Nexon Celestials

Sy No 82/20, 84/3, 91/2, 92/1, 92/2, 92/9, 92/10, 93/3 and 93/4 of Bhaktarahalli Village, Kasaba Hobli, Hosakote, Bengaluru Rural, Karnataka - 562114

Total Plots
76
Total Area
5.55 Acres
Handover
31 Dec 2029

RERA progress

Stage 3 of 4 · Under construction
  1. RERA applied(completed)
  2. RERA approved(completed)
  3. Under construction(current stage)
  4. Handover(upcoming)

RERA Approved

14 Oct 2025

PRM/KA/RERA/1250/304/PR/141025/008165

Est. Handover as per RERA

31 Dec 2029

Configurations & unit mix

9.14 × 16.76 m9about 1,648 sq ft each
9.14 × 15.24 m37about 1,616 sq ft each
ODD SITES24about 6,542 sq ft each
9.14 × 17.16 m6about 1,688 sq ft each

The register doesn't list prices, so none are shown here.

Latest quarterly report on the register

Construction progress

Construction complete95%

Quarter
Q2 2026-27
Filed on
14 Oct 2026
Reports on file
4

RERA & approvals

Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1250/304/PR/141025/008165)

Complaints on the register: 0 recorded on this project; 0 on the promoter's record, as shown on this registration

These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.

RERA registration
PRM/KA/RERA/1250/304/PR/141025/008165
Registered as
NEXON CELESTIALS
Promoter
NEXON BUILDERS AND DEVELOPERS
Acknowledgement no.
ACK/KA/RERA/1250/304/PR/190925/009636
Status on the register
Ongoing
Stage
Under Construction
Work stage
95% complete, Q2 2026-27 report filed 14 Oct 2026
RERA approved on
14 Oct 2025
Proposed completion
31 Dec 2029
Land area
5.55 acres (22,459 sq m)
Plots (this registration)
76
Plan approved by
Satellite Town Ring Road Planning Authority
Approved plan no.
STRRPA/TP/LAO/04/24-25
Plan approval date
8 Jul 2023
Land use
Residential

Dates on the register

Completion filed with RERA
31 Dec 2029 (Karnataka RERA)
Latest construction report
95% complete, Q2 2026-27, filed 14 Oct 2026 (promoter's report to RERA)

This is the date on the register now, and it may have been extended since registration.

We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.

Documents

Also filed on the register. We open a file here only after checking it for personal or financial details:

  • Approval Layout Order / Technical Sanction Letter
  • Approved Layout Plan/Demarcation Plan
  • Project Specifications
  • Brochure
  • Relinquishment Deed
  • Proforma of Agreement for Sale
  • Proforma of Allotment Letter
  • Advocate Search Report
  • NOC from ESCOMs
  • NOC for Water
  • KSPCB (If Applicable)
  • SEIAA (If Applicable)
  • Form-4 certificate (Chartered Accountant)
  • Form-6 certificate (Structural Engineer)

Location

About Nexon Celestials

We Construct Plotted Development

Developer
NEXON BUILDERS AND DEVELOPERS
Project Type
Plotted Development
Type
Plotted Development
Status
Under Construction
Total Land
5.55 Acres
Total Plots
76
Handover Date
31 Dec 2029
RERA No.
PRM/KA/RERA/1250/304/PR/141025/008165
Location
Hosakote, Bangalore

About the developer

NEXON BUILDERS AND DEVELOPERS

Promoter on the register
NEXON BUILDERS AND DEVELOPERS
Projects on the register
1
Registering since
2025
Complaints on the promoter
0, as shown on this registration

Nexon Celestials: questions answered

Where is Nexon Celestials located?

The Karnataka RERA register places Nexon Celestials in Hosakote, Bengaluru Rural.

What is the RERA number of Nexon Celestials?

The Karnataka RERA registration number of Nexon Celestials is PRM/KA/RERA/1250/304/PR/141025/008165, approved on 14 Oct 2025.

Who is the promoter of Nexon Celestials?

The promoter filed on the Karnataka RERA register is NEXON BUILDERS AND DEVELOPERS.

When is Nexon Celestials expected to be completed?

The proposed completion date filed on the register is 31 Dec 2029.

How big is Nexon Celestials?

The register lists Nexon Celestials with 76 plots and about 5.55 acres of land.

What is the latest construction progress of Nexon Celestials?

The quarterly report for Q2 2026-27, filed on 14 Oct 2026, shows construction 95% complete.

Where does this information about Nexon Celestials come from?

From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.

Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.