Registered Project
Under ConstructionSRI NANJUNDESHWARA INFRATECH
Sri Nanjundeshwara Residency
SY NO 82/5, (NEW SY NO 82/7), KATHA NO 853/4666/82/5/4666, KENGERI VILLAGE, KENGERI HOBLI, BANGALORE IN WARD NO 198, Bengaluru South, Bengaluru Urban, Karnataka - 560060
- Total Units
- 16
- Floors
- 4
- Towers
- 1
- Total Area
- 0.2 Acres
- Handover
- 31 Dec 2027
RERA progress
Stage 3 of 4 · Under construction- RERA applied(completed)
- RERA approved(completed)
- Under construction(current stage)
- Handover(upcoming)
RERA Approved
22 Jan 2025
PRM/KA/RERA/1251/310/PR/220125/007410
Est. Handover as per RERA
31 Dec 2027
Configurations & unit mix
| 3BHK | 8 | 2 of 8 | |
|---|---|---|---|
| 2BHK | 8 | 6 of 8 | 11,194 – 12,271 sq ft |
Available from the promoter's RERA report, Q4 2025-26, filed 21 Sept 2026.
The register doesn't list prices, so none are shown here.
Latest quarterly report on the register
Construction progress
Construction complete80%
- Quarter
- Q4 2025-26
- Filed on
- 21 Sept 2026
- Units booked
- 8 of 16
- Units available
- 8
- Reports on file
- 2
Amenities
- Electricity
- Power Backup
- Piped Gas
- Water and Sanitation
RERA & approvals
Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/310/PR/220125/007410)
Complaints on the register: 0 recorded on this project; 0 on the promoter's record, as shown on this registration
These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.
- RERA registration
- PRM/KA/RERA/1251/310/PR/220125/007410
- Registered as
- SRI NANJUNDESHWARA RESIDENCY
- Promoter
- SRI NANJUNDESHWARA INFRATECH
- Acknowledgement no.
- ACK/KA/RERA/1251/310/PR/270924/008557
- Status on the register
- New Project Launch
- Stage
- Under Construction
- Work stage
- 80% complete, Q4 2025-26 report filed 21 Sept 2026
- Sales status
- Ongoing Sales (per RERA QPR Q4 2025-26, as of 21 Sept 2026)
- RERA approved on
- 22 Jan 2025
- Proposed completion
- 31 Dec 2027
- Land area
- 0.2 acres (824 sq m)
- Towers (this registration)
- 1
- Floors (this registration)
- 4
- Units (this registration)
- 16
- Plan approved by
- BBMP - Bruhat Bengaluru Mahanagara Palike
- Approved plan no.
- BBMP/AD.COM/RJH/0680/24-25
- Plan approval date
- 31 Jul 2024
- Land use
- Residential
Dates on the register
- Completion filed with RERA
- 31 Dec 2027 (Karnataka RERA)
- Latest construction report
- 80% complete, Q4 2025-26, filed 21 Sept 2026 (promoter's report to RERA)
This is the date on the register now, and it may have been extended since registration.
We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.
Documents
Also filed on the register. We open a file here only after checking it for personal or financial details:
- Commencement Certificate
- Electricity Permission Letter
- Water Permission Letter
- Approved Layout Plan
- Approved Building/Plotting Plan
- Existing Layout Plan
- Existing Section Plan and Specification
- Sectional Drawing of the apartments
- Approved Section Of Building/Infrastructure Plan of Plotting
- Certificate from Registered Engineer indicating the structural safety of the building
- Change of Land Use
- Conversion Certificate under section 95 of the KLR Act 1964
- Declaration (Form B)
- ESCOM/Electricity
- KWSSB/Water
- Approval/NOC under section 109 of KLR Act 1961
- Approval/NOC under section 14 of the KTCP Act
- Fire Force Department
- Airport Authority of India
- KSPCB
Location
About Sri Nanjundeshwara Residency
RESIDENTIAL APARTMENT
- Developer
- SRI NANJUNDESHWARA INFRATECH
- Project Type
- Residential/Group Housing
- Type
- Apartment
- Status
- Under Construction
- Total Land
- 0.2 Acres
- No. of Towers
- 1
- No. of Floors
- 4
- Total Units
- 16
- Handover Date
- 31 Dec 2027
- RERA No.
- PRM/KA/RERA/1251/310/PR/220125/007410
- Location
- Bengaluru South, Bangalore
About the developer
SRI NANJUNDESHWARA INFRATECH
- Promoter on the register
- SRI NANJUNDESHWARA INFRATECH
- Projects on the register
- 1
- Registering since
- 2025
- Complaints on the promoter
- 0, as shown on this registration
Sri Nanjundeshwara Residency: questions answered
Where is Sri Nanjundeshwara Residency located?
The Karnataka RERA register places Sri Nanjundeshwara Residency in Bengaluru South, Bengaluru Urban.
What is the RERA number of Sri Nanjundeshwara Residency?
The Karnataka RERA registration number of Sri Nanjundeshwara Residency is PRM/KA/RERA/1251/310/PR/220125/007410, approved on 22 Jan 2025.
Who is the promoter of Sri Nanjundeshwara Residency?
The promoter filed on the Karnataka RERA register is SRI NANJUNDESHWARA INFRATECH.
When is Sri Nanjundeshwara Residency expected to be completed?
The proposed completion date filed on the register is 31 Dec 2027.
How big is Sri Nanjundeshwara Residency?
The register lists Sri Nanjundeshwara Residency with 16 units, 1 tower and about 0.2 acres of land.
What is the latest construction progress of Sri Nanjundeshwara Residency?
The quarterly report for Q4 2025-26, filed on 21 Sept 2026, shows construction 80% complete and 8 of 16 units booked.
Where does this information about Sri Nanjundeshwara Residency come from?
From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.
Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.