Skip to main content
PropSarathi

Registered Project

Ready (per RERA completion date)

DivyaSree Infrastructure Projects Private Limited

77° Life

157/2,157/3A,157/3B,159/1B, 77 Life, 77 Town Center, Yemalur Main Road, Off. Old Airport Road, Bengaluru East, Bengaluru Urban, Karnataka - 560037

Total Units
133
Floors
14
Towers
1
Total Area
2.27 Acres
Handover
31 Dec 2025

RERA progress

Stage 4 of 4 · Handover
  1. RERA applied(completed)
  2. RERA approved(completed)
  3. Under construction(completed)
  4. Handover(current stage)

RERA Approved

21 Dec 2022

PRM/KA/RERA/1251/446/PR/211222/005551

Est. Handover as per RERA

31 Dec 2025

Configurations & unit mix

3 BHK825 of 821,880 – 2,729 sq ft
4 BHK446 of 44979 – 3,270 sq ft
EWS 1BHK71 of 7438 sq ft

Available from the promoter's RERA report, Q3 2025-26, filed 14 Jan 2026 (over 9 months old).

The register doesn't list prices, so none are shown here.

Latest quarterly report on the register

Construction progress

Construction complete100%

Quarter
Q3 2025-26
Filed on
14 Jan 2026
Units booked
121 of 133
Units available
12

Amenities

  • Electricity
  • Club House
  • Swimming Pool
  • Gym
  • Parks
  • Power Backup
  • Piped Gas
  • Water and Sanitation

RERA & approvals

Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/446/PR/211222/005551)

Complaints on the register: 0 recorded on this project; 0 on the promoter's record, as shown on this registration

These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.

RERA registration
PRM/KA/RERA/1251/446/PR/211222/005551
Registered as
77° LIFE
Promoter
DivyaSree Infrastructure Projects Private Limited
Acknowledgement no.
ACK/KA/RERA/1251/446/PR/251122/006560
Status on the register
New Project Launch
Stage
Ready (per RERA completion date)
Work stage
100% complete, Q3 2025-26 report filed 14 Jan 2026 (over 9 months old)
RERA approved on
21 Dec 2022
Proposed completion
31 Dec 2025
Land area
2.27 acres (9,172 sq m)
Towers (this registration)
1
Floors (this registration)
14
Units (this registration)
133
Plan approved by
BBMP - Bruhat Bengaluru Mahanagara Palike
Approved plan no.
JTDP/LP/64/2010-11
Plan approval date
27 Apr 2022
Land use
Residential

Dates on the register

Completion filed with RERA
31 Dec 2025 (Karnataka RERA)
Latest construction report
100% complete, Q3 2025-26, filed 14 Jan 2026 (over 9 months old) (promoter's report to RERA)

This date has passed. Our copy of the register has no handover dates, so it can't tell you whether homes were delivered. This is the date on the register now, and it may have been extended since registration.

We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.

Documents

Also filed on the register. We open a file here only after checking it for personal or financial details:

  • Commencement Certificate
  • Electricity Permission Letter
  • Water Permission Letter
  • Approved Layout Plan
  • Approved Building/Plotting Plan
  • Existing Layout Plan
  • Existing Section Plan and Specification
  • Sectional Drawing of the apartments
  • Project Specifications
  • Approved Section Of Building/Infrastructure Plan of Plotting
  • Area Development Plan Of Project Area
  • Conversion Certificate under section 95 of the KLR Act 1964
  • Proforma of Agreement for Sale
  • ESCOM/Electricity
  • KWSSB/Water
  • Approval/NOC under section 109 of KLR Act 1961
  • Approval/NOC under section 14 of the KTCP Act
  • Fire Force Department
  • Airport Authority of India
  • KSPCB

Location

About 77° Life

Residential development of Tower A with 126 Apartments and 7 EWS units.

Developer
DivyaSree Infrastructure Projects Private Limited
Project Type
Residential/Group Housing
Type
Apartment
Status
Ready (per RERA completion date)
Total Land
2.27 Acres
No. of Towers
1
No. of Floors
14
Total Units
133
Handover Date
31 Dec 2025
RERA No.
PRM/KA/RERA/1251/446/PR/211222/005551
Location
Bengaluru East, Bangalore

About the developer

DivyaSree Infrastructure Projects Private Limited

Promoter on the register
DivyaSree Infrastructure Projects Private Limited
Projects on the register
1
Registering since
2022
Complaints on the promoter
0, as shown on this registration

77° Life: questions answered

Where is 77° Life located?

The Karnataka RERA register places 77° Life in Bengaluru East, Bengaluru Urban.

What is the RERA number of 77° Life?

The Karnataka RERA registration number of 77° Life is PRM/KA/RERA/1251/446/PR/211222/005551, approved on 21 Dec 2022.

Who is the promoter of 77° Life?

The promoter filed on the Karnataka RERA register is DivyaSree Infrastructure Projects Private Limited.

What completion date was filed for 77° Life?

The completion date filed on the register was 31 Dec 2025. Check the register for any extension.

How big is 77° Life?

The register lists 77° Life with 133 units, 1 tower and about 2.27 acres of land.

What is the latest construction progress of 77° Life?

The quarterly report for Q3 2025-26, filed on 14 Jan 2026, shows construction 100% complete and 121 of 133 units booked.

Where does this information about 77° Life come from?

From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.

Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.