Registered Project

Ready (per RERA completion date)

M D B CONSTRUCTIONS

New warrior tower

Sy No 122/8, Katha No-104, Kattegenahalli Village, Yelahanka Hobli, Bangalore North Taluk, Bengaluru North, Bengaluru Urban, Karnataka - 560064

Total Units
52
Floors
3
Towers
1
Total Area
0.5 Acres
Handover
20 Oct 2025

RERA progress

Stage 4 of 4 · Handover
  1. RERA applied(completed)
  2. RERA approved(completed)
  3. Under construction(completed)
  4. Handover(current stage)

RERA Approved

16 May 2023

PRM/KA/RERA/1251/309/PR/160523/005937

Est. Handover as per RERA

20 Oct 2025

Configurations & unit mix

3 BHK16622 – 1,089 sq ft
2 BHK36579 – 1,047 sq ft

The register doesn't list prices, so none are shown here.

Amenities

  • Electricity
  • CCTV Surveillance
  • Power Backup
  • Water and Sanitation

RERA & approvals

Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/309/PR/160523/005937)

Complaints on the register: 0 recorded on this project; 0 on the promoter's record, as shown on this registration

These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.

RERA registration
PRM/KA/RERA/1251/309/PR/160523/005937
Registered as
New warrior tower
Promoter
M D B CONSTRUCTIONS
Acknowledgement no.
ACK/KA/RERA/1251/309/PR/260423/007065
Status on the register
Ongoing
Stage
Ready (per RERA completion date)
RERA approved on
16 May 2023
Proposed completion
20 Oct 2025
Land area
0.5 acres (2,018 sq m)
Towers (this registration)
1
Floors (this registration)
3
Units (this registration)
52
Plan approved by
BBMP - Bruhat Bengaluru Mahanagara Palike
Approved plan no.
PRJ/5958/22-23
Plan approval date
21 Dec 2022
Land use
Residential

Dates on the register

Completion filed with RERA
20 Oct 2025 (Karnataka RERA)

This date has passed. Our copy of the register has no handover dates, so it can't tell you whether homes were delivered. This is the date on the register now, and it may have been extended since registration.

We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.

Documents

Also filed on the register. We open a file here only after checking it for personal or financial details:

  • Commencement Certificate
  • Electricity Permission Letter
  • Water Permission Letter
  • Approved Layout Plan
  • Approved Building/Plotting Plan
  • Existing Layout Plan
  • Existing Section Plan and Specification
  • Sectional Drawing of the apartments
  • Project Specifications
  • Approved Section Of Building/Infrastructure Plan of Plotting
  • Area Development Plan Of Project Area
  • Certificate from Registered Engineer indicating the structural safety of the building
  • Change of Land Use
  • Conversion Certificate under section 95 of the KLR Act 1964
  • Proforma of Allotment Letter
  • Brochure
  • ESCOM/Electricity
  • KWSSB/Water
  • Approval/NOC under section 109 of KLR Act 1961
  • Approval/NOC under section 14 of the KTCP Act

Location

About New warrior tower

Residential Apartment

Developer
M D B CONSTRUCTIONS
Project Type
Residential/Group Housing
Type
Apartment
Status
Ready (per RERA completion date)
Total Land
0.5 Acres
No. of Towers
1
No. of Floors
3
Total Units
52
Handover Date
20 Oct 2025
RERA No.
PRM/KA/RERA/1251/309/PR/160523/005937
Location
Bengaluru North, Bangalore

About the developer

M D B CONSTRUCTIONS

Promoter on the register
M D B CONSTRUCTIONS
Projects on the register
1
Registering since
2023
Complaints on the promoter
0, as shown on this registration

New warrior tower: questions answered

Where is New warrior tower located?

The Karnataka RERA register places New warrior tower in Bengaluru North, Bengaluru Urban.

What is the RERA number of New warrior tower?

The Karnataka RERA registration number of New warrior tower is PRM/KA/RERA/1251/309/PR/160523/005937, approved on 16 May 2023.

Who is the promoter of New warrior tower?

The promoter filed on the Karnataka RERA register is M D B CONSTRUCTIONS.

What completion date was filed for New warrior tower?

The completion date filed on the register was 20 Oct 2025. Check the register for any extension.

How big is New warrior tower?

The register lists New warrior tower with 52 units, 1 tower and about 0.5 acres of land.

Where does this information about New warrior tower come from?

From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.

Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.