Skip to main content
PropSarathi

Registered Project

Under Construction

MANA CONSTRUCTIONS

Mana Cresta

Sy no 1/1 & 1/7 chikkanayakanahalli village, varthuru hobli, bangalore east taluk, Bangalore 560103, Bengaluru East, Bengaluru Urban, Karnataka - 560103

Total Units
180
Floors
8
Towers
4
Total Area
2.46 Acres
Handover
31 Dec 2028

RERA progress

Stage 3 of 4 · Under construction
  1. RERA applied(completed)
  2. RERA approved(completed)
  3. Under construction(current stage)
  4. Handover(upcoming)

RERA Approved

16 Dec 2024

PRM/KA/RERA/1251/446/PR/161224/007303

Est. Handover as per RERA

31 Dec 2028

Configurations & unit mix

The promoter's RERA report, Q2 2026-27, filed 15 Oct 2026, by its own types and totals. Types listed more than once are added together: 2.5 BHK 14 of 46 available; 3 BHK 52 of 120 available; 2 BHK 11 of 14 available.

The register doesn't list prices, so none are shown here.

Latest quarterly report on the register

Construction progress

Construction complete38%

Quarter
Q2 2026-27
Filed on
15 Oct 2026
Units booked
103 of 180
Units available
77
Reports on file
4

Amenities

  • Electricity
  • CCTV Surveillance
  • Club House
  • Outdoor Sports facility
  • Swimming Pool
  • Parks
  • Power Backup
  • Water and Sanitation
  • Air Conditioning

RERA & approvals

Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/446/PR/161224/007303)

Complaints on the register: 0 recorded on this project; 1 on the promoter's record, as shown on this registration

These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.

RERA registration
PRM/KA/RERA/1251/446/PR/161224/007303
Registered as
Mana Cresta
Promoter
MANA CONSTRUCTIONS
Acknowledgement no.
ACK/KA/RERA/1251/446/PR/081124/008646
Status on the register
New Project Launch
Stage
Under Construction
Work stage
38% complete, Q2 2026-27 report filed 15 Oct 2026
Sales status
Ongoing Sales (per RERA QPR Q2 2026-27, as of 15 Oct 2026)
RERA approved on
16 Dec 2024
Proposed completion
31 Dec 2028
Land area
2.46 acres (9,940 sq m)
Towers (this registration)
4
Floors (this registration)
8
Units (this registration)
180
Plan approved by
BDA - Bangalore Development Authority
Approved plan no.
BDA/TPM/EM/EO-1/TA-2/EAST/30/2024-25
Plan approval date
9 Oct 2024
Land use
Residential

Dates on the register

Completion filed with RERA
31 Dec 2028 (Karnataka RERA)
Latest construction report
38% complete, Q2 2026-27, filed 15 Oct 2026 (promoter's report to RERA)

This is the date on the register now, and it may have been extended since registration.

We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.

Documents

Also filed on the register. We open a file here only after checking it for personal or financial details:

  • Commencement Certificate
  • Electricity Permission Letter
  • Water Permission Letter
  • Project Specifications
  • Advocate Search Report
  • Conversion Certificate under section 95 of the KLR Act 1964
  • Proforma of Agreement for Sale
  • Proforma of Allotment Letter
  • Brochure
  • ESCOM/Electricity
  • KWSSB/Water
  • Fire Force Department
  • Airport Authority of India
  • KSPCB
  • SEIAA
  • BSNL
  • NOC in case of building proposals abutting to neighbouring properties
  • Form-4 certificate (Chartered Accountant)
  • Form-5 certificate (Architect)
  • Form-6 certificate (Structural Engineer)

Location

About Mana Cresta

Constructing Residential Project with Basement + Ground Floor + 8 Upper Floors of 180 Units at Sy no 1/1 & 1/7 chikkanayakanahalli village, varthuru hobli, bangalore east taluk

Developer
MANA CONSTRUCTIONS
Project Type
Residential/Group Housing
Type
Apartment
Status
Under Construction
Total Land
2.46 Acres
No. of Towers
4
No. of Floors
8
Total Units
180
Handover Date
31 Dec 2028
RERA No.
PRM/KA/RERA/1251/446/PR/161224/007303
Location
Bengaluru East, Bangalore

About the developer

MANA CONSTRUCTIONS

Promoter on the register
MANA CONSTRUCTIONS
Projects on the register
1
Registering since
2024
Complaints on the promoter
1, as shown on this registration

Mana Cresta: questions answered

Where is Mana Cresta located?

The Karnataka RERA register places Mana Cresta in Bengaluru East, Bengaluru Urban.

What is the RERA number of Mana Cresta?

The Karnataka RERA registration number of Mana Cresta is PRM/KA/RERA/1251/446/PR/161224/007303, approved on 16 Dec 2024.

Who is the promoter of Mana Cresta?

The promoter filed on the Karnataka RERA register is MANA CONSTRUCTIONS.

When is Mana Cresta expected to be completed?

The proposed completion date filed on the register is 31 Dec 2028.

How big is Mana Cresta?

The register lists Mana Cresta with 180 units, 4 towers and about 2.46 acres of land.

What is the latest construction progress of Mana Cresta?

The quarterly report for Q2 2026-27, filed on 15 Oct 2026, shows construction 38% complete and 103 of 180 units booked.

Where does this information about Mana Cresta come from?

From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.

Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.