RERA progress
Stage 3 of 4 · Under construction- RERA applied(completed)
- RERA approved(completed)
- Under construction(current stage)
- Handover(upcoming)
RERA Approved
19 May 2025
PRM/KA/RERA/1251/310/PR/190525/007757
Est. Handover as per RERA
31 Dec 2029
Configurations & unit mix
| 2 BHK, 3 BHK | 170 |
|---|
The promoter's RERA report, Q2 2026-27, filed 14 Oct 2026, by its own types and totals, which don't line up with the rows above. Types listed more than once are added together: 2 BHK 85 of 95 available; 3 BHK 55 of 75 available.
The register doesn't list prices, so none are shown here.
Latest quarterly report on the register
Construction progress
Construction complete57%
- Quarter
- Q2 2026-27
- Filed on
- 14 Oct 2026
- Units booked
- 30 of 170
- Units available
- 140
- Reports on file
- 4
Amenities
- Electricity
- CCTV Surveillance
RERA & approvals
Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/310/PR/190525/007757)
Complaints on the register: 0 recorded on this project; 0 on the promoter's record, as shown on this registration
These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.
- RERA registration
- PRM/KA/RERA/1251/310/PR/190525/007757
- Registered as
- M R SERENITY
- Promoter
- M R DEVELOPERS
- Acknowledgement no.
- ACK/KA/RERA/1251/310/PR/020425/009104
- Status on the register
- Ongoing
- Stage
- Under Construction
- Work stage
- 57% complete, Q2 2026-27 report filed 14 Oct 2026
- Sales status
- Ongoing Sales (per RERA QPR Q2 2026-27, as of 14 Oct 2026)
- RERA approved on
- 19 May 2025
- Proposed completion
- 31 Dec 2029
- Land area
- 1.92 acres (7,790 sq m)
- Towers (this registration)
- 2
- Floors (this registration)
- 5
- Units (this registration)
- 170
- Plan approved by
- BBMP - Bruhat Bengaluru Mahanagara Palike
- Approved plan no.
- BBMP/Addl.Dir/JDSOUTH/0002/23-24.
- Plan approval date
- 18 Apr 2024
- Land use
- Residential
Dates on the register
- Completion filed with RERA
- 31 Dec 2029 (Karnataka RERA)
- Latest construction report
- 57% complete, Q2 2026-27, filed 14 Oct 2026 (promoter's report to RERA)
This is the date on the register now, and it may have been extended since registration.
We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.
Documents
Also filed on the register. We open a file here only after checking it for personal or financial details:
- Commencement Certificate
- Approved Building Plan
- Sectional Drawing of the apartments
- Certificate from Registered Engineer indicating the structural safety of the building
- Project Specifications
- Brochure
- Proforma of Agreement for Sale
- Proforma of Allotment Letter
- Declaration (Form B)
- Advocate Search Report
- KWSSB/Water
- KSPCB
- SEIAA
- Form-4 certificate (Chartered Accountant)
- Form-5 certificate (Architect)
- Form-6 certificate (Structural Engineer)
Location
About M R Serenity
Residential Apartments / Group Housing with 170 Flats
- Developer
- M R DEVELOPERS
- Project Type
- Residential/Group Housing
- Type
- Apartment
- Status
- Under Construction
- Total Land
- 1.92 Acres
- No. of Towers
- 2
- No. of Floors
- 5
- Total Units
- 170
- Handover Date
- 31 Dec 2029
- RERA No.
- PRM/KA/RERA/1251/310/PR/190525/007757
- Location
- Bengaluru South, Bangalore
About the developer
M R DEVELOPERS
- Promoter on the register
- M R DEVELOPERS
- Projects on the register
- 2
- Registering since
- 2018
- Complaints on the promoter
- 0, as shown on this registration
M R Serenity: questions answered
Where is M R Serenity located?
The Karnataka RERA register places M R Serenity in Bengaluru South, Bengaluru Urban.
What is the RERA number of M R Serenity?
The Karnataka RERA registration number of M R Serenity is PRM/KA/RERA/1251/310/PR/190525/007757, approved on 19 May 2025.
Who is the promoter of M R Serenity?
The promoter filed on the Karnataka RERA register is M R DEVELOPERS.
When is M R Serenity expected to be completed?
The proposed completion date filed on the register is 31 Dec 2029.
How big is M R Serenity?
The register lists M R Serenity with 170 units, 2 towers and about 1.92 acres of land.
What is the latest construction progress of M R Serenity?
The quarterly report for Q2 2026-27, filed on 14 Oct 2026, shows construction 57% complete and 30 of 170 units booked.
Where does this information about M R Serenity come from?
From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.
Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.