Parks

RERA & approvals

Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/472/PR/171224/007305)

Complaints on the register: 0 recorded on this project; 0 on the promoter's record, as shown on this registration

These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.

RERA registration
PRM/KA/RERA/1251/472/PR/171224/007305
Registered as
SURYA VALENCIA Phase I
Promoter
SURYA DEVELOPERS
Acknowledgement no.
ACK/KA/RERA/1251/472/PR/201124/008689
Status on the register
New Project Launch
Stage
Under Construction
Work stage
68% complete, Q2 2026-27 report filed 15 Oct 2026
Sales status
Ongoing Sales (per RERA QPR Q2 2026-27, as of 15 Oct 2026)
RERA approved on
17 Dec 2024
Proposed completion
31 Dec 2028
Land area
3.65 acres (14,770 sq m)
Towers (this registration)
5
Floors (this registration)
4
Units (this registration)
44
Plan approved by
Local Planing Authority
Approved plan no.
DPA/TP/CC/197/24-25
Plan approval date
8 Nov 2024
Land use
Residential

Dates on the register

Completion filed with RERA
31 Dec 2028 (Karnataka RERA)
Latest construction report
68% complete, Q2 2026-27, filed 15 Oct 2026 (promoter's report to RERA)

This is the date on the register now, and it may have been extended since registration.

We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.

Documents

Also filed on the register. We open a file here only after checking it for personal or financial details:

  • Commencement Certificate
  • Electricity Permission Letter
  • Water Permission Letter
  • Approved Building/Plotting Plan
  • Existing Section Plan and Specification
  • Sectional Drawing of the apartments
  • Project Specifications
  • Approved Section Of Building/Infrastructure Plan of Plotting
  • Certificate from Registered Engineer indicating the structural safety of the building
  • Advocate Search Report
  • Change of Land Use
  • Any other document (Rights/Title/Interest/Name)
  • Proforma of Agreement for Sale
  • Proforma of Allotment Letter
  • Declaration (Form B)
  • ESCOM/Electricity
  • KSPCB
  • Relinquishment Deed
  • Form-4 certificate (Chartered Accountant)
  • Form-5 certificate (Architect)

Location

About Surya Valencia Phase I

Residential Dwelling Units/Row Houses/Row Villas

Developer
SURYA DEVELOPERS
Project Type
Residential/Group Housing
Type
Row Houses
Status
Under Construction
Total Land
3.65 Acres
No. of Towers
5
No. of Floors
4
Total Units
44
Handover Date
31 Dec 2028
RERA No.
PRM/KA/RERA/1251/472/PR/171224/007305
Location
Yelahanka, Bangalore

About the developer

SURYA DEVELOPERS

Promoter on the register
SURYA DEVELOPERS
Projects on the register
2
Registering since
2024
Complaints on the promoter
0, as shown on this registration

Surya Valencia Phase I: questions answered

Where is Surya Valencia located?

The Karnataka RERA register places Surya Valencia in Yelahanka, Bengaluru Urban.

What is the RERA number of Surya Valencia?

The Karnataka RERA registration number of Surya Valencia is PRM/KA/RERA/1251/472/PR/171224/007305, approved on 17 Dec 2024.

Who is the promoter of Surya Valencia?

The promoter filed on the Karnataka RERA register is SURYA DEVELOPERS.

When is Surya Valencia expected to be completed?

The proposed completion date filed on the register is 31 Dec 2028.

How big is Surya Valencia?

The register lists Surya Valencia with 44 units, 5 towers and about 3.65 acres of land.

What is the latest construction progress of Surya Valencia?

The quarterly report for Q2 2026-27, filed on 15 Oct 2026, shows construction 68% complete and 33 of 44 units booked.

Where does this information about Surya Valencia come from?

From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.

Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.