Registered Project
Under ConstructionBloomfields
Sy No.79/2, 79/3, 79/4 (P) & 79/5 (P), Kumbalagudu Village, Kengeri Hobli, Bengaluru South, Bengaluru Urban, Karnataka - 560074
- Total Plots
- 105
- Total Area
- 6.8 Acres
- Handover
- 30 Apr 2029
RERA progress
Stage 3 of 4 · Under construction- RERA applied(completed)
- RERA approved(completed)
- Under construction(current stage)
- Handover(upcoming)
RERA Approved
13 May 2025
PRM/KA/RERA/1251/310/PR/130525/007736
Est. Handover as per RERA
30 Apr 2029
Configurations & unit mix
| 12.19 × 18.29 m | 15 | about 2,400 sq ft each |
|---|---|---|
| 9.14 × 12.19 m | 24 | about 1,199 sq ft each |
| Parks | 2 | about 23,358 sq ft each |
| 12.19 × 15.24 m | 2 | about 2,002 sq ft each |
| 9.14 × 15.24 m | 30 | about 1,499 sq ft each |
| Road | 10 | about 8,644 sq ft each |
| CA Sites | 1 | about 1,507 sq ft each |
| 6.10*9.14(EWS) | 8 | about 600 sq ft each |
| 9.14 × 18.29 m | 5 | about 1,800 sq ft each |
| 12.19 × 12.19 m | 3 | about 1,600 sq ft each |
| ODD Sites | 18 | about 1,621 sq ft each |
The register doesn't list prices, so none are shown here.
Latest quarterly report on the register
Construction progress
Construction complete85%
- Quarter
- Q2 2026-27
- Filed on
- 10 Oct 2026
- Reports on file
- 4
RERA & approvals
Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/310/PR/130525/007736)
Complaints on the register: 0 recorded on this project; the promoter's count isn't shown here, so check the register
These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.
- RERA registration
- PRM/KA/RERA/1251/310/PR/130525/007736
- Registered as
- Bloomfields
- Acknowledgement no.
- ACK/KA/RERA/1251/310/PR/110425/009122
- Status on the register
- Ongoing
- Stage
- Under Construction
- Work stage
- 85% complete, Q2 2026-27 report filed 10 Oct 2026
- RERA approved on
- 13 May 2025
- Proposed completion
- 30 Apr 2029
- Land area
- 6.8 acres (27,519 sq m)
- Plots (this registration)
- 105
- Plan approved by
- BDA - Bangalore Development Authority
- Approved plan no.
- BDA/TPM/PRL-17/2509/2024-25
- Plan approval date
- 3 Jan 2025
- Land use
- Residential
Dates on the register
- Completion filed with RERA
- 30 Apr 2029 (Karnataka RERA)
- Latest construction report
- 85% complete, Q2 2026-27, filed 10 Oct 2026 (promoter's report to RERA)
This is the date on the register now, and it may have been extended since registration.
We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.
Documents
Also filed on the register. We open a file here only after checking it for personal or financial details:
- Approval Layout Order / Technical Sanction Letter
- Approved Layout Plan/Demarcation Plan
- Project Specifications
- Proforma of Agreement for Sale
- Declaration (Form B)
- Advocate Search Report
- Form-4 certificate (Chartered Accountant)
- Form-6 certificate (Structural Engineer)
Location
About Bloomfields
Development of Residential Layout, Having 105 Plots at Sy No.79/2, 79/3, 79/4 (P) & 79/5 (P) in Kumbalagudu Village, Kengeri Hobli, Bengaluru South Taluk, Bengaluru Urban, Karnataka 560074
- Type
- Plotted Development
- Status
- Under Construction
- Total Land
- 6.8 Acres
- Total Plots
- 105
- Handover Date
- 30 Apr 2029
- RERA No.
- PRM/KA/RERA/1251/310/PR/130525/007736
- Location
- Bengaluru South, Bangalore
Bloomfields: questions answered
Where is Bloomfields located?
The Karnataka RERA register places Bloomfields in Bengaluru South, Bengaluru Urban.
What is the RERA number of Bloomfields?
The Karnataka RERA registration number of Bloomfields is PRM/KA/RERA/1251/310/PR/130525/007736, approved on 13 May 2025.
When is Bloomfields expected to be completed?
The proposed completion date filed on the register is 30 Apr 2029.
How big is Bloomfields?
The register lists Bloomfields with 105 plots and about 6.8 acres of land.
What is the latest construction progress of Bloomfields?
The quarterly report for Q2 2026-27, filed on 10 Oct 2026, shows construction 85% complete.
Where does this information about Bloomfields come from?
From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.
Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.