Skip to main content
PropSarathi

Registered Project

Nearing Handover

SUMMIT REALTY

Ekaa by Summit

Survey No 135/3, Kithaganur Village, Bidarhalli Hobli, Bengaluru East, Bengaluru Urban, Karnataka - 560036

Total Units
59
Floors
4
Towers
1
Total Area
0.95 Acres
Handover
31 Dec 2026

RERA progress

Stage 2 of 4 · RERA approved
  1. RERA applied(completed)
  2. RERA approved(current stage)
  3. Under construction(upcoming)
  4. Handover(upcoming)

RERA Approved

20 Nov 2024

PRM/KA/RERA/1251/446/PR/201124/007242

Est. Handover as per RERA

31 Dec 2026

Configurations & unit mix

2 BHK3531 of 35724 – 800 sq ft
3BHK2412 of 24886 – 1,144 sq ft

Available from the promoter's RERA report, Q2 2026-27, filed 15 Oct 2026.

The register doesn't list prices, so none are shown here.

Latest quarterly report on the register

Construction progress

Construction complete85%

Quarter
Q2 2026-27
Filed on
15 Oct 2026
Units booked
16 of 59
Units available
43
Reports on file
4

Amenities

  • Electricity
  • CCTV Surveillance
  • Club House
  • Community Hall
  • Swimming Pool
  • Gym
  • Parks
  • Power Backup
  • Water and Sanitation

RERA & approvals

Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/446/PR/201124/007242)

Complaints on the register: 0 recorded on this project; 0 on the promoter's record, as shown on this registration

These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.

RERA registration
PRM/KA/RERA/1251/446/PR/201124/007242
Registered as
EKAA BY SUMMIT
Promoter
SUMMIT REALTY
Acknowledgement no.
ACK/KA/RERA/1251/446/PR/120824/008411
Status on the register
Ongoing
Stage
Nearing Handover
Work stage
85% complete, Q2 2026-27 report filed 15 Oct 2026
Sales status
Ongoing Sales (per RERA QPR Q2 2026-27, as of 15 Oct 2026)
RERA approved on
20 Nov 2024
Proposed completion
31 Dec 2026
Land area
0.95 acres (3,844 sq m)
Towers (this registration)
1
Floors (this registration)
4
Units (this registration)
59
Plan approved by
BDA - Bangalore Development Authority
Plan approval date
7 Aug 2023
Land use
Residential

Dates on the register

Completion filed with RERA
31 Dec 2026 (Karnataka RERA)
Latest construction report
85% complete, Q2 2026-27, filed 15 Oct 2026 (promoter's report to RERA)

This is the date on the register now, and it may have been extended since registration.

We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.

Documents

Also filed on the register. We open a file here only after checking it for personal or financial details:

  • Electricity Permission Letter
  • Water Permission Letter
  • Approved Layout Plan
  • Approved Building/Plotting Plan
  • Existing Layout Plan
  • Existing Section Plan and Specification
  • Sectional Drawing of the apartments
  • Project Specifications
  • Approved Section Of Building/Infrastructure Plan of Plotting
  • Area Development Plan Of Project Area
  • Certificate from Registered Engineer indicating the structural safety of the building
  • Advocate Search Report
  • Collaboration Agreement/Development Agreement/Joint Development Agreement/Other Agreement
  • Change of Land Use
  • Conversion Certificate under section 95 of the KLR Act 1964
  • Proforma of Agreement for Sale
  • Proforma of Allotment Letter
  • Brochure
  • Declaration (Form B)
  • ESCOM/Electricity

Location

About Ekaa by Summit

Residential apartment comprises of 59 units

Developer
SUMMIT REALTY
Project Type
Residential/Group Housing
Type
Apartment
Status
Nearing Handover
Total Land
0.95 Acres
No. of Towers
1
No. of Floors
4
Total Units
59
Handover Date
31 Dec 2026
RERA No.
PRM/KA/RERA/1251/446/PR/201124/007242
Location
Bengaluru East, Bangalore

About the developer

SUMMIT REALTY

Promoter on the register
SUMMIT REALTY
Projects on the register
1
Registering since
2024
Complaints on the promoter
0, as shown on this registration

Ekaa by Summit: questions answered

Where is Ekaa by Summit located?

The Karnataka RERA register places Ekaa by Summit in Bengaluru East, Bengaluru Urban.

What is the RERA number of Ekaa by Summit?

The Karnataka RERA registration number of Ekaa by Summit is PRM/KA/RERA/1251/446/PR/201124/007242, approved on 20 Nov 2024.

Who is the promoter of Ekaa by Summit?

The promoter filed on the Karnataka RERA register is SUMMIT REALTY.

When is Ekaa by Summit expected to be completed?

The proposed completion date filed on the register is 31 Dec 2026.

How big is Ekaa by Summit?

The register lists Ekaa by Summit with 59 units, 1 tower and about 0.95 acres of land.

What is the latest construction progress of Ekaa by Summit?

The quarterly report for Q2 2026-27, filed on 15 Oct 2026, shows construction 85% complete and 16 of 59 units booked.

Where does this information about Ekaa by Summit come from?

From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.

Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.