Registered Project
Ready (per RERA completion date)M/s Jayani Builders and Developers
Jayani Paradise
Sy No 49/1 B.Chikkanna Layout, Mahadevapura Bangalore
- Floors
- 5
- Towers
- 2
- Handover
- 10 Jul 2023
RERA progress
Stage 4 of 4 · Handover- RERA applied(completed)
- RERA approved(completed)
- Under construction(completed)
- Handover(current stage)
RERA Approved
15 Feb 2019
PRM/KA/RERA/1251/446/PR/190215/002379
Est. Handover as per RERA
10 Jul 2023
RERA & approvals
Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/446/PR/190215/002379)
Complaints on the register: 0 recorded on this project; 0 on the promoter's record, as shown on this registration
These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.
- RERA registration
- PRM/KA/RERA/1251/446/PR/190215/002379
- Registered as
- Jayani Paradise
- Promoter
- M/s Jayani Builders and Developers
- Acknowledgement no.
- ACK/KA/RERA/1251/446/PR/181205/002878
- Status on the register
- New Project Launch
- Stage
- Ready (per RERA completion date)
- RERA approved on
- 15 Feb 2019
- Proposed completion
- 10 Jul 2023
- Towers (this registration)
- 2
- Floors (this registration)
- 5
- Plan approved by
- BBMP - Bruhat Bengaluru Mahanagara Palike
Dates on the register
- Completion filed with RERA
- 10 Jul 2023 (Karnataka RERA)
This date has passed. Our copy of the register has no handover dates, so it can't tell you whether homes were delivered. This is the date on the register now, and it may have been extended since registration.
We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.
Documents
Also filed on the register. We open a file here only after checking it for personal or financial details:
- Airport Authority of India
- Approval/NOC under Sec 14 of the KTCP Act
- Approved Building/Plotting Plan
- Approved Layout Plan
- Approved Section Of Building/Infrastructure Plan of Plotting
- Area Development Plan Of Project Area
- Bangalore Urban Arts Commission
- BESCOM
- BMRCL
- Brochure of Current Project
- BSNL
- Certificate from Registered Engineer indicating the structural safety of the building (for Apartments)
- Change of Land Use
- Coastal Regulation Zone Authority
- Commencement Certificate
- Conversion Certificate under Sec 95 of the KLR Act 1961
- Existing Layout Plan
- Existing Section Plan and Specification
- Fire Force Department
- Inspector of Factories Controller of explosives Railways
Location
About Jayani Paradise
good
- Developer
- M/s Jayani Builders and Developers
- Type
- Residential/Group Housing
- Status
- Ready (per RERA completion date)
- No. of Towers
- 2
- No. of Floors
- 5
- Handover Date
- 10 Jul 2023
- RERA No.
- PRM/KA/RERA/1251/446/PR/190215/002379
- Location
- Bengaluru East, Bangalore
About the developer
M/s Jayani Builders and Developers
- Promoter on the register
- M/s Jayani Builders and Developers
- Projects on the register
- 1
- Registering since
- 2019
- Complaints on the promoter
- 0, as shown on this registration
Jayani Paradise: questions answered
Where is Jayani Paradise located?
The Karnataka RERA register places Jayani Paradise in Bengaluru East, Bengaluru Urban.
What is the RERA number of Jayani Paradise?
The Karnataka RERA registration number of Jayani Paradise is PRM/KA/RERA/1251/446/PR/190215/002379, approved on 15 Feb 2019.
Who is the promoter of Jayani Paradise?
The promoter filed on the Karnataka RERA register is M/s Jayani Builders and Developers.
What completion date was filed for Jayani Paradise?
The completion date filed on the register was 10 Jul 2023. Check the register for any extension.
How big is Jayani Paradise?
The register lists Jayani Paradise with 2 towers.
Where does this information about Jayani Paradise come from?
From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.
Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.