Handover
15 Sept 2022

RERA progress

Stage 4 of 4 · Handover
  1. RERA applied(completed)
  2. RERA approved(completed)
  3. Under construction(completed)
  4. Handover(current stage)

RERA Approved

11 Jun 2018

PRM/KA/RERA/1251/310/PR/180611/001891

Est. Handover as per RERA

15 Sep 2022

Developer target: 15 Sept 2022

RERA & approvals

Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/310/PR/180611/001891)

Complaints on the register: 0 recorded on this project; 0 on the promoter's record, as shown on this registration

These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.

RERA registration
PRM/KA/RERA/1251/310/PR/180611/001891
Registered as
The Marquise
Promoter
BARMECHA REALTY PRIVATE LIMITED
Acknowledgement no.
ACK/KA/RERA/1251/310/PR/180517/002254
Status on the register
Completed
Stage
Ready (per RERA completion date)
RERA approved on
11 Jun 2018
Proposed completion
15 Sept 2022
Towers (this registration)
3
Floors (this registration)
9
Plan approved by
BBMP - Bruhat Bengaluru Mahanagara Palike

Dates on the register

Completion filed with RERA
15 Sep 2022 (Karnataka RERA)

This date has passed. Our copy of the register has no handover dates, so it can't tell you whether homes were delivered. This is the date on the register now, and it may have been extended since registration.

We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.

Documents

Also filed on the register. We open a file here only after checking it for personal or financial details:

  • Approved Building/Plotting Plan
  • Approved Layout Plan
  • Approved Section Of Building/Infrastructure Plan of Plotting
  • Area Development Plan Of Project Area
  • BESCOM
  • Brochure of Current Project
  • Change of Land Use
  • Commencement Certificate
  • Conversion Certificate under Sec 95 of the KLR Act 1961
  • Existing Layout Plan
  • Existing Section Plan and Specification
  • Proforma of Agreement for Sale
  • Project Specification

Location

About The Marquise

Residential Apartment

Developer
BARMECHA REALTY PRIVATE LIMITED
Project Type
Residential/Group Housing
Type
Residential/Group Housing
Status
Ready (per RERA completion date)
No. of Towers
3
No. of Floors
9
Handover Date
15 Sept 2022
RERA No.
PRM/KA/RERA/1251/310/PR/180611/001891
Location
Bengaluru South, Bangalore

About the developer

BARMECHA REALTY PRIVATE LIMITED

Promoter on the register
BARMECHA REALTY PRIVATE LIMITED
Projects on the register
1
Registering since
2018
Complaints on the promoter
0, as shown on this registration

The Marquise: questions answered

Where is The Marquise located?

The Karnataka RERA register places The Marquise in Bengaluru South, Bengaluru Urban.

What is the RERA number of The Marquise?

The Karnataka RERA registration number of The Marquise is PRM/KA/RERA/1251/310/PR/180611/001891, approved on 11 Jun 2018.

Who is the promoter of The Marquise?

The promoter filed on the Karnataka RERA register is BARMECHA REALTY PRIVATE LIMITED.

What completion date was filed for The Marquise?

The completion date filed on the register was 15 Sept 2022. Check the register for any extension.

How big is The Marquise?

The register lists The Marquise with 3 towers.

Where does this information about The Marquise come from?

From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.

Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.