Sai Lakshmi Layout

Sy No. 32/3, 35, 36/2 at Anekal Gramantara, Kasaba Hobli, Anekal Taluk, Bangalore Urban District, Anekal, Bengaluru Urban, Karnataka - 562106

Total Plots
44
Total Area
2.84 Acres
Handover
1 Apr 2028

RERA progress

Stage 3 of 4 · Under construction
  1. RERA applied(completed)
  2. RERA approved(completed)
  3. Under construction(current stage)
  4. Handover(upcoming)

RERA Approved

22 Sep 2023

PRM/KA/RERA/1251/308/PR/220923/006284

Est. Handover as per RERA

1 Apr 2028

Configurations & unit mix

9.14 X 13.76 SITES5about 1,354 sq ft each
CA1about 6,200 sq ft each
9.14 X 15.24 SITES11about 1,499 sq ft each
Park1about 12,551 sq ft each
ODD SITES18about 1,811 sq ft each
9.14 X 12.19 SITES10about 1,199 sq ft each
Road6about 6,168 sq ft each

The register doesn't list prices, so none are shown here.

Latest quarterly report on the register

Construction progress

Construction complete96%

Quarter
Q1 2026-27
Filed on
14 Jul 2026
Reports on file
3

RERA & approvals

Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/308/PR/220923/006284)

Complaints on the register: 0 recorded on this project; the promoter's count isn't shown here, so check the register

These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.

RERA registration
PRM/KA/RERA/1251/308/PR/220923/006284
Registered as
SAI LAKSHMI LAYOUT
Acknowledgement no.
ACK/KA/RERA/1251/308/PR/010923/007409
Status on the register
Ongoing
Stage
Under Construction
Work stage
96% complete, Q1 2026-27 report filed 14 Jul 2026
RERA approved on
22 Sept 2023
Proposed completion
1 Apr 2028
Land area
2.84 acres (11,483 sq m)
Plots (this registration)
44
Plan approved by
Local Planing Authority
Approved plan no.
LAO/11/2022-23
Plan approval date
13 Feb 2023
Land use
Residential

Dates on the register

Completion filed with RERA
1 Apr 2028 (Karnataka RERA)
Latest construction report
96% complete, Q1 2026-27, filed 14 Jul 2026 (promoter's report to RERA)

This is the date on the register now, and it may have been extended since registration.

We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.

Documents

Also filed on the register. We open a file here only after checking it for personal or financial details:

  • Commencement Certificate
  • Electricity Permission Letter
  • Water Permission Letter
  • Approved Layout Plan
  • Approved Building/Plotting Plan
  • Existing Layout Plan
  • Existing Section Plan and Specification
  • Project Specifications
  • Area Development Plan Of Project Area
  • Advocate Search Report
  • Conversion Certificate under section 95 of the KLR Act 1964
  • Any other document (Rights/Title/Interest/Name)
  • Proforma of Agreement for Sale
  • Proforma of Allotment Letter
  • Brochure
  • Declaration (Form B)
  • ESCOM/Electricity
  • KWSSB/Water
  • Approval/NOC under section 109 of KLR Act 1961
  • Approval/NOC under section 14 of the KTCP Act

Location

About Sai Lakshmi Layout

Development of the plots situated at Sy No 32/3, 35, 36/2 in Anekal Village, Kasaba Hobli, Anekal Taluk, Bangalore Urban District, Karnataka - 562106

Project Type
Plotted Development
Type
Plotted Development
Status
Under Construction
Total Land
2.84 Acres
Total Plots
44
Handover Date
1 Apr 2028
RERA No.
PRM/KA/RERA/1251/308/PR/220923/006284
Location
Anekal, Bangalore

Sai Lakshmi Layout: questions answered

Where is Sai Lakshmi Layout located?

The Karnataka RERA register places Sai Lakshmi Layout in Anekal, Bengaluru Urban.

What is the RERA number of Sai Lakshmi Layout?

The Karnataka RERA registration number of Sai Lakshmi Layout is PRM/KA/RERA/1251/308/PR/220923/006284, approved on 22 Sept 2023.

When is Sai Lakshmi Layout expected to be completed?

The proposed completion date filed on the register is 1 Apr 2028.

How big is Sai Lakshmi Layout?

The register lists Sai Lakshmi Layout with 44 plots and about 2.84 acres of land.

What is the latest construction progress of Sai Lakshmi Layout?

The quarterly report for Q1 2026-27, filed on 14 Jul 2026, shows construction 96% complete.

Where does this information about Sai Lakshmi Layout come from?

From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.

Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.