Registered Project
Ready (per RERA completion date)Bodhii Tree
Sy No.193/1, 193/2, 193/5, 193/6 and 193/7, situated at Thavarekere Village, Nandagudi Hobli, Hoskote Taluk, Bangalore Rural District- 562122, Hosakote, Bengaluru Rural, Karnataka - 562122
- Total Plots
- 109
- Total Area
- 7.22 Acres
- Handover
- 30 Dec 2025
RERA progress
Stage 4 of 4 · Handover- RERA applied(completed)
- RERA approved(completed)
- Under construction(completed)
- Handover(current stage)
RERA Approved
21 Mar 2024
PRM/KA/RERA/1250/304/PR/210324/006723
Est. Handover as per RERA
30 Dec 2025
Configurations & unit mix
| ODD Sites | 61 | about 1,637 sq ft each |
|---|---|---|
| 9.00 × 13.50 m | 5 | about 1,307 sq ft each |
| 9.00 × 15.00 m | 35 | about 1,453 sq ft each |
| 9.00 × 12.00 m | 6 | about 1,163 sq ft each |
| Commercial ODD Sites | 2 | about 4,225 sq ft each |
The register doesn't list prices, so none are shown here.
Latest quarterly report on the register
Construction progress
Construction complete100%
- Quarter
- Q3 2025-26
- Filed on
- 19 Feb 2026
RERA & approvals
Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1250/304/PR/210324/006723)
Complaints on the register: 0 recorded on this project; the promoter's count isn't shown here, so check the register
These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.
- RERA registration
- PRM/KA/RERA/1250/304/PR/210324/006723
- Registered as
- BODHII TREE
- Acknowledgement no.
- ACK/KA/RERA/1250/304/PR/260224/007890
- Status on the register
- New Project Launch
- Stage
- Ready (per RERA completion date)
- Work stage
- 100% complete, Q3 2025-26 report filed 19 Feb 2026
- RERA approved on
- 21 Mar 2024
- Proposed completion
- 30 Dec 2025
- Land area
- 7.22 acres (29,238 sq m)
- Plots (this registration)
- 109
- Plan approved by
- Local Planing Authority
- Approved plan no.
- LAO/07/2023-24
- Plan approval date
- 19 Dec 2023
- Land use
- Residential
Dates on the register
- Completion filed with RERA
- 30 Dec 2025 (Karnataka RERA)
- Latest construction report
- 100% complete, Q3 2025-26, filed 19 Feb 2026 (promoter's report to RERA)
This date has passed. Our copy of the register has no handover dates, so it can't tell you whether homes were delivered. This is the date on the register now, and it may have been extended since registration.
We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.
Documents
Also filed on the register. We open a file here only after checking it for personal or financial details:
- Commencement Certificate
- Electricity Permission Letter
- Water Permission Letter
- Approved Layout Plan
- Approved Building/Plotting Plan
- Existing Layout Plan
- Existing Section Plan and Specification
- Sectional Drawing of the apartments
- Project Specifications
- Approved Section Of Building/Infrastructure Plan of Plotting
- Area Development Plan Of Project Area
- Certificate from Registered Engineer indicating the structural safety of the building
- Change of Land Use
- Conversion Certificate under section 95 of the KLR Act 1964
- Proforma of Agreement for Sale
- Proforma of Allotment Letter
- Brochure
- ESCOM/Electricity
- KWSSB/Water
- Approval/NOC under section 109 of KLR Act 1961
Location
About Bodhii Tree
Residential/Group Housing
- Project Type
- Plotted Development
- Type
- Plotted Development
- Status
- Ready (per RERA completion date)
- Total Land
- 7.22 Acres
- Total Plots
- 109
- Handover Date
- 30 Dec 2025
- RERA No.
- PRM/KA/RERA/1250/304/PR/210324/006723
- Location
- Hosakote, Bangalore
Bodhii Tree: questions answered
Where is Bodhii Tree located?
The Karnataka RERA register places Bodhii Tree in Hosakote, Bengaluru Rural.
What is the RERA number of Bodhii Tree?
The Karnataka RERA registration number of Bodhii Tree is PRM/KA/RERA/1250/304/PR/210324/006723, approved on 21 Mar 2024.
What completion date was filed for Bodhii Tree?
The completion date filed on the register was 30 Dec 2025. Check the register for any extension.
How big is Bodhii Tree?
The register lists Bodhii Tree with 109 plots and about 7.22 acres of land.
What is the latest construction progress of Bodhii Tree?
The quarterly report for Q3 2025-26, filed on 19 Feb 2026, shows construction 100% complete.
Where does this information about Bodhii Tree come from?
From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.
Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.