Registered Project
Under ConstructionKalyani Tech Park Private Limited
LivingTree by Kalyani Developers
Plot 7, Hitech Defence & Aerospace park, Bangalore, SY 430,452,453,454,455,456,457,458,459,463 &177(Block No. 8,9,10,11,12, & 13) of Bagaluru Village, Jala Hoblil, Bengaluru North, Bengaluru Urban, Karnataka - 560064
- Total Units
- 2,736
- Floors
- 25
- Towers
- 6
- Total Area
- 25 Acres
- Handover
- 15 Sept 2029
RERA progress
Stage 3 of 4 · Under construction- RERA applied(completed)
- RERA approved(completed)
- Under construction(current stage)
- Handover(upcoming)
RERA Approved
26 Sep 2024
PRM/KA/RERA/1251/309/PR/260924/007084
Est. Handover as per RERA
15 Sep 2029
Developer target: 15 Sept 2029
Configurations & unit mix
| Residential Apartments | 2,736 |
|---|
The promoter's RERA report, Q2 2026-27, filed 15 Oct 2026, by its own types and totals, which don't line up with the rows above. Types listed more than once are added together: 1 BHK 228 of 1,438 available; 2 BHK 221 of 1,248 available; 3 BHK 0 of 50 available.
The register doesn't list prices, so none are shown here.
Latest quarterly report on the register
Construction progress
Construction complete45%
- Quarter
- Q2 2026-27
- Filed on
- 15 Oct 2026
- Units booked
- 2,287 of 2,736
- Units available
- 449
- Reports on file
- 4
Amenities
- Electricity
- CCTV Surveillance
- Club House
- Community Hall
- Outdoor Sports facility
- Indoor Sports facility
- Swimming Pool
- Gym
- Parks
- Power Backup
- Water and Sanitation
RERA & approvals
Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/309/PR/260924/007084)
Complaints on the register: 4 recorded on this project; 4 on the promoter's record, as shown on this registration
These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.
- RERA registration
- PRM/KA/RERA/1251/309/PR/260924/007084
- Registered as
- LivingTree by Kalyani Developers
- Promoter
- Kalyani Tech Park Private Limited
- Acknowledgement no.
- ACK/KA/RERA/1251/309/PR/040924/008478
- Status on the register
- New Project Launch
- Stage
- Under Construction
- Work stage
- 45% complete, Q2 2026-27 report filed 15 Oct 2026
- Sales status
- Ongoing Sales (per RERA QPR Q2 2026-27, as of 15 Oct 2026)
- RERA approved on
- 26 Sept 2024
- Proposed completion
- 15 Sept 2029
- Land area
- 25 acres (1,01,171 sq m)
- Towers (this registration)
- 6
- Floors (this registration)
- 25
- Units (this registration)
- 2,736
- Plan approved by
- KIADB - Karnataka Industrial Areas Development Board
- Approved plan no.
- DO3-KIADB-00156/23-24/BP
- Plan approval date
- 14 May 2024
Dates on the register
- Completion filed with RERA
- 15 Sep 2029 (Karnataka RERA)
- Latest construction report
- 45% complete, Q2 2026-27, filed 15 Oct 2026 (promoter's report to RERA)
This is the date on the register now, and it may have been extended since registration.
We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.
Documents
Also filed on the register. We open a file here only after checking it for personal or financial details:
- Commencement Certificate
- Electricity Permission Letter
- Approved Building/Plotting Plan
- Sectional Drawing of the apartments
- Project Specifications
- Certificate from Registered Engineer indicating the structural safety of the building
- Proforma of Agreement for Sale
- Proforma of Allotment Letter
- Declaration (Form B)
- ESCOM/Electricity
- Fire Force Department
- Airport Authority of India
- KSPCB
- SEIAA
- Form-4 certificate (Chartered Accountant)
- Form-5 certificate (Architect)
- Form-6 certificate (Structural Engineer)
Location
About LivingTree by Kalyani Developers
Residential Project
- Developer
- Kalyani Tech Park Private Limited
- Project Type
- Residential/Group Housing
- Type
- Apartment
- Status
- Under Construction
- Total Land
- 25 Acres
- No. of Towers
- 6
- No. of Floors
- 25
- Total Units
- 2,736
- Handover Date
- 15 Sept 2029
- RERA No.
- PRM/KA/RERA/1251/309/PR/260924/007084
- Location
- Bengaluru North, Bangalore
About the developer
Kalyani Tech Park Private Limited
- Promoter on the register
- Kalyani Tech Park Private Limited
- Projects on the register
- 1
- Registering since
- 2024
- Complaints on the promoter
- 4, as shown on this registration
LivingTree by Kalyani Developers: questions answered
Where is LivingTree by Kalyani Developers located?
The Karnataka RERA register places LivingTree by Kalyani Developers in Bengaluru North, Bengaluru Urban.
What is the RERA number of LivingTree by Kalyani Developers?
The Karnataka RERA registration number of LivingTree by Kalyani Developers is PRM/KA/RERA/1251/309/PR/260924/007084, approved on 26 Sept 2024.
Who is the promoter of LivingTree by Kalyani Developers?
The promoter filed on the Karnataka RERA register is Kalyani Tech Park Private Limited.
When is LivingTree by Kalyani Developers expected to be completed?
The proposed completion date filed on the register is 15 Sept 2029.
How big is LivingTree by Kalyani Developers?
The register lists LivingTree by Kalyani Developers with 2,736 units, 6 towers and about 25 acres of land.
What is the latest construction progress of LivingTree by Kalyani Developers?
The quarterly report for Q2 2026-27, filed on 15 Oct 2026, shows construction 45% complete and 2,287 of 2,736 units booked.
Where does this information about LivingTree by Kalyani Developers come from?
From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.
Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.