Registered Project

Under Construction

Nithya Infra Sunshine

Sy No 113/3, Chelkere Village, Horamavu, K R Puram Hobli, Bangalore, Bengaluru East, Bengaluru Urban, Karnataka - 560043

Total Units
40
Floors
3
Towers
1
Total Area
0.58 Acres
Handover
31 Dec 2027

RERA progress

Stage 3 of 4 · Under construction
  1. RERA applied(completed)
  2. RERA approved(completed)
  3. Under construction(current stage)
  4. Handover(upcoming)

RERA Approved

17 Jun 2025

PRM/KA/RERA/1251/446/PR/170625/007844

Est. Handover as per RERA

31 Dec 2027

Configurations & unit mix

4BHK43 of 41,165 sq ft
2 BHK127 of 12647 – 672 sq ft
3BHK2412 of 24834 – 987 sq ft

Available from the promoter's RERA report, Q2 2026-27, filed 15 Oct 2026.

The register doesn't list prices, so none are shown here.

Latest quarterly report on the register

Construction progress

Construction complete87%

Quarter
Q2 2026-27
Filed on
15 Oct 2026
Units booked
18 of 40
Units available
22
Reports on file
4

Amenities

  • Electricity
  • Swimming Pool
  • Power Backup
  • Water and Sanitation

RERA & approvals

Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/446/PR/170625/007844)

Complaints on the register: 0 recorded on this project; the promoter's count isn't shown here, so check the register

These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.

RERA registration
PRM/KA/RERA/1251/446/PR/170625/007844
Registered as
Nithya Infra Sunshine
Acknowledgement no.
ACK/KA/RERA/1251/446/PR/050625/009286
Status on the register
New Project Launch
Stage
Under Construction
Work stage
87% complete, Q2 2026-27 report filed 15 Oct 2026
Sales status
Ongoing Sales (per RERA QPR Q2 2026-27, as of 15 Oct 2026)
RERA approved on
17 Jun 2025
Proposed completion
31 Dec 2027
Land area
0.58 acres (2,332 sq m)
Towers (this registration)
1
Floors (this registration)
3
Units (this registration)
40
Plan approved by
BBMP - Bruhat Bengaluru Mahanagara Palike
Approved plan no.
PRJ/6874/24-25
Plan approval date
11 Mar 2025
Land use
Residential

Dates on the register

Completion filed with RERA
31 Dec 2027 (Karnataka RERA)
Latest construction report
87% complete, Q2 2026-27, filed 15 Oct 2026 (promoter's report to RERA)

This is the date on the register now, and it may have been extended since registration.

We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.

Documents

Also filed on the register. We open a file here only after checking it for personal or financial details:

  • Approved Building Plan
  • Sectional Drawing of the apartments
  • Certificate from Registered Engineer indicating the structural safety of the building
  • Project Specifications
  • Brochure
  • Proforma of Agreement for Sale
  • Proforma of Allotment Letter
  • Advocate Search Report
  • ESCOM/Electricity
  • KWSSB/Water
  • Form-4 certificate (Chartered Accountant)
  • Form-5 certificate (Architect)
  • Form-6 certificate (Structural Engineer)

Location

About Nithya Infra Sunshine

Construction of 40 Residential Flats

Project Type
Residential/Group Housing
Type
Apartment
Status
Under Construction
Total Land
0.58 Acres
No. of Towers
1
No. of Floors
3
Total Units
40
Handover Date
31 Dec 2027
RERA No.
PRM/KA/RERA/1251/446/PR/170625/007844
Location
Bengaluru East, Bangalore

Nithya Infra Sunshine: questions answered

Where is Nithya Infra Sunshine located?

The Karnataka RERA register places Nithya Infra Sunshine in Bengaluru East, Bengaluru Urban.

What is the RERA number of Nithya Infra Sunshine?

The Karnataka RERA registration number of Nithya Infra Sunshine is PRM/KA/RERA/1251/446/PR/170625/007844, approved on 17 Jun 2025.

When is Nithya Infra Sunshine expected to be completed?

The proposed completion date filed on the register is 31 Dec 2027.

How big is Nithya Infra Sunshine?

The register lists Nithya Infra Sunshine with 40 units, 1 tower and about 0.58 acres of land.

What is the latest construction progress of Nithya Infra Sunshine?

The quarterly report for Q2 2026-27, filed on 15 Oct 2026, shows construction 87% complete and 18 of 40 units booked.

Where does this information about Nithya Infra Sunshine come from?

From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.

Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.