Skip to main content
PropSarathi

Registered Project

Under Construction

BARMECHA PROPERTIES

Sparkle Atmos

Converted Sy No 42/1 and 42/3 situated at Kammasandra Agrahara Village, Kasaba Hobli Anekal Taluk, Anekal, Bengaluru Urban, Karnataka - 562106

Total Units
126
Floors
10
Towers
2
Total Area
2.07 Acres
Handover
31 Dec 2028

RERA progress

Stage 3 of 4 · Under construction
  1. RERA applied(completed)
  2. RERA approved(completed)
  3. Under construction(current stage)
  4. Handover(upcoming)

RERA Approved

3 May 2025

PRM/KA/RERA/1251/308/PR/030525/007706

Est. Handover as per RERA

31 Dec 2028

Configurations & unit mix

2 and 3 BHK Flats126

The promoter's RERA report, Q2 2026-27, filed 15 Oct 2026, by its own types and totals, which don't line up with the rows above. Types listed more than once are added together: 1 BHK 0 of 4 available; 2.5 BHK 5 of 38 available; 3 BHK 21 of 84 available.

The register doesn't list prices, so none are shown here.

Latest quarterly report on the register

Construction progress

Construction complete30%

Quarter
Q2 2026-27
Filed on
15 Oct 2026
Units booked
100 of 126
Units available
26
Reports on file
4

Amenities

  • Electricity
  • CCTV Surveillance
  • Club House
  • Swimming Pool
  • Gym
  • Power Backup
  • Water and Sanitation

RERA & approvals

Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/308/PR/030525/007706)

Complaints on the register: 0 recorded on this project; 0 on the promoter's record, as shown on this registration

These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.

RERA registration
PRM/KA/RERA/1251/308/PR/030525/007706
Registered as
SPARKLE ATMOS
Promoter
BARMECHA PROPERTIES
Acknowledgement no.
ACK/KA/RERA/1251/308/PR/180325/009043
Status on the register
New Project Launch
Stage
Under Construction
Work stage
30% complete, Q2 2026-27 report filed 15 Oct 2026
Sales status
Ongoing Sales (per RERA QPR Q2 2026-27, as of 15 Oct 2026)
RERA approved on
3 May 2025
Proposed completion
31 Dec 2028
Land area
2.07 acres (8,397 sq m)
Towers (this registration)
2
Floors (this registration)
10
Units (this registration)
126
Plan approved by
Anekal Planning Authority
Approved plan no.
CC/1053/2024-25
Plan approval date
1 Mar 2025
Land use
Residential

Dates on the register

Completion filed with RERA
31 Dec 2028 (Karnataka RERA)
Latest construction report
30% complete, Q2 2026-27, filed 15 Oct 2026 (promoter's report to RERA)

This is the date on the register now, and it may have been extended since registration.

We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.

Documents

Also filed on the register. We open a file here only after checking it for personal or financial details:

  • Commencement Certificate
  • Approved Building Plan
  • Sectional Drawing of the apartments
  • Certificate from Registered Engineer indicating the structural safety of the building
  • Proforma of Agreement for Sale
  • Declaration (Form B)
  • Advocate Search Report
  • ESCOM/Electricity
  • KWSSB/Water
  • KSPCB
  • SEIAA
  • Fire Force Department
  • Airport Authority of India
  • BSNL
  • Lift Authorities
  • BMRCL
  • NOC in case of building proposals abutting to neighbouring properties
  • Bangalore Urban Arts Commission
  • Inspector Of Factories Controller Of Explosives Railways
  • Coastal Regulation Zone Authority

Location

About Sparkle Atmos

RESIDENTIAL APARTMENT BUILDING.

Developer
BARMECHA PROPERTIES
Project Type
Residential/Group Housing
Type
Apartment
Status
Under Construction
Total Land
2.07 Acres
No. of Towers
2
No. of Floors
10
Total Units
126
Handover Date
31 Dec 2028
RERA No.
PRM/KA/RERA/1251/308/PR/030525/007706
Location
Anekal, Bangalore

About the developer

BARMECHA PROPERTIES

Promoter on the register
BARMECHA PROPERTIES
Projects on the register
1
Registering since
2025
Complaints on the promoter
0, as shown on this registration

Sparkle Atmos: questions answered

Where is Sparkle Atmos located?

The Karnataka RERA register places Sparkle Atmos in Anekal, Bengaluru Urban.

What is the RERA number of Sparkle Atmos?

The Karnataka RERA registration number of Sparkle Atmos is PRM/KA/RERA/1251/308/PR/030525/007706, approved on 3 May 2025.

Who is the promoter of Sparkle Atmos?

The promoter filed on the Karnataka RERA register is BARMECHA PROPERTIES.

When is Sparkle Atmos expected to be completed?

The proposed completion date filed on the register is 31 Dec 2028.

How big is Sparkle Atmos?

The register lists Sparkle Atmos with 126 units, 2 towers and about 2.07 acres of land.

What is the latest construction progress of Sparkle Atmos?

The quarterly report for Q2 2026-27, filed on 15 Oct 2026, shows construction 30% complete and 100 of 126 units booked.

Where does this information about Sparkle Atmos come from?

From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.

Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.