Skip to main content
PropSarathi

Registered Project

Ready (per RERA completion date)

SML Iris

Katha No: 3353/20/4, Ward No: 198, Pattanagere, Kengeri Hobli, Bangalore 560043

Floors
4
Towers
1
Handover
7 Oct 2022

RERA progress

Stage 4 of 4 · Handover
  1. RERA applied(completed)
  2. RERA approved(completed)
  3. Under construction(completed)
  4. Handover(current stage)

RERA Approved

13 Oct 2020

PRM/KA/RERA/1251/310/PR/201013/003641

Est. Handover as per RERA

7 Oct 2022

RERA & approvals

Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/310/PR/201013/003641)

Complaints on the register: 0 recorded on this project; the promoter's count isn't shown here, so check the register

These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.

RERA registration
PRM/KA/RERA/1251/310/PR/201013/003641
Registered as
SML IRIS
Acknowledgement no.
ACK/KA/RERA/1251/310/PR/200122/003846
Status on the register
Completed
Stage
Ready (per RERA completion date)
RERA approved on
13 Oct 2020
Proposed completion
7 Oct 2022
Towers (this registration)
1
Floors (this registration)
4
Plan approved by
BBMP - Bruhat Bengaluru Mahanagara Palike

Dates on the register

Completion filed with RERA
7 Oct 2022 (Karnataka RERA)

This date has passed. Our copy of the register has no handover dates, so it can't tell you whether homes were delivered. This is the date on the register now, and it may have been extended since registration.

We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.

Documents

Also filed on the register. We open a file here only after checking it for personal or financial details:

  • Airport Authority of India
  • Approval/NOC under Sec 14 of the KTCP Act
  • Approved Building/Plotting Plan
  • Approved Layout Plan
  • Bangalore Urban Arts Commission
  • BESCOM
  • BMRCL
  • Brochure of Current Project
  • BSNL
  • Certificate from Registered Engineer indicating the structural safety of the building (for Apartments)
  • Coastal Regulation Zone Authority
  • Commencement Certificate
  • Conversion Certificate under Sec 95 of the KLR Act 1961
  • Existing Layout Plan
  • Fire Force Department
  • Inspector of Factories Controller of explosives Railways
  • KSPCB
  • Lift Authorities
  • NOC in case of building proposals abutting to neighbouring properties
  • Proforma For Sale Deed

Location

About SML Iris

Residential apartment consists of 20 units (2/3 BHK)

Project Type
Residential/Group Housing
Type
Residential/Group Housing
Status
Ready (per RERA completion date)
No. of Towers
1
No. of Floors
4
Handover Date
7 Oct 2022
RERA No.
PRM/KA/RERA/1251/310/PR/201013/003641
Location
Bengaluru South, Bangalore

SML Iris: questions answered

Where is SML Iris located?

The Karnataka RERA register places SML Iris in Bengaluru South, Bengaluru Urban.

What is the RERA number of SML Iris?

The Karnataka RERA registration number of SML Iris is PRM/KA/RERA/1251/310/PR/201013/003641, approved on 13 Oct 2020.

What completion date was filed for SML Iris?

The completion date filed on the register was 7 Oct 2022. Check the register for any extension.

How big is SML Iris?

The register lists SML Iris with 1 tower.

Where does this information about SML Iris come from?

From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.

Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.