Registered Project
Under ConstructionNEXON BUILDERS
Nexon Travenza
Sy. No. 90(P), Poojena Agrahara Village, Sy. No. 78/2, 78/4, 78/6, 80/3, 81/1, 81/2, 81/4, 82/6, 82/8 & 82/10 Doddagattiganabbe Village, Kasaba Hobli, Hosakote, Bengaluru Rural, Karnataka - 562114
- Total Plots
- 83
- Total Area
- 5.61 Acres
- Handover
- 31 Dec 2031
RERA progress
Stage 3 of 4 · Under construction- RERA applied(completed)
- RERA approved(completed)
- Under construction(current stage)
- Handover(upcoming)
RERA Approved
20 Sep 2025
PRM/KA/RERA/1250/304/PR/200925/008109
Est. Handover as per RERA
31 Dec 2031
Configurations & unit mix
| 9.14 × 12.15 m | 22 | about 1,200 sq ft each |
|---|---|---|
| 9.14 × 18.29 m | 5 | about 1,800 sq ft each |
| Odd Sites | 34 | about 1,849 sq ft each |
| 9.14 × 15.24 m | 22 | about 1,499 sq ft each |
The register doesn't list prices, so none are shown here.
Latest quarterly report on the register
Construction progress
Construction complete30%
- Quarter
- Q2 2026-27
- Filed on
- 14 Oct 2026
- Reports on file
- 4
RERA & approvals
Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1250/304/PR/200925/008109)
Complaints on the register: 0 recorded on this project; 0 on the promoter's record, as shown on this registration
These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.
- RERA registration
- PRM/KA/RERA/1250/304/PR/200925/008109
- Registered as
- NEXON TRAVENZA
- Promoter
- NEXON BUILDERS
- Acknowledgement no.
- ACK/KA/RERA/1250/304/PR/310525/009279
- Status on the register
- Ongoing
- Stage
- Under Construction
- Work stage
- 30% complete, Q2 2026-27 report filed 14 Oct 2026
- RERA approved on
- 20 Sept 2025
- Proposed completion
- 31 Dec 2031
- Land area
- 5.61 acres (22,713 sq m)
- Plots (this registration)
- 83
- Plan approved by
- Satellite Town Ring Road Planning Authority
- Approved plan no.
- STRRPA/TP/LAO/08/24-25
- Plan approval date
- 19 Apr 2025
- Land use
- Residential
Dates on the register
- Completion filed with RERA
- 31 Dec 2031 (Karnataka RERA)
- Latest construction report
- 30% complete, Q2 2026-27, filed 14 Oct 2026 (promoter's report to RERA)
This is the date on the register now, and it may have been extended since registration.
We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.
Documents
Also filed on the register. We open a file here only after checking it for personal or financial details:
- Form-4 certificate (Chartered Accountant)
- Form-6 certificate (Structural Engineer)
Location
About Nexon Travenza
Plotted Development
- Developer
- NEXON BUILDERS
- Project Type
- Plotted Development
- Type
- Plotted Development
- Status
- Under Construction
- Total Land
- 5.61 Acres
- Total Plots
- 83
- Handover Date
- 31 Dec 2031
- RERA No.
- PRM/KA/RERA/1250/304/PR/200925/008109
- Location
- Hosakote, Bangalore
About the developer
NEXON BUILDERS
- Promoter on the register
- NEXON BUILDERS
- Projects on the register
- 1
- Registering since
- 2025
- Complaints on the promoter
- 0, as shown on this registration
Nexon Travenza: questions answered
Where is Nexon Travenza located?
The Karnataka RERA register places Nexon Travenza in Hosakote, Bengaluru Rural.
What is the RERA number of Nexon Travenza?
The Karnataka RERA registration number of Nexon Travenza is PRM/KA/RERA/1250/304/PR/200925/008109, approved on 20 Sept 2025.
Who is the promoter of Nexon Travenza?
The promoter filed on the Karnataka RERA register is NEXON BUILDERS.
When is Nexon Travenza expected to be completed?
The proposed completion date filed on the register is 31 Dec 2031.
How big is Nexon Travenza?
The register lists Nexon Travenza with 83 plots and about 5.61 acres of land.
What is the latest construction progress of Nexon Travenza?
The quarterly report for Q2 2026-27, filed on 14 Oct 2026, shows construction 30% complete.
Where does this information about Nexon Travenza come from?
From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.
Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.