Registered Project
Under ConstructionHYDENBEN DEVELOPERS LLP
Hydenben Clifton
Devanahalli, Bangalore
- Total Units
- 98
- Floors
- 7
- Towers
- 2
- Total Area
- 1.58 Acres
- Handover
- 2 Apr 2028
RERA progress
Stage 3 of 4 · Under construction- RERA applied(completed)
- RERA approved(completed)
- Under construction(current stage)
- Handover(upcoming)
RERA Approved
13 May 2025
PRM/KA/RERA/1250/303/PR/130525/007737
Est. Handover as per RERA
2 Apr 2028
Configurations & unit mix
| 3 BHK | 49 | 865 – 1,263 sq ft | |
|---|---|---|---|
| 2 BHK | 35 | 689 – 928 sq ft | |
| 2.5 BHK | 14 | 7 of 14 | 740 – 893 sq ft |
Available from the promoter's RERA report, Q2 2026-27, filed 15 Oct 2026.
The promoter's RERA report, Q2 2026-27, filed 15 Oct 2026, by its own types and totals, which don't line up with the rows above. Types listed more than once are added together: 2 BHK 18 of 29 available; 3 BHK 36 of 55 available.
The register doesn't list prices, so none are shown here.
Latest quarterly report on the register
Construction progress
Construction complete40%
- Quarter
- Q2 2026-27
- Filed on
- 15 Oct 2026
- Units booked
- 37 of 98
- Units available
- 61
- Reports on file
- 4
Amenities
- Electricity
- Smart Home Automation
- CCTV Surveillance
- Community Hall
- Indoor Sports facility
- Swimming Pool
- Gym
- Power Backup
- Piped Gas
- Water and Sanitation
RERA & approvals
Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1250/303/PR/130525/007737)
Complaints on the register: 0 recorded on this project; 0 on the promoter's record, as shown on this registration
These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.
- RERA registration
- PRM/KA/RERA/1250/303/PR/130525/007737
- Registered as
- HYDENBEN CLIFTON
- Promoter
- HYDENBEN DEVELOPERS LLP
- Acknowledgement no.
- ACK/KA/RERA/1250/303/PR/280325/009092
- Status on the register
- New Project Launch
- Stage
- Under Construction
- Work stage
- 40% complete, Q2 2026-27 report filed 15 Oct 2026
- Sales status
- Ongoing Sales (per RERA QPR Q2 2026-27, as of 15 Oct 2026)
- RERA approved on
- 13 May 2025
- Proposed completion
- 2 Apr 2028
- Land area
- 1.58 acres (6,374 sq m)
- Towers (this registration)
- 2
- Floors (this registration)
- 7
- Units (this registration)
- 98
- Plan approved by
- BIAPPA - Bangalore Airport Area Planning Authority
- Approved plan no.
- BIAPPA/TP/SF/LAO/110/2022-23/24-25
- Plan approval date
- 18 Apr 2024
- Land use
- Residential
Dates on the register
- Completion filed with RERA
- 2 Apr 2028 (Karnataka RERA)
- Latest construction report
- 40% complete, Q2 2026-27, filed 15 Oct 2026 (promoter's report to RERA)
This is the date on the register now, and it may have been extended since registration.
We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.
Documents
Also filed on the register. We open a file here only after checking it for personal or financial details:
- Commencement Certificate
- Approved Building Plan
- Sectional Drawing of the apartments
- Certificate from Registered Engineer indicating the structural safety of the building
- Project Specifications
- Brochure
- Relinquishment Deed
- Proforma of Agreement for Sale
- Proforma of Allotment Letter
- Declaration (Form B)
- Advocate Search Report
- ESCOM/Electricity
- KWSSB/Water
- KSPCB
- SEIAA
- Fire Force Department
- Airport Authority of India
- BSNL
- Lift Authorities
- BMRCL
Location
About Hydenben Clifton
- Developer
- HYDENBEN DEVELOPERS LLP
- Project Type
- Residential/Group Housing
- Type
- Apartment
- Status
- Under Construction
- Total Land
- 1.58 Acres
- No. of Towers
- 2
- No. of Floors
- 7
- Total Units
- 98
- Handover Date
- 2 Apr 2028
- RERA No.
- PRM/KA/RERA/1250/303/PR/130525/007737
- Location
- Devanahalli, Bangalore
About the developer
HYDENBEN DEVELOPERS LLP
- Promoter on the register
- HYDENBEN DEVELOPERS LLP
- Projects on the register
- 1
- Registering since
- 2025
- Complaints on the promoter
- 0, as shown on this registration
Hydenben Clifton: questions answered
Where is Hydenben Clifton located?
The Karnataka RERA register places Hydenben Clifton in Devanahalli, Bengaluru Rural.
What is the RERA number of Hydenben Clifton?
The Karnataka RERA registration number of Hydenben Clifton is PRM/KA/RERA/1250/303/PR/130525/007737, approved on 13 May 2025.
Who is the promoter of Hydenben Clifton?
The promoter filed on the Karnataka RERA register is HYDENBEN DEVELOPERS LLP.
When is Hydenben Clifton expected to be completed?
The proposed completion date filed on the register is 2 Apr 2028.
How big is Hydenben Clifton?
The register lists Hydenben Clifton with 98 units, 2 towers and about 1.58 acres of land.
What is the latest construction progress of Hydenben Clifton?
The quarterly report for Q2 2026-27, filed on 15 Oct 2026, shows construction 40% complete and 37 of 98 units booked.
Where does this information about Hydenben Clifton come from?
From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.
Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.