Registered Project
Under ConstructionVARASINDURI PROPERTIES
Rings Avenue
Hosakote, Bangalore
- Total Units
- 144
- Floors
- 3
- Towers
- 2
- Total Area
- 1.67 Acres
- Handover
- 31 Mar 2029
RERA progress
Stage 3 of 4 · Under construction- RERA applied(completed)
- RERA approved(completed)
- Under construction(current stage)
- Handover(upcoming)
RERA Approved
28 Mar 2025
PRM/KA/RERA/1250/304/PR/280325/007637
Est. Handover as per RERA
31 Mar 2029
Configurations & unit mix
| 2 BHK | 112 | 56 of 112 | 578 – 687 sq ft |
|---|---|---|---|
| 3 BHK | 32 | 13 of 32 | 814 – 886 sq ft |
Available from the promoter's RERA report, Q2 2026-27, filed 15 Oct 2026.
The register doesn't list prices, so none are shown here.
Latest quarterly report on the register
Construction progress
Construction complete85%
- Quarter
- Q2 2026-27
- Filed on
- 15 Oct 2026
- Units booked
- 75 of 144
- Units available
- 69
- Reports on file
- 4
Amenities
- Electricity
- Power Backup
RERA & approvals
Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1250/304/PR/280325/007637)
Complaints on the register: 0 recorded on this project; 0 on the promoter's record, as shown on this registration
These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.
- RERA registration
- PRM/KA/RERA/1250/304/PR/280325/007637
- Registered as
- RINGS AVENUE
- Promoter
- VARASINDURI PROPERTIES
- Acknowledgement no.
- ACK/KA/RERA/1250/304/PR/260125/008897
- Status on the register
- New Project Launch
- Stage
- Under Construction
- Work stage
- 85% complete, Q2 2026-27 report filed 15 Oct 2026
- Sales status
- Ongoing Sales (per RERA QPR Q2 2026-27, as of 15 Oct 2026)
- RERA approved on
- 28 Mar 2025
- Proposed completion
- 31 Mar 2029
- Land area
- 1.67 acres (6,778 sq m)
- Towers (this registration)
- 2
- Floors (this registration)
- 3
- Units (this registration)
- 144
- Plan approved by
- Hoskote Planning Authority
- Approved plan no.
- HOPA/CC/141/2024-25
- Plan approval date
- 18 Dec 2024
- Land use
- Residential
Dates on the register
- Completion filed with RERA
- 31 Mar 2029 (Karnataka RERA)
- Latest construction report
- 85% complete, Q2 2026-27, filed 15 Oct 2026 (promoter's report to RERA)
This is the date on the register now, and it may have been extended since registration.
We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.
Documents
Also filed on the register. We open a file here only after checking it for personal or financial details:
- Commencement Certificate
- Approved Building Plan
- Sectional Drawing of the apartments
- Certificate from Registered Engineer indicating the structural safety of the building
- Project Specifications
- Proforma of Agreement for Sale
- Proforma of Allotment Letter
- Declaration (Form B)
- ESCOM/Electricity
- KWSSB/Water
- KSPCB
- Form-4 certificate (Chartered Accountant)
- Form-5 certificate (Architect)
- Form-6 certificate (Structural Engineer)
Location
About Rings Avenue
RESIDENTIAL DEVELOPMENT
- Developer
- VARASINDURI PROPERTIES
- Project Type
- Residential/Group Housing
- Type
- Apartment
- Status
- Under Construction
- Total Land
- 1.67 Acres
- No. of Towers
- 2
- No. of Floors
- 3
- Total Units
- 144
- Handover Date
- 31 Mar 2029
- RERA No.
- PRM/KA/RERA/1250/304/PR/280325/007637
- Location
- Hosakote, Bangalore
About the developer
VARASINDURI PROPERTIES
- Promoter on the register
- VARASINDURI PROPERTIES
- Projects on the register
- 2
- Registering since
- 2025
- Complaints on the promoter
- 0, as shown on this registration
Rings Avenue: questions answered
Where is Rings Avenue located?
The Karnataka RERA register places Rings Avenue in Hosakote, Bengaluru Rural.
What is the RERA number of Rings Avenue?
The Karnataka RERA registration number of Rings Avenue is PRM/KA/RERA/1250/304/PR/280325/007637, approved on 28 Mar 2025.
Who is the promoter of Rings Avenue?
The promoter filed on the Karnataka RERA register is VARASINDURI PROPERTIES.
When is Rings Avenue expected to be completed?
The proposed completion date filed on the register is 31 Mar 2029.
How big is Rings Avenue?
The register lists Rings Avenue with 144 units, 2 towers and about 1.67 acres of land.
What is the latest construction progress of Rings Avenue?
The quarterly report for Q2 2026-27, filed on 15 Oct 2026, shows construction 85% complete and 75 of 144 units booked.
Where does this information about Rings Avenue come from?
From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.
Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.