Registered Project
Ready (per RERA completion date)Marudhar Infra
Arena
Municipal No. 152/152/144, Ananthapura Village, Yehalanka Hobli 560078
- Floors
- 3
- Towers
- 1
- Handover
- 30 Sept 2024
RERA progress
Stage 4 of 4 · Handover- RERA applied(completed)
- RERA approved(completed)
- Under construction(completed)
- Handover(current stage)
RERA Approved
29 Oct 2020
PRM/KA/RERA/1251/309/PR/201029/003672
Est. Handover as per RERA
30 Sep 2024
Developer target: 30 Sept 2024
RERA & approvals
Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/309/PR/201029/003672)
Complaints on the register: 0 recorded on this project; 0 on the promoter's record, as shown on this registration
These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.
- RERA registration
- PRM/KA/RERA/1251/309/PR/201029/003672
- Registered as
- Arena
- Promoter
- Marudhar Infra
- Acknowledgement no.
- ACK/KA/RERA/1251/309/PR/200924/004252
- Status on the register
- New Project Launch
- Stage
- Ready (per RERA completion date)
- RERA approved on
- 29 Oct 2020
- Proposed completion
- 30 Sept 2024
- Towers (this registration)
- 1
- Floors (this registration)
- 3
- Plan approved by
- BBMP - Bruhat Bengaluru Mahanagara Palike
Dates on the register
- Completion filed with RERA
- 30 Sep 2024 (Karnataka RERA)
This date has passed. Our copy of the register has no handover dates, so it can't tell you whether homes were delivered. This is the date on the register now, and it may have been extended since registration.
We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.
Documents
Also filed on the register. We open a file here only after checking it for personal or financial details:
- Airport Authority of India
- Approval/NOC under Sec 14 of the KTCP Act
- Approved Building/Plotting Plan
- Approved Layout Plan
- Approved Section Of Building/Infrastructure Plan of Plotting
- Area Development Plan Of Project Area
- Bangalore Urban Arts Commission
- BESCOM
- BMRCL
- Brochure of Current Project
- BSNL
- Certificate from Registered Engineer indicating the structural safety of the building (for Apartments)
- Change of Land Use
- Coastal Regulation Zone Authority
- Commencement Certificate
- Conversion Certificate under Sec 95 of the KLR Act 1961
- Existing Layout Plan
- Existing Section Plan and Specification
- Fire Force Department
- Inspector of Factories Controller of explosives Railways
Location
About Arena
All that piece and parcel of the property in New Municipal No. 152/152/144, formed in Sy.No.61, measuring 16533 sq.ft., situated at Ananthapura Village, Yelahanka Hobli, Bangalore North Taluk
- Developer
- Marudhar Infra
- Project Type
- Mixed Development
- Type
- Mixed Development
- Status
- Ready (per RERA completion date)
- No. of Towers
- 1
- No. of Floors
- 3
- Handover Date
- 30 Sept 2024
- RERA No.
- PRM/KA/RERA/1251/309/PR/201029/003672
- Location
- Bengaluru North, Bangalore
About the developer
Marudhar Infra
- Promoter on the register
- Marudhar Infra
- Projects on the register
- 2
- Registering since
- 2020
- Complaints on the promoter
- 0, as shown on this registration
Arena: questions answered
Where is Arena located?
The Karnataka RERA register places Arena in Bengaluru North, Bengaluru Urban.
What is the RERA number of Arena?
The Karnataka RERA registration number of Arena is PRM/KA/RERA/1251/309/PR/201029/003672, approved on 29 Oct 2020.
Who is the promoter of Arena?
The promoter filed on the Karnataka RERA register is Marudhar Infra.
What completion date was filed for Arena?
The completion date filed on the register was 30 Sept 2024. Check the register for any extension.
How big is Arena?
The register lists Arena with 1 tower.
Where does this information about Arena come from?
From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.
Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.