Registered Project
Under ConstructionAspire Calixia
SY NO 2/3 AND 13/7 OF RAVUGODLU VILLAGE, UTTARAHALLI HOBLI, Bengaluru South, Bengaluru Urban, Karnataka - 560082
- Total Plots
- 34
- Total Area
- 2.18 Acres
- Handover
- 31 Mar 2028
RERA progress
Stage 3 of 4 · Under construction- RERA applied(completed)
- RERA approved(completed)
- Under construction(current stage)
- Handover(upcoming)
RERA Approved
17 Jun 2025
PRM/KA/RERA/1251/310/PR/170625/007838
Est. Handover as per RERA
31 Mar 2028
Configurations & unit mix
| 10.00 × 15.00 m | 8 | about 1,615 sq ft each |
|---|---|---|
| 11.00 × 15.00 m | 7 | about 1,776 sq ft each |
| ODD SITES | 19 | about 1,418 sq ft each |
The register doesn't list prices, so none are shown here.
Latest quarterly report on the register
Construction progress
Construction complete100%
- Quarter
- Q4 2025-26
- Filed on
- 15 Apr 2026
- Reports on file
- 2
RERA & approvals
Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/310/PR/170625/007838)
Complaints on the register: 0 recorded on this project; the promoter's count isn't shown here, so check the register
These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.
- RERA registration
- PRM/KA/RERA/1251/310/PR/170625/007838
- Registered as
- ASPIRE CALIXIA
- Acknowledgement no.
- ACK/KA/RERA/1251/310/PR/300425/009180
- Status on the register
- Ongoing
- Stage
- Under Construction
- Work stage
- 100% complete, Q4 2025-26 report filed 15 Apr 2026
- RERA approved on
- 17 Jun 2025
- Proposed completion
- 31 Mar 2028
- Land area
- 2.18 acres (8,835 sq m)
- Plots (this registration)
- 34
- Plan approved by
- Kanakapura Planning Authority
- Approved plan no.
- LAO/196/2023-24/1411
- Plan approval date
- 12 Sept 2024
- Land use
- Residential
Dates on the register
- Completion filed with RERA
- 31 Mar 2028 (Karnataka RERA)
- Latest construction report
- 100% complete, Q4 2025-26, filed 15 Apr 2026 (promoter's report to RERA)
This is the date on the register now, and it may have been extended since registration.
We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.
Documents
Also filed on the register. We open a file here only after checking it for personal or financial details:
- Approval Layout Order / Technical Sanction Letter
- Approved Layout Plan/Demarcation Plan
- Project Specifications
- Form-4 certificate (Chartered Accountant)
- Form-6 certificate (Structural Engineer)
Location
About Aspire Calixia
RESIDENTIAL PLOT DEVELOPMENT
- Project Type
- Plotted Development
- Type
- Plotted Development
- Status
- Under Construction
- Total Land
- 2.18 Acres
- Total Plots
- 34
- Handover Date
- 31 Mar 2028
- RERA No.
- PRM/KA/RERA/1251/310/PR/170625/007838
- Location
- Bengaluru South, Bangalore
Aspire Calixia: questions answered
Where is Aspire Calixia located?
The Karnataka RERA register places Aspire Calixia in Bengaluru South, Bengaluru Urban.
What is the RERA number of Aspire Calixia?
The Karnataka RERA registration number of Aspire Calixia is PRM/KA/RERA/1251/310/PR/170625/007838, approved on 17 Jun 2025.
When is Aspire Calixia expected to be completed?
The proposed completion date filed on the register is 31 Mar 2028.
How big is Aspire Calixia?
The register lists Aspire Calixia with 34 plots and about 2.18 acres of land.
What is the latest construction progress of Aspire Calixia?
The quarterly report for Q4 2025-26, filed on 15 Apr 2026, shows construction 100% complete.
Where does this information about Aspire Calixia come from?
From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.
Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.