Skip to main content
PropSarathi

Registered Project

Nearing Handover

DAIWIK SHELTERS PRIVATE LIMITED

Daiwik Sayuri

SY.NO. 67/1,67/2,67/3,67/4,67/5,69/1,69/2,69/3,69/4,70/1,70/2,70/3,71/1,72/3,72/4,74/2,75/1,75/2,75/14 AND 75/15, BODHANAHOSAHALLI VILLAGE, ANUGONDANAHALLI HOBLI, HOSAKOTE TALUK, BENGALURU RURAL DISTRICT, Hosakote, Bengaluru Rural, Karnataka - 560067

Total Plots
211
Total Area
13.66 Acres
Handover
1 Dec 2026

RERA progress

Stage 2 of 4 · RERA approved
  1. RERA applied(completed)
  2. RERA approved(current stage)
  3. Under construction(upcoming)
  4. Handover(upcoming)

RERA Approved

29 May 2025

PRM/KA/RERA/1250/304/PR/290525/007791

Est. Handover as per RERA

1 Dec 2026

Configurations & unit mix

ODD SITE50about 1,604 sq ft each
ODD SITE6about 2,946 sq ft each
9.00m x 18.00m5about 349 sq ft each
9.00m x 12.00m57about 20 sq ft each
9.00m x 15.00m93about 16 sq ft each

The register doesn't list prices, so none are shown here.

Latest quarterly report on the register

Construction progress

Construction complete95%

Quarter
Q1 2026-27
Filed on
15 Jul 2026
Reports on file
3

RERA & approvals

Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1250/304/PR/290525/007791)

Complaints on the register: 0 recorded on this project; 0 on the promoter's record, as shown on this registration

These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.

RERA registration
PRM/KA/RERA/1250/304/PR/290525/007791
Registered as
DAIWIK SAYURI
Promoter
DAIWIK SHELTERS PRIVATE LIMITED
Acknowledgement no.
ACK/KA/RERA/1250/304/PR/270325/009081
Status on the register
Ongoing
Stage
Nearing Handover
Work stage
95% complete, Q1 2026-27 report filed 15 Jul 2026
RERA approved on
29 May 2025
Proposed completion
1 Dec 2026
Land area
13.66 acres (55,289 sq m)
Plots (this registration)
211
Plan approved by
Satellite Town Ring Road Planning Authority
Approved plan no.
STRRPA/TP/LAO/12/2024-25
Plan approval date
9 Dec 2024
Land use
Residential

Dates on the register

Completion filed with RERA
1 Dec 2026 (Karnataka RERA)
Latest construction report
95% complete, Q1 2026-27, filed 15 Jul 2026 (promoter's report to RERA)

This is the date on the register now, and it may have been extended since registration.

We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.

Documents

Also filed on the register. We open a file here only after checking it for personal or financial details:

  • Approval Layout Order / Technical Sanction Letter
  • Approved Layout Plan/Demarcation Plan
  • Project Specifications
  • Brochure
  • Relinquishment Deed
  • Proforma of Agreement for Sale
  • Proforma of Allotment Letter
  • Declaration (Form B)
  • Advocate Search Report
  • NOC for Water
  • Form-4 certificate (Chartered Accountant)
  • Form-6 certificate (Structural Engineer)

Location

About Daiwik Sayuri

Residential Plotted development with plots of various dimensions

Developer
DAIWIK SHELTERS PRIVATE LIMITED
Project Type
Plotted Development
Type
Plotted Development
Status
Nearing Handover
Total Land
13.66 Acres
Total Plots
211
Handover Date
1 Dec 2026
RERA No.
PRM/KA/RERA/1250/304/PR/290525/007791
Location
Hosakote, Bangalore

About the developer

DAIWIK SHELTERS PRIVATE LIMITED

Promoter on the register
DAIWIK SHELTERS PRIVATE LIMITED
Projects on the register
1
Registering since
2025
Complaints on the promoter
0, as shown on this registration

Daiwik Sayuri: questions answered

Where is Daiwik Sayuri located?

The Karnataka RERA register places Daiwik Sayuri in Hosakote, Bengaluru Rural.

What is the RERA number of Daiwik Sayuri?

The Karnataka RERA registration number of Daiwik Sayuri is PRM/KA/RERA/1250/304/PR/290525/007791, approved on 29 May 2025.

Who is the promoter of Daiwik Sayuri?

The promoter filed on the Karnataka RERA register is DAIWIK SHELTERS PRIVATE LIMITED.

When is Daiwik Sayuri expected to be completed?

The proposed completion date filed on the register is 1 Dec 2026.

How big is Daiwik Sayuri?

The register lists Daiwik Sayuri with 211 plots and about 13.66 acres of land.

What is the latest construction progress of Daiwik Sayuri?

The quarterly report for Q1 2026-27, filed on 15 Jul 2026, shows construction 95% complete.

Where does this information about Daiwik Sayuri come from?

From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.

Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.