Registered Project
TOTAL ENVIRONMENT BUILDING SYSTEMS PVT LTD
After The Rain Phase III
Survey numbers 354/1B, 354/2, 231/3, 244/1, 244/2, 244/3, 244/4, 245/3, SIR MVIT COLLEGE ROAD, Bettahalasuru Village Jala Hobli, Bengaluru North, Bengaluru Urban, Karnataka - 562157
- Total Units
- 36
- Floors
- 1
- Towers
- 1
- Total Area
- 7.74 Acres
- Handover
- 30 Apr 2032
RERA progress
Stage 3 of 4 · Under construction- RERA applied(completed)
- RERA approved(completed)
- Under construction(current stage)
- Handover(upcoming)
RERA Approved
16 Aug 2025
PRM/KA/RERA/1251/309/PR/160825/008002
Est. Handover as per RERA
30 Apr 2032
Configurations & unit mix
| V80 | 6 |
|---|---|
| V50a | 2 |
| V30c | 6 |
| V30a | 4 |
| V45 | 18 |
The promoter's RERA report, Q2 2026-27, filed 15 Oct 2026, by its own types and totals, which don't line up with the rows above. Types listed more than once are added together: 3 BHK 0 of 18 available; 4 BHK 7 of 18 available.
The register doesn't list prices, so none are shown here.
Latest quarterly report on the register
Construction progress
Construction complete3%
- Quarter
- Q2 2026-27
- Filed on
- 15 Oct 2026
- Units booked
- 29 of 36
- Units available
- 7
- Reports on file
- 4
Amenities
- Electricity
- Club House
- Parks
RERA & approvals
Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/309/PR/160825/008002)
Complaints on the register: 0 recorded on this project; 14 on the promoter's record, as shown on this registration
These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.
- RERA registration
- PRM/KA/RERA/1251/309/PR/160825/008002
- Registered as
- After The Rain Phase III
- Promoter
- TOTAL ENVIRONMENT BUILDING SYSTEMS PVT LTD
- Acknowledgement no.
- ACK/KA/RERA/1251/309/PR/090525/009200
- Status on the register
- New Project Launch
- Stage
- Under Construction
- Work stage
- 3% complete, Q2 2026-27 report filed 15 Oct 2026
- Sales status
- Ongoing Sales (per RERA QPR Q2 2026-27, as of 15 Oct 2026)
- RERA approved on
- 16 Aug 2025
- Proposed completion
- 30 Apr 2032
- Land area
- 7.74 acres (31,312 sq m)
- Towers (this registration)
- 1
- Floors (this registration)
- 1
- Units (this registration)
- 36
- Plan approved by
- Local Planing Authority
- Approved plan no.
- 105/2024-25
- Plan approval date
- 27 Mar 2025
- Land use
- Residential
Dates on the register
- Completion filed with RERA
- 30 Apr 2032 (Karnataka RERA)
- Latest construction report
- 3% complete, Q2 2026-27, filed 15 Oct 2026 (promoter's report to RERA)
This is the date on the register now, and it may have been extended since registration.
We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.
Documents
Also filed on the register. We open a file here only after checking it for personal or financial details:
- Commencement Certificate
- Approved Building Plan
- Sectional Drawing of the apartments
- Certificate from Registered Engineer indicating the structural safety of the building
- Project Specifications
- Relinquishment Deed
- Proforma of Agreement for Sale
- Proforma of Allotment Letter
- Declaration (Form B)
- Advocate Search Report
- ESCOM/Electricity
- KWSSB/Water
- KSPCB
- SEIAA
- Fire Force Department
- Airport Authority of India
- BSNL
- Lift Authorities
- BMRCL
- NOC in case of building proposals abutting to neighbouring properties
Location
About After The Rain Phase III
Residential Group Housing comprises of 36 villas of different dimensions in the Project After the Rain
- Developer
- TOTAL ENVIRONMENT BUILDING SYSTEMS PVT LTD
- Project Type
- Residential/Group Housing
- Type
- Apartment
- Status
- Under Construction
- Total Land
- 7.74 Acres
- No. of Towers
- 1
- No. of Floors
- 1
- Total Units
- 36
- Handover Date
- 30 Apr 2032
- RERA No.
- PRM/KA/RERA/1251/309/PR/160825/008002
- Location
- Bengaluru North, Bangalore
About the developer
TOTAL ENVIRONMENT BUILDING SYSTEMS PVT LTD
- Promoter on the register
- TOTAL ENVIRONMENT BUILDING SYSTEMS PVT LTD
- Projects on the register
- 2
- Registering since
- 2024
- Complaints on the promoter
- 14, as shown on this registration
After The Rain Phase III: questions answered
Where is After The Rain located?
The Karnataka RERA register places After The Rain in Bengaluru North, Bengaluru Urban.
What is the RERA number of After The Rain?
The Karnataka RERA registration number of After The Rain is PRM/KA/RERA/1251/309/PR/160825/008002, approved on 16 Aug 2025.
Who is the promoter of After The Rain?
The promoter filed on the Karnataka RERA register is TOTAL ENVIRONMENT BUILDING SYSTEMS PVT LTD.
When is After The Rain expected to be completed?
The proposed completion date filed on the register is 30 Apr 2032.
How big is After The Rain?
The register lists After The Rain with 36 units, 1 tower and about 7.74 acres of land.
What is the latest construction progress of After The Rain?
The quarterly report for Q2 2026-27, filed on 15 Oct 2026, shows construction 3% complete and 29 of 36 units booked.
Where does this information about After The Rain come from?
From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.
Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.