Registered Project
Under ConstructionRainbow Mayfair
SY NO 41/4, AND SY NO 43/1, HULLAHALLI VILLAGE, JIGANI HOBLI, Anekal, Bengaluru Urban, Karnataka - 560083
- Total Units
- 62
- Floors
- 4
- Towers
- 1
- Total Area
- 3.73 Acres
- Handover
- 31 Jan 2030
RERA progress
Stage 3 of 4 · Under construction- RERA applied(completed)
- RERA approved(completed)
- Under construction(current stage)
- Handover(upcoming)
RERA Approved
19 Mar 2025
PRM/KA/RERA/1251/308/PR/190325/007593
Est. Handover as per RERA
31 Jan 2030
Configurations & unit mix
| 4 BHK | 48 | 36 of 48 | 3,000 – 3,179 sq ft |
|---|---|---|---|
| 5 BHK | 14 | 13 of 14 | 3,574 – 3,663 sq ft |
Available from the promoter's RERA report, Q2 2026-27, filed 15 Oct 2026.
The register doesn't list prices, so none are shown here.
Latest quarterly report on the register
Construction progress
Construction complete27%
- Quarter
- Q2 2026-27
- Filed on
- 15 Oct 2026
- Units booked
- 13 of 62
- Units available
- 49
- Reports on file
- 4
Amenities
- Electricity
- Club House
- Swimming Pool
RERA & approvals
Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/308/PR/190325/007593)
Complaints on the register: 0 recorded on this project; the promoter's count isn't shown here, so check the register
These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.
- RERA registration
- PRM/KA/RERA/1251/308/PR/190325/007593
- Registered as
- RAINBOW MAYFAIR
- Acknowledgement no.
- ACK/KA/RERA/1251/308/PR/190225/008970
- Status on the register
- New Project Launch
- Stage
- Under Construction
- Work stage
- 27% complete, Q2 2026-27 report filed 15 Oct 2026
- Sales status
- Ongoing Sales (per RERA QPR Q2 2026-27, as of 15 Oct 2026)
- RERA approved on
- 19 Mar 2025
- Proposed completion
- 31 Jan 2030
- Land area
- 3.73 acres (15,075 sq m)
- Towers (this registration)
- 1
- Floors (this registration)
- 4
- Units (this registration)
- 62
- Plan approved by
- BDA - Bangalore Development Authority
- Approved plan no.
- 115/2024-25
- Plan approval date
- 31 Dec 2024
- Land use
- Residential
Dates on the register
- Completion filed with RERA
- 31 Jan 2030 (Karnataka RERA)
- Latest construction report
- 27% complete, Q2 2026-27, filed 15 Oct 2026 (promoter's report to RERA)
This is the date on the register now, and it may have been extended since registration.
We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.
Documents
Also filed on the register. We open a file here only after checking it for personal or financial details:
- Commencement Certificate
- Approved Building Plan
- Brochure
- Proforma of Agreement for Sale
- Proforma of Allotment Letter
- Declaration (Form B)
- Advocate Search Report
- ESCOM/Electricity
- KWSSB/Water
- KSPCB
- SEIAA
- Form-4 certificate (Chartered Accountant)
- Form-5 certificate (Architect)
- Form-6 certificate (Structural Engineer)
Location
About Rainbow Mayfair
REAL ESTATE DEVELOPMENT
- Project Type
- Residential/Group Housing
- Type
- Row Houses
- Status
- Under Construction
- Total Land
- 3.73 Acres
- No. of Towers
- 1
- No. of Floors
- 4
- Total Units
- 62
- Handover Date
- 31 Jan 2030
- RERA No.
- PRM/KA/RERA/1251/308/PR/190325/007593
- Location
- Anekal, Bangalore
Rainbow Mayfair: questions answered
Where is Rainbow Mayfair located?
The Karnataka RERA register places Rainbow Mayfair in Anekal, Bengaluru Urban.
What is the RERA number of Rainbow Mayfair?
The Karnataka RERA registration number of Rainbow Mayfair is PRM/KA/RERA/1251/308/PR/190325/007593, approved on 19 Mar 2025.
When is Rainbow Mayfair expected to be completed?
The proposed completion date filed on the register is 31 Jan 2030.
How big is Rainbow Mayfair?
The register lists Rainbow Mayfair with 62 units, 1 tower and about 3.73 acres of land.
What is the latest construction progress of Rainbow Mayfair?
The quarterly report for Q2 2026-27, filed on 15 Oct 2026, shows construction 27% complete and 13 of 62 units booked.
Where does this information about Rainbow Mayfair come from?
From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.
Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.