Registered Project
Under ConstructionLORVEN VENTURES
Cascade Garden
@ KATHA NO 82/598/548/116/2/1 SY NO 116/8,116/6,116/7,116/9,116/5,116/2,116/4 of, Nagondanahalli Village, BBMP Ward No. 84, Bengaluru East, Bengaluru Urban, Karnataka - 560066
- Total Units
- 312
- Floors
- 9
- Towers
- 4
- Total Area
- 4.3 Acres
- Handover
- 28 Dec 2028
RERA progress
Stage 3 of 4 · Under construction- RERA applied(completed)
- RERA approved(completed)
- Under construction(current stage)
- Handover(upcoming)
RERA Approved
31 Dec 2024
PRM/KA/RERA/1251/446/PR/311224/007332
Est. Handover as per RERA
28 Dec 2028
Configurations & unit mix
| 3 BHK | 310 | 278 of 310 | 884 – 1,135 sq ft |
|---|---|---|---|
| 2 BHK | 2 | 2 of 2 | 782 sq ft |
Available from the promoter's RERA report, Q2 2026-27, filed 15 Oct 2026.
The register doesn't list prices, so none are shown here.
Latest quarterly report on the register
Construction progress
Construction complete60%
- Quarter
- Q2 2026-27
- Filed on
- 15 Oct 2026
- Units booked
- 14 of 312
- Units available
- 298
- Reports on file
- 4
Amenities
- Electricity
- Club House
- Swimming Pool
- Power Backup
- Piped Gas
RERA & approvals
Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/446/PR/311224/007332)
- RERA registration
- PRM/KA/RERA/1251/446/PR/311224/007332
- Registered as
- LORVEN CASCADE GARDEN
- Promoter
- LORVEN VENTURES
- Acknowledgement no.
- ACK/KA/RERA/1251/446/PR/151124/008668
- Status on the register
- New Project Launch
- Stage
- Under Construction
- Work stage
- 60% complete, Q2 2026-27 report filed 15 Oct 2026
- Sales status
- Ongoing Sales (per RERA QPR Q2 2026-27, as of 15 Oct 2026)
- RERA approved on
- 31 Dec 2024
- Proposed completion
- 28 Dec 2028
- Land area
- 4.3 acres (17,411 sq m)
- Towers (this registration)
- 4
- Floors (this registration)
- 9
- Units (this registration)
- 312
- Plan approved by
- BBMP - Bruhat Bengaluru Mahanagara Palike
- Approved plan no.
- BBMP/Addl.Dir/JDNORTH/0036/24-25
- Plan approval date
- 16 Oct 2024
- Land use
- Residential
Dates on the register
- Completion filed with RERA
- 28 Dec 2028 (Karnataka RERA)
- Latest construction report
- 60% complete, Q2 2026-27, filed 15 Oct 2026 (promoter's report to RERA)
This is the date on the register now, and it may have been extended since registration.
We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.
Documents
Also filed on the register. We open a file here only after checking it for personal or financial details:
- Commencement Certificate
- Electricity Permission Letter
- Water Permission Letter
- Approved Building/Plotting Plan
- Existing Section Plan and Specification
- Sectional Drawing of the apartments
- Project Specifications
- Approved Section Of Building/Infrastructure Plan of Plotting
- Area Development Plan Of Project Area
- Certificate from Registered Engineer indicating the structural safety of the building
- Advocate Search Report
- Collaboration Agreement/Development Agreement/Joint Development Agreement/Other Agreement
- Any other document (Rights/Title/Interest/Name)
- Proforma of Agreement for Sale
- Proforma of Allotment Letter
- Declaration (Form B)
Location
About Cascade Garden
Residential Apartment Comprises of 312 Flats of Different Dimensions
- Developer
- LORVEN VENTURES
- Project Type
- Residential/Group Housing
- Type
- Apartment
- Status
- Under Construction
- Total Land
- 4.3 Acres
- No. of Towers
- 4
- No. of Floors
- 9
- Total Units
- 312
- Handover Date
- 28 Dec 2028
- RERA No.
- PRM/KA/RERA/1251/446/PR/311224/007332
- Location
- Bengaluru East, Bangalore
About the developer
LORVEN VENTURES
- Promoter on the register
- LORVEN VENTURES
- Projects on the register
- 1
- Registering since
- 2024
Cascade Garden: questions answered
Where is Cascade Garden located?
The Karnataka RERA register places Cascade Garden in Bengaluru East, Bengaluru Urban.
What is the RERA number of Cascade Garden?
The Karnataka RERA registration number of Cascade Garden is PRM/KA/RERA/1251/446/PR/311224/007332, approved on 31 Dec 2024.
Who is the promoter of Cascade Garden?
The promoter filed on the Karnataka RERA register is LORVEN VENTURES.
When is Cascade Garden expected to be completed?
The proposed completion date filed on the register is 28 Dec 2028.
How big is Cascade Garden?
The register lists Cascade Garden with 312 units, 4 towers and about 4.3 acres of land.
What is the latest construction progress of Cascade Garden?
The quarterly report for Q2 2026-27, filed on 15 Oct 2026, shows construction 60% complete and 14 of 312 units booked.
Where does this information about Cascade Garden come from?
From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.
Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.