Skip to main content
PropSarathi

Registered Project

Sri Sai Bharath Towers

Sy No 29/2, Kothunuru Village, Hennur Main Road, Bengaluru North, Bengaluru Urban, Karnataka - 560077

Total Units
76
Floors
3
Towers
2
Total Area
1 Acres
Handover
31 Dec 2029

RERA progress

Stage 2 of 4 · RERA approved
  1. RERA applied(completed)
  2. RERA approved(current stage)
  3. Under construction(upcoming)
  4. Handover(upcoming)

RERA Approved

20 Jan 2026

PRM/KA/RERA/1251/309/PR/200126/008413

Est. Handover as per RERA

31 Dec 2029

Configurations & unit mix

2BHK2524 of 25580 – 807 sq ft
3BHK5151 of 51702 – 933 sq ft

Available from the promoter's RERA report, Q2 2026-27, filed 13 Oct 2026.

The register doesn't list prices, so none are shown here.

Latest quarterly report on the register

Construction progress

Construction complete80%

Quarter
Q2 2026-27
Filed on
13 Oct 2026
Units booked
1 of 76
Units available
75
Reports on file
3

Amenities

  • Electricity
  • CCTV Surveillance
  • Community Hall
  • Outdoor Sports facility
  • Indoor Sports facility
  • Swimming Pool
  • Gym
  • Power Backup
  • Water and Sanitation

RERA & approvals

Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/309/PR/200126/008413)

Complaints on the register: 0 recorded on this project; the promoter's count isn't shown here, so check the register

These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.

RERA registration
PRM/KA/RERA/1251/309/PR/200126/008413
Registered as
SRI SAI BHARATH TOWERS
Acknowledgement no.
ACK/KA/RERA/1251/309/PR/141025/009700
Status on the register
New Project Launch
Stage
New Launch
Work stage
80% complete, Q2 2026-27 report filed 13 Oct 2026
Sales status
Ongoing Sales (per RERA QPR Q2 2026-27, as of 13 Oct 2026)
RERA approved on
20 Jan 2026
Proposed completion
31 Dec 2029
Land area
1 acres (4,045 sq m)
Towers (this registration)
2
Floors (this registration)
3
Units (this registration)
76
Plan approved by
BBMP - Bruhat Bengaluru Mahanagara Palike
Plan approval date
27 Aug 2025
Land use
Residential

Dates on the register

Completion filed with RERA
31 Dec 2029 (Karnataka RERA)
Latest construction report
80% complete, Q2 2026-27, filed 13 Oct 2026 (promoter's report to RERA)

This is the date on the register now, and it may have been extended since registration.

We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.

Documents

Also filed on the register. We open a file here only after checking it for personal or financial details:

  • Commencement Certificate
  • Approved Building Plan
  • Sectional Drawing of the apartments
  • Certificate from Registered Engineer indicating the structural safety of the building
  • Project Specifications
  • Brochure
  • Relinquishment Deed
  • Proforma of Agreement for Sale
  • Proforma of Allotment Letter
  • ESCOM/Electricity
  • KWSSB/Water
  • KSPCB
  • SEIAA
  • Fire Force Department
  • Airport Authority of India
  • BSNL
  • Lift Authorities
  • BMRCL
  • NOC in case of building proposals abutting to neighbouring properties
  • Bangalore Urban Arts Commission

Location

About Sri Sai Bharath Towers

Apartment project

Project Type
Residential/Group Housing
Type
Apartment
Status
New Launch
Total Land
1 Acres
No. of Towers
2
No. of Floors
3
Total Units
76
Handover Date
31 Dec 2029
RERA No.
PRM/KA/RERA/1251/309/PR/200126/008413
Location
Bengaluru North, Bangalore

Sri Sai Bharath Towers: questions answered

Where is Sri Sai Bharath Towers located?

The Karnataka RERA register places Sri Sai Bharath Towers in Bengaluru North, Bengaluru Urban.

What is the RERA number of Sri Sai Bharath Towers?

The Karnataka RERA registration number of Sri Sai Bharath Towers is PRM/KA/RERA/1251/309/PR/200126/008413, approved on 20 Jan 2026.

When is Sri Sai Bharath Towers expected to be completed?

The proposed completion date filed on the register is 31 Dec 2029.

How big is Sri Sai Bharath Towers?

The register lists Sri Sai Bharath Towers with 76 units, 2 towers and about 1 acres of land.

What is the latest construction progress of Sri Sai Bharath Towers?

The quarterly report for Q2 2026-27, filed on 13 Oct 2026, shows construction 80% complete and 1 of 76 units booked.

Where does this information about Sri Sai Bharath Towers come from?

From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.

Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.