Registered Project
New LaunchOpera Akshar
Bengaluru South, Bangalore
- Total Units
- 15
- Floors
- 3
- Towers
- 1
- Total Area
- 0.3 Acres
- Handover
- 31 Aug 2028
RERA progress
Stage 2 of 4 · RERA approved- RERA applied(completed)
- RERA approved(current stage)
- Under construction(upcoming)
- Handover(upcoming)
RERA Approved
5 Nov 2025
PRM/KA/RERA/1251/309/PR/051125/008225
Est. Handover as per RERA
31 Aug 2028
Configurations & unit mix
| 3 BHK | 9 | 9 of 9 | 1,090 – 1,624 sq ft |
|---|---|---|---|
| 2.5 BHK | 6 | 5 of 6 | 1,202 – 1,499 sq ft |
Available from the promoter's RERA report, Q2 2026-27, filed 13 Oct 2026.
The register doesn't list prices, so none are shown here.
Latest quarterly report on the register
Construction progress
Construction complete41%
- Quarter
- Q2 2026-27
- Filed on
- 13 Oct 2026
- Units booked
- 1 of 15
- Units available
- 14
- Reports on file
- 4
Amenities
- Electricity
- Community Hall
- Outdoor Sports facility
- Gym
- Parks
- Power Backup
- Water and Sanitation
RERA & approvals
Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/309/PR/051125/008225)
Complaints on the register: 0 recorded on this project; the promoter's count isn't shown here, so check the register
These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.
- RERA registration
- PRM/KA/RERA/1251/309/PR/051125/008225
- Registered as
- OPERA AKSHAR
- Acknowledgement no.
- ACK/KA/RERA/1251/309/PR/101025/009687
- Status on the register
- New Project Launch
- Stage
- New Launch
- Work stage
- 41% complete, Q2 2026-27 report filed 13 Oct 2026
- Sales status
- Ongoing Sales (per RERA QPR Q2 2026-27, as of 13 Oct 2026)
- RERA approved on
- 5 Nov 2025
- Proposed completion
- 31 Aug 2028
- Land area
- 0.3 acres (1,223 sq m)
- Towers (this registration)
- 1
- Floors (this registration)
- 3
- Units (this registration)
- 15
- Plan approved by
- BBMP - Bruhat Bengaluru Mahanagara Palike
- Approved plan no.
- BBMP/Ad.Com./SUT/1344/24-25
- Plan approval date
- 6 Aug 2025
Dates on the register
- Completion filed with RERA
- 31 Aug 2028 (Karnataka RERA)
- Latest construction report
- 41% complete, Q2 2026-27, filed 13 Oct 2026 (promoter's report to RERA)
This is the date on the register now, and it may have been extended since registration.
We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.
Documents
Also filed on the register. We open a file here only after checking it for personal or financial details:
- Approved Building Plan
- Sectional Drawing of the apartments
- Certificate from Registered Engineer indicating the structural safety of the building
- Project Specifications
- Proforma of Agreement for Sale
- Declaration (Form B)
- ESCOM/Electricity
- KSPCB
- SEIAA
- Fire Force Department
- Airport Authority of India
- BSNL
- Lift Authorities
- BMRCL
- NOC in case of building proposals abutting to neighbouring properties
- Bangalore Urban Arts Commission
- Inspector Of Factories Controller Of Explosives Railways
- Coastal Regulation Zone Authority
- Form-4 certificate (Chartered Accountant)
- Form-5 certificate (Architect)
Location
About Opera Akshar
Residential Apartment
- Project Type
- Residential/Group Housing
- Type
- Apartment
- Status
- New Launch
- Total Land
- 0.3 Acres
- No. of Towers
- 1
- No. of Floors
- 3
- Total Units
- 15
- Handover Date
- 31 Aug 2028
- RERA No.
- PRM/KA/RERA/1251/309/PR/051125/008225
- Location
- Bengaluru South, Bangalore
Opera Akshar: questions answered
Where is Opera Akshar located?
The Karnataka RERA register places Opera Akshar in Bengaluru South, Bengaluru Urban.
What is the RERA number of Opera Akshar?
The Karnataka RERA registration number of Opera Akshar is PRM/KA/RERA/1251/309/PR/051125/008225, approved on 5 Nov 2025.
When is Opera Akshar expected to be completed?
The proposed completion date filed on the register is 31 Aug 2028.
How big is Opera Akshar?
The register lists Opera Akshar with 15 units, 1 tower and about 0.3 acres of land.
What is the latest construction progress of Opera Akshar?
The quarterly report for Q2 2026-27, filed on 13 Oct 2026, shows construction 41% complete and 1 of 15 units booked.
Where does this information about Opera Akshar come from?
From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.
Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.