Registered Project
Ready (per RERA completion date)Jupiter Homes
JUPITER HOMES,KATHA NO.839/11/3,SY NO.11/3,OF SAMETHANAHALLI VILLAGE,ANUGONDANALLI HOBLI,HOSKOTE TALUK,BANGALORE RURAL DISTRICT, JUPITER HOMES,KATHA NO.839/11/3,SY NO.11/3,OF SAMETHANAHALLI VILLAGE,ANUGONDANALLI HOBLI,HOSKOTE TALUK,BANGALORE RURAL DISTRICT, Hosakote, Bengaluru Rural, Karnataka - 560067
- Total Units
- 180
- Floors
- 3
- Towers
- 1
- Total Area
- 1.8 Acres
- Handover
- 15 May 2024
RERA progress
Stage 4 of 4 · Handover- RERA applied(completed)
- RERA approved(completed)
- Under construction(completed)
- Handover(current stage)
RERA Approved
19 Jul 2022
PRM/KA/RERA/1250/304/PR/190722/005080
Est. Handover as per RERA
15 May 2024
Configurations & unit mix
| 2BHK | 180 | 592 – 646 sq ft |
|---|
The register doesn't list prices, so none are shown here.
Amenities
- Electricity
- CCTV Surveillance
- Community Hall
- Outdoor Sports facility
- Indoor Sports facility
- Swimming Pool
- Gym
- Parks
- Power Backup
- Water and Sanitation
RERA & approvals
Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1250/304/PR/190722/005080)
Complaints on the register: 0 recorded on this project; the promoter's count isn't shown here, so check the register
These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.
- RERA registration
- PRM/KA/RERA/1250/304/PR/190722/005080
- Registered as
- JUPITER HOMES
- Acknowledgement no.
- ACK/KA/RERA/1250/304/PR/230322/005795
- Status on the register
- Ongoing
- Stage
- Ready (per RERA completion date)
- RERA approved on
- 19 Jul 2022
- Proposed completion
- 15 May 2024
- Land area
- 1.8 acres (7,286 sq m)
- Towers (this registration)
- 1
- Floors (this registration)
- 3
- Units (this registration)
- 180
- Plan approved by
- Local Planing Authority
- Approved plan no.
- STRRPA/TP/CC/458/2018-19
- Plan approval date
- 10 Jan 2019
- Land use
- Residential
Dates on the register
- Completion filed with RERA
- 15 May 2024 (Karnataka RERA)
This date has passed. Our copy of the register has no handover dates, so it can't tell you whether homes were delivered. This is the date on the register now, and it may have been extended since registration.
We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.
Documents
Also filed on the register. We open a file here only after checking it for personal or financial details:
- Commencement Certificate
- Water Permission Letter
- Approved Layout Plan
- Approved Building/Plotting Plan
- Existing Layout Plan
- Existing Section Plan and Specification
- Sectional Drawing of the apartments
- Project Specifications
- Approved Section Of Building/Infrastructure Plan of Plotting
- Certificate from Registered Engineer indicating the structural safety of the building
- Change of Land Use
- Conversion Certificate under section 95 of the KLR Act 1964
- Proforma of Agreement for Sale
- Brochure
- KWSSB/Water
- KSPCB
- SEIAA
Location
About Jupiter Homes
Residential Apartment Building Consisting of 180 units with Amenities
- Project Type
- Residential/Group Housing
- Type
- Apartment
- Status
- Ready (per RERA completion date)
- Total Land
- 1.8 Acres
- No. of Towers
- 1
- No. of Floors
- 3
- Total Units
- 180
- Handover Date
- 15 May 2024
- RERA No.
- PRM/KA/RERA/1250/304/PR/190722/005080
- Location
- Hosakote, Bangalore
Jupiter Homes: questions answered
Where is Jupiter Homes located?
The Karnataka RERA register places Jupiter Homes in Hosakote, Bengaluru Rural.
What is the RERA number of Jupiter Homes?
The Karnataka RERA registration number of Jupiter Homes is PRM/KA/RERA/1250/304/PR/190722/005080, approved on 19 Jul 2022.
What completion date was filed for Jupiter Homes?
The completion date filed on the register was 15 May 2024. Check the register for any extension.
How big is Jupiter Homes?
The register lists Jupiter Homes with 180 units, 1 tower and about 1.8 acres of land.
Where does this information about Jupiter Homes come from?
From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.
Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.