Registered Project
Ready (per RERA completion date)KEYSTONE PROJECTS
DSR Star Light
SY NO 133/7, GUNJUR VILLAGE VARTUR HOBLI 560066
- Floors
- 3
- Towers
- 1
- Handover
- 4 Sept 2023
RERA progress
Stage 4 of 4 · Handover- RERA applied(completed)
- RERA approved(completed)
- Under construction(completed)
- Handover(current stage)
RERA Approved
29 Oct 2020
PRM/KA/RERA/1251/446/PR/201029/003670
Est. Handover as per RERA
4 Sep 2023
Developer target: 4 Sept 2023
RERA & approvals
Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/446/PR/201029/003670)
Complaints on the register: 0 recorded on this project; 0 on the promoter's record, as shown on this registration
These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.
- RERA registration
- PRM/KA/RERA/1251/446/PR/201029/003670
- Registered as
- KEYSTONE DSR STAR LIGHT
- Promoter
- KEYSTONE PROJECTS
- Acknowledgement no.
- ACK/KA/RERA/1251/446/PR/201003/004275
- Status on the register
- New Project Launch
- Stage
- Ready (per RERA completion date)
- RERA approved on
- 29 Oct 2020
- Proposed completion
- 4 Sept 2023
- Towers (this registration)
- 1
- Floors (this registration)
- 3
- Plan approved by
- BBMP - Bruhat Bengaluru Mahanagara Palike
Dates on the register
- Completion filed with RERA
- 4 Sep 2023 (Karnataka RERA)
This date has passed. Our copy of the register has no handover dates, so it can't tell you whether homes were delivered. This is the date on the register now, and it may have been extended since registration.
We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.
Documents
Also filed on the register. We open a file here only after checking it for personal or financial details:
- Airport Authority of India
- Approval/NOC under Sec 14 of the KTCP Act
- Approved Building/Plotting Plan
- Approved Section Of Building/Infrastructure Plan of Plotting
- Area Development Plan Of Project Area
- Bangalore Urban Arts Commission
- BESCOM
- BMRCL
- BSNL
- Certificate from Registered Engineer indicating the structural safety of the building (for Apartments)
- Coastal Regulation Zone Authority
- Commencement Certificate
- Conversion Certificate under Sec 95 of the KLR Act 1961
- Existing Section Plan and Specification
- Fire Force Department
- Inspector of Factories Controller of explosives Railways
- KSPCB
- Lift Authorities
- NOC in case of building proposals abutting to neighbouring properties
- Project Specification
Location
About DSR Star Light
S+G+2 WITH RESIDENTIAL BUILDING WITH 39 RESIDENTIAL UNITS
- Developer
- KEYSTONE PROJECTS
- Project Type
- Residential/Group Housing
- Type
- Residential/Group Housing
- Status
- Ready (per RERA completion date)
- No. of Towers
- 1
- No. of Floors
- 3
- Handover Date
- 4 Sept 2023
- RERA No.
- PRM/KA/RERA/1251/446/PR/201029/003670
- Location
- Bengaluru East, Bangalore
About the developer
KEYSTONE PROJECTS
- Promoter on the register
- KEYSTONE PROJECTS
- Projects on the register
- 1
- Registering since
- 2020
- Complaints on the promoter
- 0, as shown on this registration
DSR Star Light: questions answered
Where is DSR Star Light located?
The Karnataka RERA register places DSR Star Light in Bengaluru East, Bengaluru Urban.
What is the RERA number of DSR Star Light?
The Karnataka RERA registration number of DSR Star Light is PRM/KA/RERA/1251/446/PR/201029/003670, approved on 29 Oct 2020.
Who is the promoter of DSR Star Light?
The promoter filed on the Karnataka RERA register is KEYSTONE PROJECTS.
What completion date was filed for DSR Star Light?
The completion date filed on the register was 4 Sept 2023. Check the register for any extension.
How big is DSR Star Light?
The register lists DSR Star Light with 1 tower.
Where does this information about DSR Star Light come from?
From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.
Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.