Skip to main content
PropSarathi

Registered Project

Under Construction

SRI NANJUNDESHWARA INFRATECH

Sri Nanjundeshwara Residency

SY NO 82/5, (NEW SY NO 82/7), KATHA NO 853/4666/82/5/4666, KENGERI VILLAGE, KENGERI HOBLI, BANGALORE IN WARD NO 198, Bengaluru South, Bengaluru Urban, Karnataka - 560060

Total Units
16
Floors
4
Towers
1
Total Area
0.2 Acres
Handover
31 Dec 2027

RERA progress

Stage 3 of 4 · Under construction
  1. RERA applied(completed)
  2. RERA approved(completed)
  3. Under construction(current stage)
  4. Handover(upcoming)

RERA Approved

22 Jan 2025

PRM/KA/RERA/1251/310/PR/220125/007410

Est. Handover as per RERA

31 Dec 2027

Configurations & unit mix

3BHK82 of 8
2BHK86 of 811,194 – 12,271 sq ft

Available from the promoter's RERA report, Q4 2025-26, filed 21 Sept 2026.

The register doesn't list prices, so none are shown here.

Latest quarterly report on the register

Construction progress

Construction complete80%

Quarter
Q4 2025-26
Filed on
21 Sept 2026
Units booked
8 of 16
Units available
8
Reports on file
2

Amenities

  • Electricity
  • Power Backup
  • Piped Gas
  • Water and Sanitation

RERA & approvals

Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/310/PR/220125/007410)

Complaints on the register: 0 recorded on this project; 0 on the promoter's record, as shown on this registration

These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.

RERA registration
PRM/KA/RERA/1251/310/PR/220125/007410
Registered as
SRI NANJUNDESHWARA RESIDENCY
Promoter
SRI NANJUNDESHWARA INFRATECH
Acknowledgement no.
ACK/KA/RERA/1251/310/PR/270924/008557
Status on the register
New Project Launch
Stage
Under Construction
Work stage
80% complete, Q4 2025-26 report filed 21 Sept 2026
Sales status
Ongoing Sales (per RERA QPR Q4 2025-26, as of 21 Sept 2026)
RERA approved on
22 Jan 2025
Proposed completion
31 Dec 2027
Land area
0.2 acres (824 sq m)
Towers (this registration)
1
Floors (this registration)
4
Units (this registration)
16
Plan approved by
BBMP - Bruhat Bengaluru Mahanagara Palike
Approved plan no.
BBMP/AD.COM/RJH/0680/24-25
Plan approval date
31 Jul 2024
Land use
Residential

Dates on the register

Completion filed with RERA
31 Dec 2027 (Karnataka RERA)
Latest construction report
80% complete, Q4 2025-26, filed 21 Sept 2026 (promoter's report to RERA)

This is the date on the register now, and it may have been extended since registration.

We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.

Documents

Also filed on the register. We open a file here only after checking it for personal or financial details:

  • Commencement Certificate
  • Electricity Permission Letter
  • Water Permission Letter
  • Approved Layout Plan
  • Approved Building/Plotting Plan
  • Existing Layout Plan
  • Existing Section Plan and Specification
  • Sectional Drawing of the apartments
  • Approved Section Of Building/Infrastructure Plan of Plotting
  • Certificate from Registered Engineer indicating the structural safety of the building
  • Change of Land Use
  • Conversion Certificate under section 95 of the KLR Act 1964
  • Declaration (Form B)
  • ESCOM/Electricity
  • KWSSB/Water
  • Approval/NOC under section 109 of KLR Act 1961
  • Approval/NOC under section 14 of the KTCP Act
  • Fire Force Department
  • Airport Authority of India
  • KSPCB

Location

About Sri Nanjundeshwara Residency

RESIDENTIAL APARTMENT

Developer
SRI NANJUNDESHWARA INFRATECH
Project Type
Residential/Group Housing
Type
Apartment
Status
Under Construction
Total Land
0.2 Acres
No. of Towers
1
No. of Floors
4
Total Units
16
Handover Date
31 Dec 2027
RERA No.
PRM/KA/RERA/1251/310/PR/220125/007410
Location
Bengaluru South, Bangalore

About the developer

SRI NANJUNDESHWARA INFRATECH

Promoter on the register
SRI NANJUNDESHWARA INFRATECH
Projects on the register
1
Registering since
2025
Complaints on the promoter
0, as shown on this registration

Sri Nanjundeshwara Residency: questions answered

Where is Sri Nanjundeshwara Residency located?

The Karnataka RERA register places Sri Nanjundeshwara Residency in Bengaluru South, Bengaluru Urban.

What is the RERA number of Sri Nanjundeshwara Residency?

The Karnataka RERA registration number of Sri Nanjundeshwara Residency is PRM/KA/RERA/1251/310/PR/220125/007410, approved on 22 Jan 2025.

Who is the promoter of Sri Nanjundeshwara Residency?

The promoter filed on the Karnataka RERA register is SRI NANJUNDESHWARA INFRATECH.

When is Sri Nanjundeshwara Residency expected to be completed?

The proposed completion date filed on the register is 31 Dec 2027.

How big is Sri Nanjundeshwara Residency?

The register lists Sri Nanjundeshwara Residency with 16 units, 1 tower and about 0.2 acres of land.

What is the latest construction progress of Sri Nanjundeshwara Residency?

The quarterly report for Q4 2025-26, filed on 21 Sept 2026, shows construction 80% complete and 8 of 16 units booked.

Where does this information about Sri Nanjundeshwara Residency come from?

From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.

Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.