Skip to main content
PropSarathi

Registered Project

Nearing Handover

APPLE REALMART PRIVATE LIMITED

BCM Vertex

Site No. 56 (Old No. 33), Industrial Suburb, Municipal Ward No. 10 of Mahalakshmipura (PID. NO. 10-1-56), Marappanapalya, Bengaluru North, Bengaluru Urban, Karnataka - 560022

Total Units
11
Floors
10
Towers
1
Total Area
0.87 Acres
Handover
28 Feb 2027

RERA progress

Stage 2 of 4 · RERA approved
  1. RERA applied(completed)
  2. RERA approved(current stage)
  3. Under construction(upcoming)
  4. Handover(upcoming)

RERA Approved

30 Mar 2023

PRM/KA/RERA/1251/309/PR/300323/005831

Est. Handover as per RERA

28 Feb 2027

Configurations & unit mix

Office Space11

The promoter's RERA report, Q1 2026-27, filed 15 Oct 2026, by its own types and totals, which don't line up with the rows above. Types listed more than once are added together: COMMERCIAL 3 of 11 available.

The register doesn't list prices, so none are shown here.

Latest quarterly report on the register

Construction progress

Construction complete87%

Quarter
Q1 2026-27
Filed on
15 Oct 2026
Units booked
8 of 11
Units available
3
Reports on file
4

Amenities

  • Electricity
  • CCTV Surveillance
  • Power Backup
  • Water and Sanitation

RERA & approvals

Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/309/PR/300323/005831)

Complaints on the register: 0 recorded on this project; 0 on the promoter's record, as shown on this registration

These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.

RERA registration
PRM/KA/RERA/1251/309/PR/300323/005831
Registered as
BCM VERTEX
Promoter
APPLE REALMART PRIVATE LIMITED
Acknowledgement no.
ACK/KA/RERA/1251/309/PR/100323/006935
Status on the register
Ongoing
Stage
Nearing Handover
Work stage
87% complete, Q1 2026-27 report filed 15 Oct 2026
Sales status
Ongoing Sales (per RERA QPR Q1 2026-27, as of 15 Oct 2026)
RERA approved on
30 Mar 2023
Proposed completion
28 Feb 2027
Land area
0.87 acres (3,526 sq m)
Towers (this registration)
1
Floors (this registration)
10
Units (this registration)
11
Plan approved by
BBMP - Bruhat Bengaluru Mahanagara Palike
Approved plan no.
BBMP/CC/9916/22-23
Plan approval date
22 Dec 2022
Land use
Commercial

Dates on the register

Completion filed with RERA
28 Feb 2027 (Karnataka RERA)
Latest construction report
87% complete, Q1 2026-27, filed 15 Oct 2026 (promoter's report to RERA)

This is the date on the register now, and it may have been extended since registration.

We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.

Documents

Also filed on the register. We open a file here only after checking it for personal or financial details:

  • Commencement Certificate
  • Electricity Permission Letter
  • Water Permission Letter
  • Approved Layout Plan
  • Approved Building/Plotting Plan
  • Existing Layout Plan
  • Existing Section Plan and Specification
  • Sectional Drawing of the apartments
  • Project Specifications
  • Approved Section Of Building/Infrastructure Plan of Plotting
  • Area Development Plan Of Project Area
  • Certificate from Registered Engineer indicating the structural safety of the building
  • Advocate Search Report
  • Urban Land Ceiling
  • Collaboration Agreement/Development Agreement/Joint Development Agreement/Other Agreement
  • Change of Land Use
  • District Magistrate
  • Conversion Certificate under section 95 of the KLR Act 1964
  • Any other document (Rights/Title/Interest/Name)
  • Proforma of Agreement for Sale

Location

About BCM Vertex

Commercial IT/BT Office Building Comprises of 11 Units of different dimensions

Developer
APPLE REALMART PRIVATE LIMITED
Type
Commercial
Status
Nearing Handover
Total Land
0.87 Acres
No. of Towers
1
No. of Floors
10
Total Units
11
Handover Date
28 Feb 2027
RERA No.
PRM/KA/RERA/1251/309/PR/300323/005831
Location
Bengaluru North, Bangalore

About the developer

APPLE REALMART PRIVATE LIMITED

Promoter on the register
APPLE REALMART PRIVATE LIMITED
Projects on the register
1
Registering since
2023
Complaints on the promoter
0, as shown on this registration

BCM Vertex: questions answered

Where is BCM Vertex located?

The Karnataka RERA register places BCM Vertex in Bengaluru North, Bengaluru Urban.

What is the RERA number of BCM Vertex?

The Karnataka RERA registration number of BCM Vertex is PRM/KA/RERA/1251/309/PR/300323/005831, approved on 30 Mar 2023.

Who is the promoter of BCM Vertex?

The promoter filed on the Karnataka RERA register is APPLE REALMART PRIVATE LIMITED.

When is BCM Vertex expected to be completed?

The proposed completion date filed on the register is 28 Feb 2027.

How big is BCM Vertex?

The register lists BCM Vertex with 11 units, 1 tower and about 0.87 acres of land.

What is the latest construction progress of BCM Vertex?

The quarterly report for Q1 2026-27, filed on 15 Oct 2026, shows construction 87% complete and 8 of 11 units booked.

Where does this information about BCM Vertex come from?

From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.

Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.