Registered Project

Ready (per RERA completion date)

Casa Flora

Sy.No.64/1, Katha No.91, Horamavu Agara Village, K.R.Puram Hobli, Ward No.25

Floors
3
Towers
1
Handover
30 Sept 2022

RERA progress

Stage 4 of 4 · Handover
  1. RERA applied(completed)
  2. RERA approved(completed)
  3. Under construction(completed)
  4. Handover(current stage)

RERA Approved

22 Nov 2018

PRM/KA/RERA/1251/446/PR/181122/002143

Est. Handover as per RERA

30 Sep 2022

Developer target: 30 Sept 2022

RERA & approvals

Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/446/PR/181122/002143)

Complaints on the register: 0 recorded on this project; the promoter's count isn't shown here, so check the register

These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.

RERA registration
PRM/KA/RERA/1251/446/PR/181122/002143
Registered as
CASA FLORA
Acknowledgement no.
ACK/KA/RERA/1251/446/PR/180705/002432
Status on the register
New Project Launch
Stage
Ready (per RERA completion date)
RERA approved on
22 Nov 2018
Proposed completion
30 Sept 2022
Towers (this registration)
1
Floors (this registration)
3
Plan approved by
BBMP - Bruhat Bengaluru Mahanagara Palike

Dates on the register

Completion filed with RERA
30 Sep 2022 (Karnataka RERA)

This date has passed. Our copy of the register has no handover dates, so it can't tell you whether homes were delivered. This is the date on the register now, and it may have been extended since registration.

We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.

Documents

Also filed on the register. We open a file here only after checking it for personal or financial details:

  • Approved Building/Plotting Plan
  • Approved Layout Plan
  • Approved Section Of Building/Infrastructure Plan of Plotting
  • Area Development Plan Of Project Area
  • Brochure of Current Project
  • Change of Land Use
  • Commencement Certificate
  • Conversion Certificate under Sec 95 of the KLR Act 1961
  • Existing Layout Plan
  • Existing Section Plan and Specification
  • Proforma For Sale Deed
  • Proforma of Agreement for Sale
  • Project Specification

Location

About Casa Flora

Residential Apartment

Project Type
Residential/Group Housing
Type
Residential/Group Housing
Status
Ready (per RERA completion date)
No. of Towers
1
No. of Floors
3
Handover Date
30 Sept 2022
RERA No.
PRM/KA/RERA/1251/446/PR/181122/002143
Location
Bengaluru East, Bangalore

Casa Flora: questions answered

Where is Casa Flora located?

The Karnataka RERA register places Casa Flora in Bengaluru East, Bengaluru Urban.

What is the RERA number of Casa Flora?

The Karnataka RERA registration number of Casa Flora is PRM/KA/RERA/1251/446/PR/181122/002143, approved on 22 Nov 2018.

What completion date was filed for Casa Flora?

The completion date filed on the register was 30 Sept 2022. Check the register for any extension.

How big is Casa Flora?

The register lists Casa Flora with 1 tower.

Where does this information about Casa Flora come from?

From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.

Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.