Registered Project

Nearing Handover

Srikara Urban Park

Sy. No. 67/1, 67/2, 68/3 of Maragondanahalli Village, Jigani Hobli, Anekal Taluk, Bengaluru 560092

Floors
4
Towers
2
Handover
31 Mar 2027

RERA progress

Stage 2 of 4 · RERA approved
  1. RERA applied(completed)
  2. RERA approved(current stage)
  3. Under construction(upcoming)
  4. Handover(upcoming)

RERA Approved

31 Mar 2021

PRM/KA/RERA/1251/308/PR/210331/004075

Est. Handover as per RERA

31 Mar 2027

Configurations & unit mix

The promoter's RERA report, Q2 2026-27, filed 13 Oct 2026, by its own types and totals. Types listed more than once are added together: 2BHK 93 of 97 available; 3BHK 14 of 14 available; 2.5BHK 12 of 15 available.

The register doesn't list prices, so none are shown here.

Latest quarterly report on the register

Construction progress

Construction complete91%

Quarter
Q2 2026-27
Filed on
13 Oct 2026
Units booked
7 of 126
Units available
119
Reports on file
4

RERA & approvals

Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/308/PR/210331/004075)

Complaints on the register: 0 recorded on this project; the promoter's count isn't shown here, so check the register

These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.

RERA registration
PRM/KA/RERA/1251/308/PR/210331/004075
Registered as
SRIKARA URBAN PARK
Acknowledgement no.
ACK/KA/RERA/1251/308/PR/210211/004671
Status on the register
New Project Launch
Stage
Nearing Handover
Work stage
91% complete, Q2 2026-27 report filed 13 Oct 2026
Sales status
Ongoing Sales (per RERA QPR Q2 2026-27, as of 13 Oct 2026)
RERA approved on
31 Mar 2021
Proposed completion
31 Mar 2027
Towers (this registration)
2
Floors (this registration)
4
Plan approved by
BDA - Bangalore Development Authority

Dates on the register

Completion filed with RERA
31 Mar 2027 (Karnataka RERA)
Latest construction report
91% complete, Q2 2026-27, filed 13 Oct 2026 (promoter's report to RERA)

This is the date on the register now, and it may have been extended since registration.

We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.

Documents

Also filed on the register. We open a file here only after checking it for personal or financial details:

  • Advocate Search Report
  • Airport Authority of India
  • Any other document (Rights/Title/Interest/Name)
  • Approval/NOC under Sec 14 of the KTCP Act
  • Approved Building/Plotting Plan
  • Approved Layout Plan
  • Approved Section Of Building/Infrastructure Plan of Plotting
  • Area Development Plan Of Project Area
  • Bangalore Urban Arts Commission
  • BESCOM
  • BMRCL
  • Brochure of Current Project
  • BSNL
  • Certificate from Registered Engineer indicating the structural safety of the building (for Apartments)
  • Coastal Regulation Zone Authority
  • Commencement Certificate
  • Conversion Certificate under Sec 95 of the KLR Act 1961
  • Declaration (Form B)
  • Dist Magistrate
  • Encumbrance Certificate

Location

About Srikara Urban Park

Multi-Storied Residential Apartment comprises of 126 units

Type
Residential/Group Housing
Status
Nearing Handover
No. of Towers
2
No. of Floors
4
Handover Date
31 Mar 2027
RERA No.
PRM/KA/RERA/1251/308/PR/210331/004075
Location
Anekal, Bangalore

Srikara Urban Park: questions answered

Where is Srikara Urban Park located?

The Karnataka RERA register places Srikara Urban Park in Anekal, Bengaluru Urban.

What is the RERA number of Srikara Urban Park?

The Karnataka RERA registration number of Srikara Urban Park is PRM/KA/RERA/1251/308/PR/210331/004075, approved on 31 Mar 2021.

When is Srikara Urban Park expected to be completed?

The proposed completion date filed on the register is 31 Mar 2027.

How big is Srikara Urban Park?

The register lists Srikara Urban Park with 2 towers.

What is the latest construction progress of Srikara Urban Park?

The quarterly report for Q2 2026-27, filed on 13 Oct 2026, shows construction 91% complete and 7 of 126 units booked.

Where does this information about Srikara Urban Park come from?

From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.

Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.