Skip to main content
PropSarathi

Registered Project

New Launch

Commune by Are PHASE 1

Sy.No.151/2, 3 of Taralu Village, Uttarahalli Hobli, Bengaluru South, Bengaluru Urban, Karnataka - 560082

Total Plots
24
Total Area
2.75 Acres
Handover
31 Jan 2029

RERA progress

Stage 2 of 4 · RERA approved
  1. RERA applied(completed)
  2. RERA approved(current stage)
  3. Under construction(upcoming)
  4. Handover(upcoming)

RERA Approved

18 Feb 2026

PRM/KA/RERA/1251/310/PR/180226/008471

Est. Handover as per RERA

31 Jan 2029

Configurations & unit mix

Odd Sites24about 1,716 sq ft each

The register doesn't list prices, so none are shown here.

Latest quarterly report on the register

Construction progress

Construction complete96%

Quarter
Q2 2026-27
Filed on
15 Oct 2026
Reports on file
3

RERA & approvals

Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/310/PR/180226/008471)

Complaints on the register: 0 recorded on this project; the promoter's count isn't shown here, so check the register

These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.

RERA registration
PRM/KA/RERA/1251/310/PR/180226/008471
Registered as
COMMUNE BY ARE PHASE 1
Acknowledgement no.
ACK/KA/RERA/1251/310/PR/050226/009990
Status on the register
Ongoing
Stage
New Launch
Work stage
96% complete, Q2 2026-27 report filed 15 Oct 2026
RERA approved on
18 Feb 2026
Proposed completion
31 Jan 2029
Land area
2.75 acres (11,129 sq m)
Plots (this registration)
24
Plan approved by
Kanakapura Planning Authority
Approved plan no.
2917
Plan approval date
26 Nov 2025
Land use
Residential

Dates on the register

Completion filed with RERA
31 Jan 2029 (Karnataka RERA)
Latest construction report
96% complete, Q2 2026-27, filed 15 Oct 2026 (promoter's report to RERA)

This is the date on the register now, and it may have been extended since registration.

We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.

Documents

Also filed on the register. We open a file here only after checking it for personal or financial details:

  • Approval Layout Order / Technical Sanction Letter
  • Approved Layout Plan/Demarcation Plan
  • Project Specifications
  • Brochure
  • Relinquishment Deed
  • Proforma of Agreement for Sale
  • Proforma of Allotment Letter
  • Declaration (Form B)
  • Advocate Search Report
  • NOC from ESCOMs
  • NOC for Water
  • KSPCB (If Applicable)
  • SEIAA (If Applicable)
  • Form-4 certificate (Chartered Accountant)
  • Form-6 certificate (Structural Engineer)

Location

About Commune by Are PHASE 1

Plotted development

Type
Plotted Development
Status
New Launch
Total Land
2.75 Acres
Total Plots
24
Handover Date
31 Jan 2029
RERA No.
PRM/KA/RERA/1251/310/PR/180226/008471
Location
Bengaluru South, Bangalore

Commune by Are PHASE 1: questions answered

Where is Commune by Are located?

The Karnataka RERA register places Commune by Are in Bengaluru South, Bengaluru Urban.

What is the RERA number of Commune by Are?

The Karnataka RERA registration number of Commune by Are is PRM/KA/RERA/1251/310/PR/180226/008471, approved on 18 Feb 2026.

When is Commune by Are expected to be completed?

The proposed completion date filed on the register is 31 Jan 2029.

How big is Commune by Are?

The register lists Commune by Are with 24 plots and about 2.75 acres of land.

What is the latest construction progress of Commune by Are?

The quarterly report for Q2 2026-27, filed on 15 Oct 2026, shows construction 96% complete.

Where does this information about Commune by Are come from?

From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.

Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.