Registered Project
Nearing HandoverRegistered project (name under review)
Anekal, Bangalore
- Total Units
- 84
- Floors
- 2
- Towers
- 1
- Total Area
- 4.6 Acres
- Handover
- 31 Dec 2026
RERA progress
Stage 2 of 4 · RERA approved- RERA applied(completed)
- RERA approved(current stage)
- Under construction(upcoming)
- Handover(upcoming)
RERA Approved
21 Mar 2024
PRM/KA/RERA/1251/308/PR/210324/006708
Est. Handover as per RERA
31 Dec 2026
Configurations & unit mix
| 3BHK FLATS | 84 |
|---|
The promoter's RERA report, Q1 2026-27, filed 15 Jul 2026, by its own types and totals, which don't line up with the rows above. Types listed more than once are added together: 3 BHK G+2 67 of 84 available.
The register doesn't list prices, so none are shown here.
Latest quarterly report on the register
Construction progress
Construction complete82%
- Quarter
- Q1 2026-27
- Filed on
- 15 Jul 2026
- Units booked
- 17 of 84
- Units available
- 67
- Reports on file
- 3
Amenities
- Electricity
- CCTV Surveillance
- Swimming Pool
- Gym
- Parks
- Power Backup
- Piped Gas
- Water and Sanitation
RERA & approvals
Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/308/PR/210324/006708)
Complaints on the register: 0 recorded on this project; the promoter's count isn't shown here, so check the register
These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.
- RERA registration
- PRM/KA/RERA/1251/308/PR/210324/006708
- Acknowledgement no.
- ACK/KA/RERA/1251/308/PR/020722/006105
- Status on the register
- New Project Launch
- Stage
- Nearing Handover
- Work stage
- 82% complete, Q1 2026-27 report filed 15 Jul 2026
- Sales status
- Ongoing Sales (per RERA QPR Q1 2026-27, as of 15 Jul 2026)
- RERA approved on
- 21 Mar 2024
- Proposed completion
- 31 Dec 2026
- Land area
- 4.6 acres (18,616 sq m)
- Towers (this registration)
- 1
- Floors (this registration)
- 2
- Units (this registration)
- 84
- Plan approved by
- Local Planing Authority
- Plan approval date
- 1 Jun 2018
- Land use
- Residential
Dates on the register
- Completion filed with RERA
- 31 Dec 2026 (Karnataka RERA)
- Latest construction report
- 82% complete, Q1 2026-27, filed 15 Jul 2026 (promoter's report to RERA)
This is the date on the register now, and it may have been extended since registration.
We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.
Documents
Also filed on the register. We open a file here only after checking it for personal or financial details:
- Declaration (Form B)
- ESCOM/Electricity
- KWSSB/Water
- Approval/NOC under section 109 of KLR Act 1961
- Approval/NOC under section 14 of the KTCP Act
- Fire Force Department
- Airport Authority of India
- KSPCB
- SEIAA
- BSNL
- Lift Authorities
- BMRCL
- NOC in case of building proposals abutting to neighbouring properties
- Bangalore Urban Arts Commission
- Inspector Of Factories Controller Of Explosives Railways
- Coastal Regulation Zone Authority
- Utilisation certificate
- Transfer of development rights certificate
- Relinquishment Deed
- Form-4 certificate (Chartered Accountant)
Location
About Registered project (name under review)
- Project Type
- Residential/Group Housing
- Type
- Apartment
- Status
- Nearing Handover
- Total Land
- 4.6 Acres
- No. of Towers
- 1
- No. of Floors
- 2
- Total Units
- 84
- Handover Date
- 31 Dec 2026
- RERA No.
- PRM/KA/RERA/1251/308/PR/210324/006708
- Location
- Anekal, Bangalore
Registered project (name under review): questions answered
Where is Registered project (name under review) located?
The Karnataka RERA register places Registered project (name under review) in Anekal, Bengaluru Urban.
What is the RERA number of Registered project (name under review)?
The Karnataka RERA registration number of Registered project (name under review) is PRM/KA/RERA/1251/308/PR/210324/006708, approved on 21 Mar 2024.
When is Registered project (name under review) expected to be completed?
The proposed completion date filed on the register is 31 Dec 2026.
How big is Registered project (name under review)?
The register lists Registered project (name under review) with 84 units, 1 tower and about 4.6 acres of land.
What is the latest construction progress of Registered project (name under review)?
The quarterly report for Q1 2026-27, filed on 15 Jul 2026, shows construction 82% complete and 17 of 84 units booked.
Where does this information about Registered project (name under review) come from?
From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.
Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.