Skip to main content
PropSarathi

Registered Project

Nearing Handover

Amaravathi Builders

Registered project (name under review)

Anekal, Bangalore

Total Units
32
Floors
4
Towers
1
Total Area
0.4 Acres
Handover
15 Jan 2027

RERA progress

Stage 2 of 4 · RERA approved
  1. RERA applied(completed)
  2. RERA approved(current stage)
  3. Under construction(upcoming)
  4. Handover(upcoming)

RERA Approved

10 Sep 2025

PRM/KA/RERA/1251/308/PR/100925/008082

Est. Handover as per RERA

15 Jan 2027

Configurations & unit mix

3 BHK2424 of 24862 – 1,075 sq ft
2 BHK88 of 8695 – 812 sq ft

Available from the promoter's RERA report, Q2 2026-27, filed 15 Oct 2026.

The register doesn't list prices, so none are shown here.

Latest quarterly report on the register

Construction progress

Construction complete84%

Quarter
Q2 2026-27
Filed on
15 Oct 2026
Units booked
0 of 32
Units available
32
Reports on file
4

Amenities

  • Electricity
  • CCTV Surveillance
  • Water and Sanitation

RERA & approvals

Source: Karnataka RERA, read 28 Oct 2026. Verify on the register (search PRM/KA/RERA/1251/308/PR/100925/008082)

Complaints on the register: 0 recorded on this project; 0 on the promoter's record, as shown on this registration

These are counts only; they don't show what a complaint was about or how it ended. No count here is a clean record. The register copy we hold has no field for court cases, so ask your lawyer to check those.

RERA registration
PRM/KA/RERA/1251/308/PR/100925/008082
Promoter
Amaravathi Builders
Acknowledgement no.
ACK/KA/RERA/1251/308/PR/290725/009470
Status on the register
Ongoing
Stage
Nearing Handover
Work stage
84% complete, Q2 2026-27 report filed 15 Oct 2026
Sales status
Ongoing Sales (per RERA QPR Q2 2026-27, as of 15 Oct 2026)
RERA approved on
10 Sept 2025
Proposed completion
15 Jan 2027
Land area
0.4 acres (1,615 sq m)
Towers (this registration)
1
Floors (this registration)
4
Units (this registration)
32
Plan approved by
Anekal Planning Authority
Approved plan no.
APA/CC/726/2023-24
Plan approval date
22 Feb 2024
Land use
Residential

Dates on the register

Completion filed with RERA
15 Jan 2027 (Karnataka RERA)
Latest construction report
84% complete, Q2 2026-27, filed 15 Oct 2026 (promoter's report to RERA)

This is the date on the register now, and it may have been extended since registration.

We don't show a developer delay record: our copy of the register doesn't hold what would make one accurate. Ask the developer for handover dates on its past projects. Source: Karnataka RERA.

Documents

Also filed on the register. We open a file here only after checking it for personal or financial details:

  • Commencement Certificate
  • Approved Building Plan
  • Sectional Drawing of the apartments
  • Certificate from Registered Engineer indicating the structural safety of the building
  • Project Specifications
  • Brochure
  • Relinquishment Deed
  • Proforma of Agreement for Sale
  • Proforma of Allotment Letter
  • Declaration (Form B)
  • Advocate Search Report
  • ESCOM/Electricity
  • KWSSB/Water
  • KSPCB
  • SEIAA
  • Fire Force Department
  • Airport Authority of India
  • BSNL
  • Lift Authorities
  • BMRCL

Location

About Registered project (name under review)

Developer
Amaravathi Builders
Project Type
Residential/Group Housing
Type
Apartment
Status
Nearing Handover
Total Land
0.4 Acres
No. of Towers
1
No. of Floors
4
Total Units
32
Handover Date
15 Jan 2027
RERA No.
PRM/KA/RERA/1251/308/PR/100925/008082
Location
Anekal, Bangalore

About the developer

Amaravathi Builders

Promoter on the register
Amaravathi Builders
Projects on the register
1
Registering since
2025
Complaints on the promoter
0, as shown on this registration

Registered project (name under review): questions answered

Where is Registered project (name under review) located?

The Karnataka RERA register places Registered project (name under review) in Anekal, Bengaluru Urban.

What is the RERA number of Registered project (name under review)?

The Karnataka RERA registration number of Registered project (name under review) is PRM/KA/RERA/1251/308/PR/100925/008082, approved on 10 Sept 2025.

Who is the promoter of Registered project (name under review)?

The promoter filed on the Karnataka RERA register is Amaravathi Builders.

When is Registered project (name under review) expected to be completed?

The proposed completion date filed on the register is 15 Jan 2027.

How big is Registered project (name under review)?

The register lists Registered project (name under review) with 32 units, 1 tower and about 0.4 acres of land.

What is the latest construction progress of Registered project (name under review)?

The quarterly report for Q2 2026-27, filed on 15 Oct 2026, shows construction 84% complete and 0 of 32 units booked.

Where does this information about Registered project (name under review) come from?

From the public Karnataka RERA register, read on 28 Oct 2026. You can check it at rera.karnataka.gov.in.

Data from the Karnataka RERA register, read 28 Oct 2026. Check it on rera.karnataka.gov.in before you decide.