Skip to main content
PropSarathi

Registered Project

Under Construction

R K Cortina

Sy No 5/2B, 5/3B, 5/4B, 7 and 8/4 Chikkadasarahalli Village, Sarjapura Hobli, Anekal Taluk, Anekal, Bengaluru Urban, Karnataka - 562125

Total Plots
99
Total Area
5.87 Acres
Handover
31 Dec 2027

RERA progress

Stage 3 of 4 · Under construction
  1. RERA applied(completed)
  2. RERA approved(completed)
  3. Under construction(current stage)
  4. Handover(upcoming)

RERA Approved

29 May 2025

PRM/KA/RERA/1251/308/PR/290525/007792

Est. Handover as per RERA

31 Dec 2027

Configurations & unit mix

9.14 M x 12.19 M49about 1,199 sq ft each
9.14 M x 18.29 M8about 1,799 sq ft each
9.14 M x 15.24 M5about 1,498 sq ft each
Odd Plots Size37about 1,398 sq ft each

The register doesn't list prices, so none are shown here.

Latest quarterly report on the register

Construction progress

Construction complete95%

Quarter
Q1 2026-27
Filed on
15 Jul 2026
Reports on file
3

RERA & approvals

Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/308/PR/290525/007792)

Complaints on the register: 0 recorded on this project; the promoter's count isn't shown here, so check the register

These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.

RERA registration
PRM/KA/RERA/1251/308/PR/290525/007792
Registered as
R K CORTINA
Acknowledgement no.
ACK/KA/RERA/1251/308/PR/300425/009179
Status on the register
Ongoing
Stage
Under Construction
Work stage
95% complete, Q1 2026-27 report filed 15 Jul 2026
RERA approved on
29 May 2025
Proposed completion
31 Dec 2027
Land area
5.87 acres (23,775 sq m)
Plots (this registration)
99
Plan approved by
Anekal Planning Authority
Approved plan no.
APA/LAO/27/2024-25
Plan approval date
17 Jan 2025
Land use
Residential

Dates on the register

Completion filed with RERA
31 Dec 2027 (Karnataka RERA)
Latest construction report
95% complete, Q1 2026-27, filed 15 Jul 2026 (promoter's report to RERA)

This is the date on the register now, and it may have been extended since registration.

We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.

Documents

Also filed on the register. We open a file here only after checking it for personal or financial details:

  • Approval Layout Order / Technical Sanction Letter
  • Approved Layout Plan/Demarcation Plan
  • Project Specifications
  • Relinquishment Deed
  • Proforma of Agreement for Sale
  • Proforma of Allotment Letter
  • Declaration (Form B)
  • Advocate Search Report
  • NOC from ESCOMs
  • NOC for Water
  • KSPCB (If Applicable)
  • SEIAA (If Applicable)
  • Form-4 certificate (Chartered Accountant)
  • Form-6 certificate (Structural Engineer)

Location

About R K Cortina

To Develop 99 No of Residential Plots Situated at Sy No 5/2B, 5/3B, 5/4B, 7 and 8/4 Chikkadasarahalli Village, Sarjapura Hobli, Anekal Taluk 562125

Project Type
Plotted Development
Type
Plotted Development
Status
Under Construction
Total Land
5.87 Acres
Total Plots
99
Handover Date
31 Dec 2027
RERA No.
PRM/KA/RERA/1251/308/PR/290525/007792
Location
Anekal, Bangalore

R K Cortina: questions answered

Where is R K Cortina located?

The Karnataka RERA register places R K Cortina in Anekal, Bengaluru Urban.

What is the RERA number of R K Cortina?

The Karnataka RERA registration number of R K Cortina is PRM/KA/RERA/1251/308/PR/290525/007792, approved on 29 May 2025.

When is R K Cortina expected to be completed?

The proposed completion date filed on the register is 31 Dec 2027.

How big is R K Cortina?

The register lists R K Cortina with 99 plots and about 5.87 acres of land.

What is the latest construction progress of R K Cortina?

The quarterly report for Q1 2026-27, filed on 15 Jul 2026, shows construction 95% complete.

Where does this information about R K Cortina come from?

From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.

Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.