Registered Project

sumuk projects

Sumuk Square-2

SY NO-55/5 AND 55/23, KHATHA NO-384/1163/1159/55/5,23, JARAKABANDE KAVAL VILLAGE,YELAHANKA HOBLI, BANGALORE NORTH(ADDL)TALUK,BANGALORE, Yelahanka, Bengaluru Urban, Karnataka - 560098

Total Units
79
Floors
5
Towers
1
Total Area
0.76 Acres
Handover
30 Apr 2029

RERA progress

Stage 3 of 4 · Under construction
  1. RERA applied(completed)
  2. RERA approved(completed)
  3. Under construction(current stage)
  4. Handover(upcoming)

RERA Approved

15 May 2025

PRM/KA/RERA/1251/472/PR/150525/007747

Est. Handover as per RERA

30 Apr 2029

Configurations & unit mix

2BHK AND 3BHK79

The promoter's RERA report, Q2 2026-27, filed 13 Oct 2026, by its own types and totals, which don't line up with the rows above. Types listed more than once are added together: 2 BHK 7 of 21 available; 3 BHK 21 of 58 available.

The register doesn't list prices, so none are shown here.

Latest quarterly report on the register

Construction progress

Construction complete69%

Quarter
Q2 2026-27
Filed on
13 Oct 2026
Units booked
51 of 79
Units available
28
Reports on file
4

Amenities

  • Electricity
  • CCTV Surveillance
  • Outdoor Sports facility
  • Power Backup
  • Water and Sanitation

RERA & approvals

Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/472/PR/150525/007747)

Complaints on the register: 0 recorded on this project; 0 on the promoter's record, as shown on this registration

These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.

RERA registration
PRM/KA/RERA/1251/472/PR/150525/007747
Registered as
SUMUK SQUARE-2
Promoter
sumuk projects
Acknowledgement no.
ACK/KA/RERA/1251/472/PR/180425/009145
Status on the register
New Project Launch
Stage
Under Construction
Work stage
69% complete, Q2 2026-27 report filed 13 Oct 2026
Sales status
Ongoing Sales (per RERA QPR Q2 2026-27, as of 13 Oct 2026)
RERA approved on
15 May 2025
Proposed completion
30 Apr 2029
Land area
0.76 acres (3,059 sq m)
Towers (this registration)
1
Floors (this registration)
5
Units (this registration)
79
Plan approved by
BBMP - Bruhat Bengaluru Mahanagara Palike
Approved plan no.
BBMP/ADDL.DIR/JDNORTH/0032/24-25
Plan approval date
19 Nov 2024
Land use
Residential

Dates on the register

Completion filed with RERA
30 Apr 2029 (Karnataka RERA)
Latest construction report
69% complete, Q2 2026-27, filed 13 Oct 2026 (promoter's report to RERA)

This is the date on the register now, and it may have been extended since registration.

We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.

Documents

Also filed on the register. We open a file here only after checking it for personal or financial details:

  • Approved Building Plan
  • Sectional Drawing of the apartments
  • Certificate from Registered Engineer indicating the structural safety of the building
  • Project Specifications
  • Proforma of Agreement for Sale
  • Proforma of Allotment Letter
  • Declaration (Form B)
  • Advocate Search Report
  • ESCOM/Electricity
  • KWSSB/Water
  • KSPCB
  • Form-4 certificate (Chartered Accountant)
  • Form-5 certificate (Architect)
  • Form-6 certificate (Structural Engineer)

Location

About Sumuk Square-2

RESIDENTIAL PROJECT

Developer
sumuk projects
Project Type
Residential/Group Housing
Type
Apartment
Status
Under Construction
Total Land
0.76 Acres
No. of Towers
1
No. of Floors
5
Total Units
79
Handover Date
30 Apr 2029
RERA No.
PRM/KA/RERA/1251/472/PR/150525/007747
Location
Yelahanka, Bangalore

About the developer

sumuk projects

Promoter on the register
sumuk projects
Projects on the register
1
Registering since
2025
Complaints on the promoter
0, as shown on this registration

Sumuk Square-2: questions answered

Where is Sumuk Square-2 located?

The Karnataka RERA register places Sumuk Square-2 in Yelahanka, Bengaluru Urban.

What is the RERA number of Sumuk Square-2?

The Karnataka RERA registration number of Sumuk Square-2 is PRM/KA/RERA/1251/472/PR/150525/007747, approved on 15 May 2025.

Who is the promoter of Sumuk Square-2?

The promoter filed on the Karnataka RERA register is sumuk projects.

When is Sumuk Square-2 expected to be completed?

The proposed completion date filed on the register is 30 Apr 2029.

How big is Sumuk Square-2?

The register lists Sumuk Square-2 with 79 units, 1 tower and about 0.76 acres of land.

What is the latest construction progress of Sumuk Square-2?

The quarterly report for Q2 2026-27, filed on 13 Oct 2026, shows construction 69% complete and 51 of 79 units booked.

Where does this information about Sumuk Square-2 come from?

From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.

Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.