Registered Project
DS-MAX Properties Private Limited
Sky Fields
Hosakote, Bangalore
- Total Units
- 870
- Floors
- 14
- Towers
- 1
- Total Area
- 4.94 Acres
- Handover
- 30 Sept 2030
RERA progress
Stage 3 of 4 · Under construction- RERA applied(completed)
- RERA approved(completed)
- Under construction(current stage)
- Handover(upcoming)
RERA Approved
25 Oct 2024
PRM/KA/RERA/1250/304/PR/251024/007179
Est. Handover as per RERA
30 Sep 2030
Developer target: 30 Sept 2030
Configurations & unit mix
| 2 BHK | 454 | 333 of 454 | 647 – 741 sq ft |
|---|---|---|---|
| 3 BHK | 416 | 292 of 416 | 745 – 1,023 sq ft |
Available from the promoter's RERA report, Q2 2026-27, filed 13 Oct 2026.
The register doesn't list prices, so none are shown here.
Latest quarterly report on the register
Construction progress
Construction complete38%
- Quarter
- Q2 2026-27
- Filed on
- 13 Oct 2026
- Units booked
- 245 of 870
- Units available
- 625
- Reports on file
- 4
Amenities
- Electricity
- CCTV Surveillance
- Community Hall
- Outdoor Sports facility
- Indoor Sports facility
- Swimming Pool
- Gym
- Parks
- Power Backup
- Water and Sanitation
RERA & approvals
Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1250/304/PR/251024/007179)
Complaints on the register: 1 recorded on this project; 19 on the promoter's record, as shown on this registration
These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.
- RERA registration
- PRM/KA/RERA/1250/304/PR/251024/007179
- Registered as
- DS MAX SKY FIELDS
- Promoter
- DS-MAX Properties Private Limited
- Acknowledgement no.
- ACK/KA/RERA/1250/304/PR/081024/008573
- Status on the register
- New Project Launch
- Stage
- Under Construction
- Work stage
- 38% complete, Q2 2026-27 report filed 13 Oct 2026
- Sales status
- Ongoing Sales (per RERA QPR Q2 2026-27, as of 13 Oct 2026)
- RERA approved on
- 25 Oct 2024
- Proposed completion
- 30 Sept 2030
- Land area
- 4.94 acres (20,006 sq m)
- Towers (this registration)
- 1
- Floors (this registration)
- 14
- Units (this registration)
- 870
- Plan approved by
- Local Planing Authority
- Approved plan no.
- STRRPA/TP/CC/439/23-24
- Plan approval date
- 6 Jul 2024
- Land use
- Residential
Dates on the register
- Completion filed with RERA
- 30 Sep 2030 (Karnataka RERA)
- Latest construction report
- 38% complete, Q2 2026-27, filed 13 Oct 2026 (promoter's report to RERA)
This is the date on the register now, and it may have been extended since registration.
We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.
Documents
Also filed on the register. We open a file here only after checking it for personal or financial details:
- Commencement Certificate
- Electricity Permission Letter
- Water Permission Letter
- Approved Building/Plotting Plan
- Existing Section Plan and Specification
- Sectional Drawing of the apartments
- Project Specifications
- Approved Section Of Building/Infrastructure Plan of Plotting
- Area Development Plan Of Project Area
- Certificate from Registered Engineer indicating the structural safety of the building
- Advocate Search Report
- Any other document (Rights/Title/Interest/Name)
- Proforma of Agreement for Sale
- Proforma of Allotment Letter
- Declaration (Form B)
- ESCOM/Electricity
- KWSSB/Water
- Approval/NOC under section 109 of KLR Act 1961
- Approval/NOC under section 14 of the KTCP Act
- Fire Force Department
Location
About Sky Fields
Residential Group housing
- Developer
- DS-MAX Properties Private Limited
- Project Type
- Residential/Group Housing
- Type
- Apartment
- Status
- Under Construction
- Total Land
- 4.94 Acres
- No. of Towers
- 1
- No. of Floors
- 14
- Total Units
- 870
- Handover Date
- 30 Sept 2030
- RERA No.
- PRM/KA/RERA/1250/304/PR/251024/007179
- Location
- Hosakote, Bangalore
About the developer
DS-MAX Properties Private Limited
- Promoter on the register
- DS-MAX Properties Private Limited
- Projects on the register
- 44
- Registering since
- 2017
- Complaints on the promoter
- 19, as shown on this registration
Sky Fields: questions answered
Where is Sky Fields located?
The Karnataka RERA register places Sky Fields in Hosakote, Bengaluru Rural.
What is the RERA number of Sky Fields?
The Karnataka RERA registration number of Sky Fields is PRM/KA/RERA/1250/304/PR/251024/007179, approved on 25 Oct 2024.
Who is the promoter of Sky Fields?
The promoter filed on the Karnataka RERA register is DS-MAX Properties Private Limited.
When is Sky Fields expected to be completed?
The proposed completion date filed on the register is 30 Sept 2030.
How big is Sky Fields?
The register lists Sky Fields with 870 units, 1 tower and about 4.94 acres of land.
What is the latest construction progress of Sky Fields?
The quarterly report for Q2 2026-27, filed on 13 Oct 2026, shows construction 38% complete and 245 of 870 units booked.
Where does this information about Sky Fields come from?
From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.
Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.