Registered Project
New LaunchRegistered project (name under review)
Bengaluru East, Bangalore
- Total Plots
- 48
- Total Area
- 2.11 Acres
- Handover
- 31 Dec 2028
RERA progress
Stage 2 of 4 · RERA approved- RERA applied(completed)
- RERA approved(current stage)
- Under construction(upcoming)
- Handover(upcoming)
RERA Approved
6 Mar 2026
PRM/KA/RERA/1251/446/PR/060326/008509
Est. Handover as per RERA
31 Dec 2028
Configurations & unit mix
| ODD SITES | 20 | about 1,089 sq ft each |
|---|---|---|
| 6.10 X 9.14 M | 15 | about 600 sq ft each |
| 9.14 X 12.19 M | 13 | about 1,199 sq ft each |
The register doesn't list prices, so none are shown here.
Latest quarterly report on the register
Construction progress
Construction complete70%
- Quarter
- Q2 2026-27
- Filed on
- 13 Oct 2026
- Reports on file
- 3
RERA & approvals
Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/446/PR/060326/008509)
Complaints on the register: 0 recorded on this project; the promoter's count isn't shown here, so check the register
These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.
- RERA registration
- PRM/KA/RERA/1251/446/PR/060326/008509
- Acknowledgement no.
- ACK/KA/RERA/1251/446/PR/200226/010026
- Status on the register
- Ongoing
- Stage
- New Launch
- Work stage
- 70% complete, Q2 2026-27 report filed 13 Oct 2026
- RERA approved on
- 6 Mar 2026
- Proposed completion
- 31 Dec 2028
- Land area
- 2.11 acres (8,549 sq m)
- Plots (this registration)
- 48
- Plan approved by
- BDA - Bangalore Development Authority
- Approved plan no.
- PRL-337/1139/2025-26
- Plan approval date
- 30 May 2025
- Land use
- Residential
Dates on the register
- Completion filed with RERA
- 31 Dec 2028 (Karnataka RERA)
- Latest construction report
- 70% complete, Q2 2026-27, filed 13 Oct 2026 (promoter's report to RERA)
This is the date on the register now, and it may have been extended since registration.
We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.
Documents
Also filed on the register. We open a file here only after checking it for personal or financial details:
- Approval Layout Order / Technical Sanction Letter
- Approved Layout Plan/Demarcation Plan
- Project Specifications
- Relinquishment Deed
- Proforma of Agreement for Sale
- Proforma of Allotment Letter
- Declaration (Form B)
- Advocate Search Report
- NOC from ESCOMs
- NOC for Water
- KSPCB (If Applicable)
- SEIAA (If Applicable)
- Form-4 certificate (Chartered Accountant)
- Form-6 certificate (Structural Engineer)
Location
About Registered project (name under review)
- Type
- Plotted Development
- Status
- New Launch
- Total Land
- 2.11 Acres
- Total Plots
- 48
- Handover Date
- 31 Dec 2028
- RERA No.
- PRM/KA/RERA/1251/446/PR/060326/008509
- Location
- Bengaluru East, Bangalore
Registered project (name under review): questions answered
Where is Registered project (name under review) located?
The Karnataka RERA register places Registered project (name under review) in Bengaluru East, Bengaluru Urban.
What is the RERA number of Registered project (name under review)?
The Karnataka RERA registration number of Registered project (name under review) is PRM/KA/RERA/1251/446/PR/060326/008509, approved on 6 Mar 2026.
When is Registered project (name under review) expected to be completed?
The proposed completion date filed on the register is 31 Dec 2028.
How big is Registered project (name under review)?
The register lists Registered project (name under review) with 48 plots and about 2.11 acres of land.
What is the latest construction progress of Registered project (name under review)?
The quarterly report for Q2 2026-27, filed on 13 Oct 2026, shows construction 70% complete.
Where does this information about Registered project (name under review) come from?
From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.
Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.