Registered Project

Under Construction

NIRVANA DEVELOPERS

Riviera Uno

Hosakote, Bangalore

Total Units
137
Floors
2
Towers
19
Total Area
12.6 Acres
Handover
31 Jan 2030

RERA progress

Stage 3 of 4 · Under construction
  1. RERA applied(completed)
  2. RERA approved(completed)
  3. Under construction(current stage)
  4. Handover(upcoming)

RERA Approved

6 Feb 2025

PRM/KA/RERA/1250/304/PR/060225/007489

Est. Handover as per RERA

31 Jan 2030

Configurations & unit mix

4 BHK13730 of 1372,499 – 2,524 sq ft

Available from the promoter's RERA report, Q2 2026-27, filed 15 Oct 2026.

The register doesn't list prices, so none are shown here.

Latest quarterly report on the register

Construction progress

Construction complete65%

Quarter
Q2 2026-27
Filed on
15 Oct 2026
Units booked
107 of 137
Units available
30
Reports on file
4

Amenities

  • Electricity
  • CCTV Surveillance
  • Outdoor Sports facility
  • Parks
  • Water and Sanitation

RERA & approvals

Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1250/304/PR/060225/007489)

Complaints on the register: 0 recorded on this project; 0 on the promoter's record, as shown on this registration

These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.

RERA registration
PRM/KA/RERA/1250/304/PR/060225/007489
Registered as
RIVIERA UNO
Promoter
NIRVANA DEVELOPERS
Acknowledgement no.
ACK/KA/RERA/1250/304/PR/230125/008889
Status on the register
New Project Launch
Stage
Under Construction
Work stage
65% complete, Q2 2026-27 report filed 15 Oct 2026
Sales status
Ongoing Sales (per RERA QPR Q2 2026-27, as of 15 Oct 2026)
RERA approved on
6 Feb 2025
Proposed completion
31 Jan 2030
Land area
12.6 acres (50,974 sq m)
Towers (this registration)
19
Floors (this registration)
2
Units (this registration)
137
Plan approved by
Satellite Town Ring Road Planning Authority
Approved plan no.
STRRPA/TP/CC/223-233/2024-25
Plan approval date
9 Jan 2025
Land use
Residential

Dates on the register

Completion filed with RERA
31 Jan 2030 (Karnataka RERA)
Latest construction report
65% complete, Q2 2026-27, filed 15 Oct 2026 (promoter's report to RERA)

This is the date on the register now, and it may have been extended since registration.

We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.

Documents

Also filed on the register. We open a file here only after checking it for personal or financial details:

  • Commencement Certificate
  • Approved Building Plan
  • Sectional Drawing of the apartments
  • Certificate from Registered Engineer indicating the structural safety of the building
  • Project Specifications
  • Relinquishment Deed
  • Proforma of Agreement for Sale
  • Proforma of Allotment Letter
  • Declaration (Form B)
  • Advocate Search Report
  • ESCOM/Electricity
  • KSPCB
  • SEIAA
  • Fire Force Department
  • Airport Authority of India
  • BSNL
  • Lift Authorities
  • BMRCL
  • NOC in case of building proposals abutting to neighbouring properties
  • Bangalore Urban Arts Commission

Location

About Riviera Uno

Row House Development

Developer
NIRVANA DEVELOPERS
Project Type
Residential/Group Housing
Type
Row Houses
Status
Under Construction
Total Land
12.6 Acres
No. of Towers
19
No. of Floors
2
Total Units
137
Handover Date
31 Jan 2030
RERA No.
PRM/KA/RERA/1250/304/PR/060225/007489
Location
Hosakote, Bangalore

About the developer

NIRVANA DEVELOPERS

Promoter on the register
NIRVANA DEVELOPERS
Projects on the register
1
Registering since
2025
Complaints on the promoter
0, as shown on this registration

Riviera Uno: questions answered

Where is Riviera Uno located?

The Karnataka RERA register places Riviera Uno in Hosakote, Bengaluru Rural.

What is the RERA number of Riviera Uno?

The Karnataka RERA registration number of Riviera Uno is PRM/KA/RERA/1250/304/PR/060225/007489, approved on 6 Feb 2025.

Who is the promoter of Riviera Uno?

The promoter filed on the Karnataka RERA register is NIRVANA DEVELOPERS.

When is Riviera Uno expected to be completed?

The proposed completion date filed on the register is 31 Jan 2030.

How big is Riviera Uno?

The register lists Riviera Uno with 137 units, 19 towers and about 12.6 acres of land.

What is the latest construction progress of Riviera Uno?

The quarterly report for Q2 2026-27, filed on 15 Oct 2026, shows construction 65% complete and 107 of 137 units booked.

Where does this information about Riviera Uno come from?

From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.

Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.