Skip to main content
PropSarathi

Registered Project

Hillcrest Haven

Sy.No.24/1, Shetterahalli Village, Kasaba Hobli, Devanahalli Taluk, Devanahalli, Bengaluru Rural, Karnataka - 562110

Total Plots
38
Total Area
3 Acres
Handover
30 May 2028

RERA progress

Stage 2 of 4 · RERA approved
  1. RERA applied(completed)
  2. RERA approved(current stage)
  3. Under construction(upcoming)
  4. Handover(upcoming)

RERA Approved

26 Nov 2025

PRM/KA/RERA/1250/303/PR/261125/008272

Est. Handover as per RERA

30 May 2028

Configurations & unit mix

ODD SITE15about 1,887 sq ft each
9.14M*16.77M23about 1,650 sq ft each

The register doesn't list prices, so none are shown here.

Latest quarterly report on the register

Construction progress

Construction complete80%

Quarter
Q2 2026-27
Filed on
9 Oct 2026
Reports on file
4

RERA & approvals

Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1250/303/PR/261125/008272)

Complaints on the register: 0 recorded on this project; the promoter's count isn't shown here, so check the register

These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.

RERA registration
PRM/KA/RERA/1250/303/PR/261125/008272
Registered as
HILLCREST HAVEN
Acknowledgement no.
ACK/KA/RERA/1250/303/PR/160625/009314
Status on the register
Ongoing
Stage
New Launch
Work stage
80% complete, Q2 2026-27 report filed 9 Oct 2026
RERA approved on
26 Nov 2025
Proposed completion
30 May 2028
Land area
3 acres (12,140 sq m)
Plots (this registration)
38
Plan approved by
Satellite Town Ring Road Planning Authority
Approved plan no.
STRRPA/TP/LAO/07/2024-25
Plan approval date
14 Feb 2025
Land use
Residential

Dates on the register

Completion filed with RERA
30 May 2028 (Karnataka RERA)
Latest construction report
80% complete, Q2 2026-27, filed 9 Oct 2026 (promoter's report to RERA)

This is the date on the register now, and it may have been extended since registration.

We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.

Documents

Also filed on the register. We open a file here only after checking it for personal or financial details:

  • Approval Layout Order / Technical Sanction Letter
  • Approved Layout Plan/Demarcation Plan
  • Project Specifications
  • Brochure
  • Relinquishment Deed
  • Proforma of Agreement for Sale
  • Proforma of Allotment Letter
  • Advocate Search Report
  • NOC from ESCOMs
  • NOC for Water
  • KSPCB (If Applicable)
  • SEIAA (If Applicable)
  • Form-4 certificate (Chartered Accountant)
  • Form-6 certificate (Structural Engineer)

Location

About Hillcrest Haven

Residential Plotted Development

Project Type
Plotted Development
Type
Plotted Development
Status
New Launch
Total Land
3 Acres
Total Plots
38
Handover Date
30 May 2028
RERA No.
PRM/KA/RERA/1250/303/PR/261125/008272
Location
Devanahalli, Bangalore

Hillcrest Haven: questions answered

Where is Hillcrest Haven located?

The Karnataka RERA register places Hillcrest Haven in Devanahalli, Bengaluru Rural.

What is the RERA number of Hillcrest Haven?

The Karnataka RERA registration number of Hillcrest Haven is PRM/KA/RERA/1250/303/PR/261125/008272, approved on 26 Nov 2025.

When is Hillcrest Haven expected to be completed?

The proposed completion date filed on the register is 30 May 2028.

How big is Hillcrest Haven?

The register lists Hillcrest Haven with 38 plots and about 3 acres of land.

What is the latest construction progress of Hillcrest Haven?

The quarterly report for Q2 2026-27, filed on 9 Oct 2026, shows construction 80% complete.

Where does this information about Hillcrest Haven come from?

From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.

Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.