Bengaluru South, Bangalore

Total Units
11
Floors
3
Towers
1
Total Area
0.2 Acres
Handover
31 Mar 2029

RERA progress

Stage 2 of 4 · RERA approved
  1. RERA applied(completed)
  2. RERA approved(current stage)
  3. Under construction(upcoming)
  4. Handover(upcoming)

RERA Approved

29 Jul 2026

PRM/KA/RERA/1251/310/PR/290726/008855

Est. Handover as per RERA

31 Mar 2029

Configurations & unit mix

3 BHK1010 of 101,731 – 1,899 sq ft
Duplex11 of 13,799 sq ft

Available from the promoter's RERA report, Q2 2026-27, filed 15 Oct 2026.

The register doesn't list prices, so none are shown here.

Latest quarterly report on the register

Construction progress

Construction complete60%

Quarter
Q2 2026-27
Filed on
15 Oct 2026
Units booked
0 of 11
Units available
11

Amenities

  • Electricity
  • CCTV Surveillance
  • Power Backup
  • Piped Gas
  • Water and Sanitation

RERA & approvals

Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/310/PR/290726/008855)

Complaints on the register: 0 recorded on this project; the promoter's count isn't shown here, so check the register

These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.

RERA registration
PRM/KA/RERA/1251/310/PR/290726/008855
Acknowledgement no.
ACK/KA/RERA/1251/310/PR/170726/010425
Status on the register
Ongoing
Stage
New Launch
Work stage
60% complete, Q2 2026-27 report filed 15 Oct 2026
Sales status
Ongoing Sales (per RERA QPR Q2 2026-27, as of 15 Oct 2026)
RERA approved on
29 Jul 2026
Proposed completion
31 Mar 2029
Land area
0.2 acres (816 sq m)
Towers (this registration)
1
Floors (this registration)
3
Units (this registration)
11
Plan approved by
BBMP - Bruhat Bengaluru Mahanagara Palike
Approved plan no.
GBA/RRN/DDTP/0101/25-26
Plan approval date
13 Jan 2026

Dates on the register

Completion filed with RERA
31 Mar 2029 (Karnataka RERA)
Latest construction report
60% complete, Q2 2026-27, filed 15 Oct 2026 (promoter's report to RERA)

This is the date on the register now, and it may have been extended since registration.

We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.

Documents

Also filed on the register. We open a file here only after checking it for personal or financial details:

  • Commencement Certificate
  • Approved Building Plan
  • Sectional Drawing of the apartments
  • Certificate from Registered Engineer indicating the structural safety of the building
  • Project Specifications
  • Proforma of Agreement for Sale
  • Proforma of Allotment Letter
  • Declaration (Form B)
  • Advocate Search Report
  • ESCOM/Electricity
  • KSPCB
  • SEIAA
  • Fire Force Department
  • Airport Authority of India
  • BSNL
  • Lift Authorities
  • BMRCL
  • NOC in case of building proposals abutting to neighbouring properties
  • Bangalore Urban Arts Commission
  • Inspector Of Factories Controller Of Explosives Railways

Location

About Registered project (name under review)

Project Type
Residential/Group Housing
Type
Apartment
Status
New Launch
Total Land
0.2 Acres
No. of Towers
1
No. of Floors
3
Total Units
11
Handover Date
31 Mar 2029
RERA No.
PRM/KA/RERA/1251/310/PR/290726/008855
Location
Bengaluru South, Bangalore

Registered project (name under review): questions answered

Where is Registered project (name under review) located?

The Karnataka RERA register places Registered project (name under review) in Bengaluru South, Bengaluru Urban.

What is the RERA number of Registered project (name under review)?

The Karnataka RERA registration number of Registered project (name under review) is PRM/KA/RERA/1251/310/PR/290726/008855, approved on 29 Jul 2026.

When is Registered project (name under review) expected to be completed?

The proposed completion date filed on the register is 31 Mar 2029.

How big is Registered project (name under review)?

The register lists Registered project (name under review) with 11 units, 1 tower and about 0.2 acres of land.

What is the latest construction progress of Registered project (name under review)?

The quarterly report for Q2 2026-27, filed on 15 Oct 2026, shows construction 60% complete and 0 of 11 units booked.

Where does this information about Registered project (name under review) come from?

From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.

Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.