Skip to main content
PropSarathi

Registered Project

Ready (per RERA completion date)

Unnathi Vaibhavi

SURVEY NO 99 KHATHA NO 96 HORAMAVU AGARA VILLAGE, K R PURAM HOBLI WARD NO 25 560036

Floors
3
Towers
1
Handover
2 Mar 2023

RERA progress

Stage 4 of 4 · Handover
  1. RERA applied(completed)
  2. RERA approved(completed)
  3. Under construction(completed)
  4. Handover(current stage)

RERA Approved

11 Jul 2019

PRM/KA/RERA/1251/446/PR/190711/002666

Est. Handover as per RERA

2 Mar 2023

RERA & approvals

Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/446/PR/190711/002666)

Complaints on the register: 0 recorded on this project; the promoter's count isn't shown here, so check the register

These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.

RERA registration
PRM/KA/RERA/1251/446/PR/190711/002666
Registered as
UNNATHI VAIBHAVI
Acknowledgement no.
ACK/KA/RERA/1251/446/PR/190411/003216
Status on the register
New Project Launch
Stage
Ready (per RERA completion date)
RERA approved on
11 Jul 2019
Proposed completion
2 Mar 2023
Towers (this registration)
1
Floors (this registration)
3
Plan approved by
BBMP - Bruhat Bengaluru Mahanagara Palike

Dates on the register

Completion filed with RERA
2 Mar 2023 (Karnataka RERA)

This date has passed. Our copy of the register has no handover dates, so it can't tell you whether homes were delivered. This is the date on the register now, and it may have been extended since registration.

We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.

Documents

Also filed on the register. We open a file here only after checking it for personal or financial details:

  • Approved Building/Plotting Plan
  • Approved Layout Plan
  • Approved Section Of Building/Infrastructure Plan of Plotting
  • Area Development Plan Of Project Area
  • Brochure of Current Project
  • Change of Land Use
  • Commencement Certificate
  • Conversion Certificate under Sec 95 of the KLR Act 1961
  • Existing Layout Plan
  • Existing Section Plan and Specification
  • KSPCB
  • Proforma of Agreement for Sale
  • Project Specification

Location

About Unnathi Vaibhavi

RESIDENTIAL APARTMENT WITH 176 FLATS AND ALL AMENITIES.

Project Type
Residential/Group Housing
Type
Residential/Group Housing
Status
Ready (per RERA completion date)
No. of Towers
1
No. of Floors
3
Handover Date
2 Mar 2023
RERA No.
PRM/KA/RERA/1251/446/PR/190711/002666
Location
Bengaluru East, Bangalore

Unnathi Vaibhavi: questions answered

Where is Unnathi Vaibhavi located?

The Karnataka RERA register places Unnathi Vaibhavi in Bengaluru East, Bengaluru Urban.

What is the RERA number of Unnathi Vaibhavi?

The Karnataka RERA registration number of Unnathi Vaibhavi is PRM/KA/RERA/1251/446/PR/190711/002666, approved on 11 Jul 2019.

What completion date was filed for Unnathi Vaibhavi?

The completion date filed on the register was 2 Mar 2023. Check the register for any extension.

How big is Unnathi Vaibhavi?

The register lists Unnathi Vaibhavi with 1 tower.

Where does this information about Unnathi Vaibhavi come from?

From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.

Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.