Registered Project
Under ConstructionNETRA SOFTWARE TECHNOLOGIES PRIVATE LIMITED
Assetz Sora & Saki Phase 2
PLOT Nos. R-9-D1, R-9-D2, R-9-D1-P & R-9-D2-P OF HITECH, DEFENCE & AEROSPACE PARK, (HARDWARE SECTOR) COMPRISED IN SURVEY Nos. 176, 177, 470, 471, OF BAGALUR VILLAGE AND SURVEY NO. 176 & 82 OF HOOVINAYAKANAHALLI VILLAGE, JALA HOBLI,BENGALURU NORTH YELAHANKA TALUK, BENGALURU URBAN DIST., Bengaluru North, Bengaluru Urban, Karnataka - 562110
- Total Units
- 634
- Floors
- 18
- Towers
- 3
- Total Area
- 2.45 Acres
- Handover
- 31 Jul 2029
RERA progress
Stage 3 of 4 · Under construction- RERA applied(completed)
- RERA approved(completed)
- Under construction(current stage)
- Handover(upcoming)
RERA Approved
21 May 2024
PRM/KA/RERA/1251/309/PR/210524/006929
Est. Handover as per RERA
31 Jul 2029
Configurations & unit mix
| 2BHK | 278 | 996 sq ft |
|---|---|---|
| EWS/STUDIO | 278 | |
| 3BHK | 436 | 1,139 – 1,182 sq ft |
The promoter's RERA report, Q2 2026-27, filed 15 Oct 2026, by its own types and totals, which don't line up with the rows above. Types listed more than once are added together: 2 BHK 129 of 206 available; 3 BHK 134 of 222 available; Studio 129 of 206 available.
The register doesn't list prices, so none are shown here.
Latest quarterly report on the register
Construction progress
Construction complete29%
- Quarter
- Q2 2026-27
- Filed on
- 15 Oct 2026
- Units booked
- 242 of 634
- Units available
- 392
- Reports on file
- 4
Amenities
- Electricity
- CCTV Surveillance
- Club House
- Community Hall
- Outdoor Sports facility
- Indoor Sports facility
- Swimming Pool
- Gym
- Parks
- Power Backup
- Water and Sanitation
- Air Conditioning
RERA & approvals
Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/309/PR/210524/006929)
Complaints on the register: 0 recorded on this project; 0 on the promoter's record, as shown on this registration
These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.
- RERA registration
- PRM/KA/RERA/1251/309/PR/210524/006929
- Registered as
- Assetz Sora & Saki Phase 2
- Promoter
- NETRA SOFTWARE TECHNOLOGIES PRIVATE LIMITED
- Acknowledgement no.
- ACK/KA/RERA/1251/309/PR/140524/008138
- Status on the register
- New Project Launch
- Stage
- Under Construction
- Work stage
- 29% complete, Q2 2026-27 report filed 15 Oct 2026
- Sales status
- Ongoing Sales (per RERA QPR Q2 2026-27, as of 15 Oct 2026)
- RERA approved on
- 21 May 2024
- Proposed completion
- 31 Jul 2029
- Land area
- 2.45 acres (9,917 sq m)
- Towers (this registration)
- 3
- Floors (this registration)
- 18
- Units (this registration)
- 634
- Plan approved by
- KIADB - Karnataka Industrial Areas Development Board
- Approved plan no.
- DO3-KIADB-00018/23-24/BP
- Plan approval date
- 15 Feb 2024
- Land use
- Residential
Dates on the register
- Completion filed with RERA
- 31 Jul 2029 (Karnataka RERA)
- Latest construction report
- 29% complete, Q2 2026-27, filed 15 Oct 2026 (promoter's report to RERA)
This is the date on the register now, and it may have been extended since registration.
We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.
Documents
Also filed on the register. We open a file here only after checking it for personal or financial details:
- Commencement Certificate
- Electricity Permission Letter
- Water Permission Letter
- Approved Building/Plotting Plan
- Sectional Drawing of the apartments
- Project Specifications
- Approved Section Of Building/Infrastructure Plan of Plotting
- Certificate from Registered Engineer indicating the structural safety of the building
- Advocate Search Report
- Conversion Certificate under section 95 of the KLR Act 1964
- Brochure
- Declaration (Form B)
- ESCOM/Electricity
- KWSSB/Water
- Fire Force Department
- Airport Authority of India
- SEIAA
- BSNL
- Form-4 certificate (Chartered Accountant)
- Form-5 certificate (Architect)
Location
About Assetz Sora & Saki Phase 2
Residential
- Developer
- NETRA SOFTWARE TECHNOLOGIES PRIVATE LIMITED
- Project Type
- Residential/Group Housing
- Type
- Apartment
- Status
- Under Construction
- Total Land
- 2.45 Acres
- No. of Towers
- 3
- No. of Floors
- 18
- Total Units
- 634
- Handover Date
- 31 Jul 2029
- RERA No.
- PRM/KA/RERA/1251/309/PR/210524/006929
- Location
- Bengaluru North, Bangalore
About the developer
NETRA SOFTWARE TECHNOLOGIES PRIVATE LIMITED
- Promoter on the register
- NETRA SOFTWARE TECHNOLOGIES PRIVATE LIMITED
- Projects on the register
- 2
- Registering since
- 2024
- Complaints on the promoter
- 0, as shown on this registration
Assetz Sora & Saki Phase 2: questions answered
Where is Assetz Sora & Saki located?
The Karnataka RERA register places Assetz Sora & Saki in Bengaluru North, Bengaluru Urban.
What is the RERA number of Assetz Sora & Saki?
The Karnataka RERA registration number of Assetz Sora & Saki is PRM/KA/RERA/1251/309/PR/210524/006929, approved on 21 May 2024.
Who is the promoter of Assetz Sora & Saki?
The promoter filed on the Karnataka RERA register is NETRA SOFTWARE TECHNOLOGIES PRIVATE LIMITED.
When is Assetz Sora & Saki expected to be completed?
The proposed completion date filed on the register is 31 Jul 2029.
How big is Assetz Sora & Saki?
The register lists Assetz Sora & Saki with 634 units, 3 towers and about 2.45 acres of land.
What is the latest construction progress of Assetz Sora & Saki?
The quarterly report for Q2 2026-27, filed on 15 Oct 2026, shows construction 29% complete and 242 of 634 units booked.
Where does this information about Assetz Sora & Saki come from?
From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.
Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.