Registered Project

Nearing Handover

VRR Golden Enclave PHASE-III

Sy.no 355/1 & 355/2 (Part), Hulimangala Village, Jigani Hobli, Anekal Taluk, Bengaluru Urban District, Anekal, Bengaluru Urban, Karnataka - 560100

Total Units
13
Floors
3
Towers
1
Total Area
0.88 Acres
Handover
30 Jun 2027

RERA progress

Stage 2 of 4 · RERA approved
  1. RERA applied(completed)
  2. RERA approved(current stage)
  3. Under construction(upcoming)
  4. Handover(upcoming)

RERA Approved

29 Apr 2025

PRM/KA/RERA/1251/308/PR/290425/007698

Est. Handover as per RERA

30 Jun 2027

Configurations & unit mix

Rowhouses13

The promoter's RERA report, Q2 2026-27, filed 13 Oct 2026, by its own types and totals, which don't line up with the rows above. Types listed more than once are added together: 3 BHK 7 of 13 available.

The register doesn't list prices, so none are shown here.

Latest quarterly report on the register

Construction progress

Construction complete99%

Quarter
Q2 2026-27
Filed on
13 Oct 2026
Units booked
6 of 13
Units available
7
Reports on file
4

Amenities

  • Electricity
  • CCTV Surveillance
  • Power Backup
  • Water and Sanitation

RERA & approvals

Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/308/PR/290425/007698)

Complaints on the register: 0 recorded on this project; the promoter's count isn't shown here, so check the register

These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.

RERA registration
PRM/KA/RERA/1251/308/PR/290425/007698
Registered as
VRR GOLDEN ENCLAVE PHASE-III
Acknowledgement no.
ACK/KA/RERA/1251/308/PR/300125/008913
Status on the register
Ongoing
Stage
Nearing Handover
Work stage
99% complete, Q2 2026-27 report filed 13 Oct 2026
Sales status
Ongoing Sales (per RERA QPR Q2 2026-27, as of 13 Oct 2026)
RERA approved on
29 Apr 2025
Proposed completion
30 Jun 2027
Land area
0.88 acres (3,569 sq m)
Towers (this registration)
1
Floors (this registration)
3
Units (this registration)
13
Plan approved by
BDA - Bangalore Development Authority
Approved plan no.
BDA/TPM/DLP-75/2011-12/2088/2024-25-DT:25.11.2024
Plan approval date
25 Nov 2024
Land use
Residential

Dates on the register

Completion filed with RERA
30 Jun 2027 (Karnataka RERA)
Latest construction report
99% complete, Q2 2026-27, filed 13 Oct 2026 (promoter's report to RERA)

This is the date on the register now, and it may have been extended since registration.

We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.

Documents

Also filed on the register. We open a file here only after checking it for personal or financial details:

  • Commencement Certificate
  • Approved Building Plan
  • Sectional Drawing of the apartments
  • Certificate from Registered Engineer indicating the structural safety of the building
  • Project Specifications
  • Brochure
  • Relinquishment Deed
  • Proforma of Agreement for Sale
  • Proforma of Allotment Letter
  • Advocate Search Report
  • ESCOM/Electricity
  • KWSSB/Water
  • KSPCB
  • Form-4 certificate (Chartered Accountant)
  • Form-5 certificate (Architect)
  • Form-6 certificate (Structural Engineer)

Location

About VRR Golden Enclave PHASE-III

Development of our project Golden Enclave Phase III consisting of 13 RowHouses situated at Hulimangala Village, Jigani Hobli, Anekal Taluk, Bengaluru , Anekal , Bengaluru Urban

Project Type
Residential/Group Housing
Type
Row Houses
Status
Nearing Handover
Total Land
0.88 Acres
No. of Towers
1
No. of Floors
3
Total Units
13
Handover Date
30 Jun 2027
RERA No.
PRM/KA/RERA/1251/308/PR/290425/007698
Location
Anekal, Bangalore

VRR Golden Enclave PHASE-III: questions answered

Where is VRR Golden Enclave located?

The Karnataka RERA register places VRR Golden Enclave in Anekal, Bengaluru Urban.

What is the RERA number of VRR Golden Enclave?

The Karnataka RERA registration number of VRR Golden Enclave is PRM/KA/RERA/1251/308/PR/290425/007698, approved on 29 Apr 2025.

When is VRR Golden Enclave expected to be completed?

The proposed completion date filed on the register is 30 Jun 2027.

How big is VRR Golden Enclave?

The register lists VRR Golden Enclave with 13 units, 1 tower and about 0.88 acres of land.

What is the latest construction progress of VRR Golden Enclave?

The quarterly report for Q2 2026-27, filed on 13 Oct 2026, shows construction 99% complete and 6 of 13 units booked.

Where does this information about VRR Golden Enclave come from?

From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.

Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.