Registered Project
Nearing HandoverECLECTIC HARBOUR CREATORS PRIVATE LIMITED
Aurelius
Site no. 858, Khata Number 921/896/858, Yelahanka, Bengaluru Urban, Karnataka - 560065
- Total Units
- 9
- Floors
- 4
- Towers
- 1
- Total Area
- 0.21 Acres
- Handover
- 8 Aug 2027
RERA progress
Stage 2 of 4 · RERA approved- RERA applied(completed)
- RERA approved(current stage)
- Under construction(upcoming)
- Handover(upcoming)
RERA Approved
26 Nov 2024
PRM/KA/RERA/1251/472/PR/261124/007250
Est. Handover as per RERA
8 Aug 2027
Configurations & unit mix
| APARTMENT | 9 |
|---|
The promoter's RERA report, Q2 2026-27, filed 11 Oct 2026, by its own types and totals, which don't line up with the rows above. Types listed more than once are added together: 3 BHK 6 of 8 available; 4 BHK 1 of 1 available.
The register doesn't list prices, so none are shown here.
Latest quarterly report on the register
Construction progress
Construction complete96%
- Quarter
- Q2 2026-27
- Filed on
- 11 Oct 2026
- Units booked
- 2 of 9
- Units available
- 7
- Reports on file
- 4
Amenities
- Electricity
- CCTV Surveillance
- Water and Sanitation
RERA & approvals
Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/472/PR/261124/007250)
Complaints on the register: 0 recorded on this project; 0 on the promoter's record, as shown on this registration
These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.
- RERA registration
- PRM/KA/RERA/1251/472/PR/261124/007250
- Registered as
- AURELIUS
- Promoter
- ECLECTIC HARBOUR CREATORS PRIVATE LIMITED
- Acknowledgement no.
- ACK/KA/RERA/1251/472/PR/190824/008427
- Status on the register
- Ongoing
- Stage
- Nearing Handover
- Work stage
- 96% complete, Q2 2026-27 report filed 11 Oct 2026
- Sales status
- Ongoing Sales (per RERA QPR Q2 2026-27, as of 11 Oct 2026)
- RERA approved on
- 26 Nov 2024
- Proposed completion
- 8 Aug 2027
- Land area
- 0.21 acres (842 sq m)
- Towers (this registration)
- 1
- Floors (this registration)
- 4
- Units (this registration)
- 9
- Plan approved by
- BBMP - Bruhat Bengaluru Mahanagara Palike
- Approved plan no.
- PRJ/11325/23-24
- Plan approval date
- 3 Jul 2024
Dates on the register
- Completion filed with RERA
- 8 Aug 2027 (Karnataka RERA)
- Latest construction report
- 96% complete, Q2 2026-27, filed 11 Oct 2026 (promoter's report to RERA)
This is the date on the register now, and it may have been extended since registration.
We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.
Documents
Also filed on the register. We open a file here only after checking it for personal or financial details:
- Declaration (Form B)
- ESCOM/Electricity
- KWSSB/Water
- Form-4 certificate (Chartered Accountant)
- Form-5 certificate (Architect)
- Form-6 certificate (Structural Engineer)
Location
About Aurelius
Residential Apartment
- Developer
- ECLECTIC HARBOUR CREATORS PRIVATE LIMITED
- Project Type
- Residential/Group Housing
- Type
- Apartment
- Status
- Nearing Handover
- Total Land
- 0.21 Acres
- No. of Towers
- 1
- No. of Floors
- 4
- Total Units
- 9
- Handover Date
- 8 Aug 2027
- RERA No.
- PRM/KA/RERA/1251/472/PR/261124/007250
- Location
- Yelahanka, Bangalore
About the developer
ECLECTIC HARBOUR CREATORS PRIVATE LIMITED
- Promoter on the register
- ECLECTIC HARBOUR CREATORS PRIVATE LIMITED
- Projects on the register
- 1
- Registering since
- 2024
- Complaints on the promoter
- 0, as shown on this registration
Aurelius: questions answered
Where is Aurelius located?
The Karnataka RERA register places Aurelius in Yelahanka, Bengaluru Urban.
What is the RERA number of Aurelius?
The Karnataka RERA registration number of Aurelius is PRM/KA/RERA/1251/472/PR/261124/007250, approved on 26 Nov 2024.
Who is the promoter of Aurelius?
The promoter filed on the Karnataka RERA register is ECLECTIC HARBOUR CREATORS PRIVATE LIMITED.
When is Aurelius expected to be completed?
The proposed completion date filed on the register is 8 Aug 2027.
How big is Aurelius?
The register lists Aurelius with 9 units, 1 tower and about 0.21 acres of land.
What is the latest construction progress of Aurelius?
The quarterly report for Q2 2026-27, filed on 11 Oct 2026, shows construction 96% complete and 2 of 9 units booked.
Where does this information about Aurelius come from?
From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.
Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.