Registered Project

Under Construction

VIJAYASRI VIJETHA INFRA PROJECTS

Carpe Diem

Sy No 10/2, 10/3, 190 and 191/1 of Kolaturu Village, Kasaba Hobli, Hosakote, Bengaluru Rural, Karnataka - 562114

Total Plots
125
Total Area
7.87 Acres
Handover
31 Dec 2027

RERA progress

Stage 3 of 4 · Under construction
  1. RERA applied(completed)
  2. RERA approved(completed)
  3. Under construction(current stage)
  4. Handover(upcoming)

RERA Approved

8 May 2025

PRM/KA/RERA/1250/304/PR/080525/007729

Est. Handover as per RERA

31 Dec 2027

Configurations & unit mix

9X15M30about 1,453 sq ft each
9X12.19M23about 1,181 sq ft each
Odd Sites50about 1,638 sq ft each
9X15.24M3about 1,475 sq ft each
9X13.77M14about 1,334 sq ft each
12.19X15M1about 1,970 sq ft each
12.19X12.19M4about 1,598 sq ft each

The register doesn't list prices, so none are shown here.

Latest quarterly report on the register

Construction progress

Construction complete100%

Quarter
Q2 2026-27
Filed on
15 Oct 2026
Reports on file
4

RERA & approvals

Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1250/304/PR/080525/007729)

Complaints on the register: 0 recorded on this project; 0 on the promoter's record, as shown on this registration

These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.

RERA registration
PRM/KA/RERA/1250/304/PR/080525/007729
Registered as
CARPE DIEM
Promoter
VIJAYASRI VIJETHA INFRA PROJECTS
Acknowledgement no.
ACK/KA/RERA/1250/304/PR/120425/009124
Status on the register
Ongoing
Stage
Under Construction
Work stage
100% complete, Q2 2026-27 report filed 15 Oct 2026
RERA approved on
8 May 2025
Proposed completion
31 Dec 2027
Land area
7.87 acres (31,869 sq m)
Plots (this registration)
125
Plan approved by
Hoskote Planning Authority
Approved plan no.
HPA/LAO/36/2024-25/3219
Plan approval date
12 Mar 2025
Land use
Residential

Dates on the register

Completion filed with RERA
31 Dec 2027 (Karnataka RERA)
Latest construction report
100% complete, Q2 2026-27, filed 15 Oct 2026 (promoter's report to RERA)

This is the date on the register now, and it may have been extended since registration.

We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.

Documents

Also filed on the register. We open a file here only after checking it for personal or financial details:

  • Approval Layout Order / Technical Sanction Letter
  • Approved Layout Plan/Demarcation Plan
  • Project Specifications
  • Relinquishment Deed
  • Proforma of Agreement for Sale
  • Proforma of Allotment Letter
  • NOC from ESCOMs
  • NOC for Water
  • KSPCB (If Applicable)
  • SEIAA (If Applicable)
  • Form-4 certificate (Chartered Accountant)
  • Form-6 certificate (Structural Engineer)

Location

About Carpe Diem

Development of Residential Layout of 125 Plots situated at Sy No 10/2, 10/3, 190 and 191/1 of Kolaturu Village, Kasaba Hobli, Hoskote Taluk, Bengaluru Rural District, Karnataka – 562114

Developer
VIJAYASRI VIJETHA INFRA PROJECTS
Project Type
Plotted Development
Type
Plotted Development
Status
Under Construction
Total Land
7.87 Acres
Total Plots
125
Handover Date
31 Dec 2027
RERA No.
PRM/KA/RERA/1250/304/PR/080525/007729
Location
Hosakote, Bangalore

About the developer

VIJAYASRI VIJETHA INFRA PROJECTS

Promoter on the register
VIJAYASRI VIJETHA INFRA PROJECTS
Projects on the register
1
Registering since
2025
Complaints on the promoter
0, as shown on this registration

Carpe Diem: questions answered

Where is Carpe Diem located?

The Karnataka RERA register places Carpe Diem in Hosakote, Bengaluru Rural.

What is the RERA number of Carpe Diem?

The Karnataka RERA registration number of Carpe Diem is PRM/KA/RERA/1250/304/PR/080525/007729, approved on 8 May 2025.

Who is the promoter of Carpe Diem?

The promoter filed on the Karnataka RERA register is VIJAYASRI VIJETHA INFRA PROJECTS.

When is Carpe Diem expected to be completed?

The proposed completion date filed on the register is 31 Dec 2027.

How big is Carpe Diem?

The register lists Carpe Diem with 125 plots and about 7.87 acres of land.

What is the latest construction progress of Carpe Diem?

The quarterly report for Q2 2026-27, filed on 15 Oct 2026, shows construction 100% complete.

Where does this information about Carpe Diem come from?

From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.

Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.