Skip to main content
PropSarathi

Registered Project

Under Construction

Elara Celestia

Khata No. 239/240/275/88/1 and 240/276/89/1 of ward No. 07, Sy No. 88/1(P),89/1,89/2,90, 1,92/1,93/1,93/2A,93/2B,93/3,93/4,93/5,94/1,/2,94/3.94/4,95/1, 95/2,96/1,96/2,97/1,97/2,97/3,98/1P,98/2,98/3,98/4,99,100/1P,101/1AP,101/1B1,101/2P,101/3P,102/1P,102/2P,102/3P,103,104/1P,104/2,104/3,104/4 of Byatarayanapura Village, Yelahanka, Bengaluru Urban, Karnataka - 560092

Total Units
634
Floors
13
Towers
3
Total Area
10.07 Acres
Handover
31 Mar 2030

RERA progress

Stage 3 of 4 · Under construction
  1. RERA applied(completed)
  2. RERA approved(completed)
  3. Under construction(current stage)
  4. Handover(upcoming)

RERA Approved

10 Mar 2025

PRM/KA/RERA/1251/472/PR/100325/007564

Est. Handover as per RERA

31 Mar 2030

Configurations & unit mix

3BHK466
4BHK - Duplex2
1BHK Special Unit4
3BHK Special Unit3
4BHK144
2BHK Special Unit8
5BHK - Duplex7

The promoter's RERA report, Q2 2026-27, filed 14 Oct 2026, by its own types and totals, which don't line up with the rows above. Types listed more than once are added together: 3BHK L1A 12 of 44 available; 3BHK L2A 6 of 68 available; 3BHK L2C 2 of 28 available; 3BHK S1A 16 of 56 available; 3BHK S1B 15 of 28 available; 3BHK S1D 1 of 24 available; 3BHK XS1 3 of 112 available; 4BHK L1A 2 of 46 available; 4BHK L1B 2 of 12 available; 4BHK S1 1 of 50 available; 4BHK S2 2 of 24 available; 4BHK S2 DU 0 of 1 available; and more.

The register doesn't list prices, so none are shown here.

Latest quarterly report on the register

Construction progress

Construction complete23%

Quarter
Q2 2026-27
Filed on
14 Oct 2026
Units booked
561 of 634
Units available
73
Reports on file
4

Amenities

  • Electricity
  • CCTV Surveillance
  • Club House
  • Outdoor Sports facility
  • Indoor Sports facility
  • Swimming Pool
  • Gym
  • Parks
  • Power Backup
  • Water and Sanitation
  • Air Conditioning

RERA & approvals

Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/472/PR/100325/007564)

Complaints on the register: 1 recorded on this project; the promoter's count isn't shown here, so check the register

These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.

RERA registration
PRM/KA/RERA/1251/472/PR/100325/007564
Registered as
Elara Celestia
Acknowledgement no.
ACK/KA/RERA/1251/472/PR/060225/008929
Status on the register
New Project Launch
Stage
Under Construction
Work stage
23% complete, Q2 2026-27 report filed 14 Oct 2026
Sales status
Ongoing Sales (per RERA QPR Q2 2026-27, as of 14 Oct 2026)
RERA approved on
10 Mar 2025
Proposed completion
31 Mar 2030
Land area
10.07 acres (40,752 sq m)
Towers (this registration)
3
Floors (this registration)
13
Units (this registration)
634
Plan approved by
BBMP - Bruhat Bengaluru Mahanagara Palike
Approved plan no.
BBMP/Addl.Dir/JDNORTH/0105/24-25
Plan approval date
4 Mar 2025
Land use
Residential

Dates on the register

Completion filed with RERA
31 Mar 2030 (Karnataka RERA)
Latest construction report
23% complete, Q2 2026-27, filed 14 Oct 2026 (promoter's report to RERA)

This is the date on the register now, and it may have been extended since registration.

We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.

Documents

Also filed on the register. We open a file here only after checking it for personal or financial details:

  • Commencement Certificate
  • Approved Building Plan
  • Certificate from Registered Engineer indicating the structural safety of the building
  • Project Specifications
  • Relinquishment Deed
  • Proforma of Agreement for Sale
  • Proforma of Allotment Letter
  • Declaration (Form B)
  • Advocate Search Report
  • ESCOM/Electricity
  • KWSSB/Water
  • KSPCB
  • SEIAA
  • Fire Force Department
  • Airport Authority of India
  • BSNL
  • Form-4 certificate (Chartered Accountant)
  • Form-5 certificate (Architect)
  • Form-6 certificate (Structural Engineer)

Location

About Elara Celestia

Residential Apartments with 634 Units

Project Type
Residential/Group Housing
Type
Apartment
Status
Under Construction
Total Land
10.07 Acres
No. of Towers
3
No. of Floors
13
Total Units
634
Handover Date
31 Mar 2030
RERA No.
PRM/KA/RERA/1251/472/PR/100325/007564
Location
Yelahanka, Bangalore

Elara Celestia: questions answered

Where is Elara Celestia located?

The Karnataka RERA register places Elara Celestia in Yelahanka, Bengaluru Urban.

What is the RERA number of Elara Celestia?

The Karnataka RERA registration number of Elara Celestia is PRM/KA/RERA/1251/472/PR/100325/007564, approved on 10 Mar 2025.

When is Elara Celestia expected to be completed?

The proposed completion date filed on the register is 31 Mar 2030.

How big is Elara Celestia?

The register lists Elara Celestia with 634 units, 3 towers and about 10.07 acres of land.

What is the latest construction progress of Elara Celestia?

The quarterly report for Q2 2026-27, filed on 14 Oct 2026, shows construction 23% complete and 561 of 634 units booked.

Where does this information about Elara Celestia come from?

From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.

Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.